New home permits in the City of Gainesville, FL

Data through July 2026 · updated 19 Oct 2026

376 new home permits were issued in the City of Gainesville, August 2024 through July 2026: about 188 a year and 2% of all permits. 184 new home permits in the last 12 months on file (Aug 2025–Jul 2026), 4% fewer than the 192 in the 12 months before. The busiest month is March. The usual one took 165 days from issue to the city's final. 32608 has the most, 123.

376permits issued
184last 12 months on file
Marbusiest month
165days, usual issue to final
87%finished
Jul 2026records through

New home permits by month

Permits issued each month, August 2024 through July 2026.

Aug 2024: 18Aug2024Sep 2024: 9Oct 2024: 13Nov 2024: 3Dec 2024: 8Jan 2025: 14Jan2025Feb 2025: 17Mar 2025: 47Apr 2025: 20May 2025: 13Jun 2025: 16Jul 2025: 14JulAug 2025: 10Sep 2025: 10Oct 2025: 19Nov 2025: 20Dec 2025: 12Jan 2026: 32Jan2026Feb 2026: 10Mar 2026: 24Apr 2026: 21May 2026: 9Jun 2026: 10Jul 2026: 7Jul
The same numbers as a table
MonthPermits
Aug 202418
Sep 20249
Oct 202413
Nov 20243
Dec 20248
Jan 202514
Feb 202517
Mar 202547
Apr 202520
May 202513
Jun 202516
Jul 202514
Aug 202510
Sep 202510
Oct 202519
Nov 202520
Dec 202512
Jan 202632
Feb 202610
Mar 202624
Apr 202621
May 20269
Jun 202610
Jul 20267

Download this table (CSV)

When new home permits are filed

By calendar month, 100 = an average month (the thin line). March is the busiest (227), September the quietest (61). A busy month at the permit counter usually means a longer wait for a contractor.

January: 147 (100 = an average month)February: 86 (100 = an average month)March: 227 (100 = an average month)227April: 131 (100 = an average month)May: 70 (100 = an average month)June: 83 (100 = an average month)July: 67 (100 = an average month)August: 89 (100 = an average month)September: 61 (100 = an average month)October: 102 (100 = an average month)November: 73 (100 = an average month)December: 64 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January147
February86
March227
April131
May70
June83
July67
August89
September61
October102
November73
December64

Download this table (CSV)

How long a new home permit takes

Permits issued Aug 2024–Jul 2025, at least 12 months before the file ends. Usual days is the middle permit among the 162 with a final date.

MeasureValue
Permits issued Aug 2024–Jul 2025192
Finished87.0%
Expired0.0%
Usual days, issue to final165
Middle half, days135–270

Download this table (CSV)

ZIP codes with the most new home permits

Counted at the property's ZIP code. Share is the part of the city's 376 new home permits.

ZIP codePermitsShare
3260812333%
326536818%
326076116%
326014111%
326414011%
32605164%
32609154%
32603123%

Download this table (CSV)

The city's own permit types

How the city filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
Building: New Construction36597%
Building: Manufactured Home (HUD)82%
Building: Foundation Only3under 1%

Download this table (CSV)

How Gainesville compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

Nearby permit data

New home permits for other places in Gainesville. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: City of Gainesville, Gainesville Permit Cases (ArcGIS Online, table All_Permit_Cases), read 19 Oct 2026. We count permits issued August 2024 through July 2026; denied and withdrawn permits are left out.

Building and trade permits the City of Gainesville issues inside city limits. Unincorporated Alachua County and the other towns in the county (Alachua, High Springs, Newberry and others) have their own permit offices and are not in this file.

  • The file names no contractor company (only the license holder's personal name), so there are no contractor lists, rankings or firm pages here.
  • The file has no declared job value, so we show no costs.
  • The city loaded this permit table once, on July 31, 2026, and it has not been updated since, so the window ends in July 2026.
  • Each trade on a job gets its own permit: a new house usually has a building permit plus separate electrical, mechanical, plumbing and gas permits. Those trade permits are counted under their trade.
  • A final date is the date the city closed the permit. Homes versus other property comes from the parcel's land-use code on the county tax roll, and the ZIP code from the same roll.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "New home permits in the City of Gainesville, FL", https://contractorrecords.com/gainesville/new-home-permits, data through July 2026, from the City of Gainesville Building Division building-permit records.

Link to a table: By month · Season · Days to final · By ZIP code · Permit types.

Download the tables (CSV): New homes permits by month · New homes permits by calendar month (index) · New homes permits: days to final · New homes permits by ZIP code · New homes permits by permit type.

Common questions

  • How many new home permits does Gainesville issue a year?About 188 a year in the City of Gainesville: 376 permits issued August 2024 through July 2026, 184 of them in the last 12 months on file (to July 2026).
  • How long does a new home permit take in Gainesville?The usual one took 165 days from issue to the city's final inspection, and the middle half took 135 to 270 days (162 permits issued Aug 2024–Jul 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Gainesville file the most new home permits?March (227 against an average month of 100); September is the quietest (61). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.
  • Which ZIP code has the most new home permits in Gainesville?32608, with 123 of the 376 (33%); then 32653 (68).