Contractor Records
Home › Guides › Do I need an electrical permit in Orlando? The ELE permit, the owner exemption, fees and inspections

Do I need an electrical permit in Orlando? The ELE permit, the owner exemption, fees and inspections

Yes: Orlando requires an electrical permit for new wiring, circuits, panels, service changes, EV chargers and solar, and Florida's new under-$7,500 permit exemption leaves electrical work out entirely. The City issued 7,076 electrical permits on homes from October 2023 to September 2026; the usual one was filed at $2,700 and took 127 days to reach final.

By Contractor Records · data through October 17, 2026

The Orlando rule

The City's electrical permit application (updated 12/24, read 23 October 2026) lists the work it covers: addition, alteration, change of service, new, repair ("restoring existing equipment and materials with new equipment and materials in the same location"), solar, low voltage, safety check, swimming pool, temporary service, and EV charging stations by level. It adds: "Rewiring one or more rooms, or opening walls requires compliance with current code for the affected location(s)."

The City's HB803 exemption guide says "Electrical, plumbing, mechanical, or gas work" is "not eligible for exemption, regardless of cost", so the July 2026 state exemption does not reach any of it.

Job Permit route in Orlando
New circuit, outlets, lighting Electrical permit, "Alteration" or "Addition"
Panel replacement or service upgrade Electrical permit, "Change of Service" ($50 line on the fee schedule)
EV charger Electrical permit, EV charging station section
Rewiring a room or opening walls Electrical permit; the affected rooms must meet current code
Security alarm Low voltage permit plus the Low Voltage Security Alarm form
Wiring inside a remodel Electrical permit tied to the building permit number

Who can pull it

A Florida electrical contractor: DBPR's Electrical Contractors' Licensing Board licenses them, as statewide EC or local ER contractors. 95.5% of the 751 electrical firms on Orlando permits matched an active DBPR license in our file.

Or you, on your own home. § 489.503(6) exempts "an owner of property when acting as his or her own electrical contractor and providing all material supervision himself or herself" on a single-family or duplex residence for the owner's use and "not offered for sale or lease". The owner must "personally appear and sign the building permit application". The City's form also asks for a notarized owner signature when the work "IS NOT PART OF A PROJECT WITH AN ISSUED BUILDING PERMIT".

How to apply and what gets inspected

  1. Fill in the ELE application, including the fixture counts (receptacles, lights, switches) and the utility (OUC or Duke Energy), and email it to digitalpermits@orlando.gov.
  2. Notice of Commencement: the form says a job over $5,000 that is not part of a building permit needs a certified copy of the recorded notice "prior to scheduling your first inspection".
  3. Pay in the City's Permit Lookup tool.
  4. Inspections. Orlando's electrical inspection codes are 350 temporary service, 355 underground/slab, 200 rough-in, 135 above ceiling, 199 pre-power and 600 final.

The City's electrical checklist lists why residential inspections fail. The ones a homeowner can check: work "covered up without inspections", "No access to property", "Work outside scope of permit", missing GFCI protection, missing arc-fault protection for bedroom outlets, and a panel with no circuit directory.

What it costs

From the 2026 residential fee schedule:

Fee Amount
Electrical permit $66.24 for the first $1,000 of construction cost, plus $11.03 per additional $1,000 up to $25,000, then $8.28 per $1,000
Change of service $50
Safety check $50
Low voltage, residential $50
Technology surcharge 3% of the permit fee
Re-inspection (failed) $150
Work without a permit An additional 100% of the permit fee

Worked out from the schedule: a $3,000 job is $66.24 + 2 × $11.03 = $88.30, about $91 with the surcharge. The form says "Owner furnished equipment and materials must be included in Estimated Construction Cost", so a charger you bought yourself still counts. The City is reviewing fees after HB803; the invoice is the final word.

What 7,076 Orlando electrical permits show

Measure Orlando electrical
Permits on homes, October 2023 to September 2026 7,076
Firms 751
Firms with a permit in the last 12 months 446
Usual filed value $2,700
Middle half of firms' usual value (3+ permits) $1,800 to $7,000
Usual days from issue to final 127
Busiest / quietest month July (114) / September (81)
Share held by the busiest firm 16.9%

At 127 days, electrical permits are the slowest of Orlando's trade permits (new homes, additions and pools aside), about four times a roof permit's 27. Part of that is structure: an electrical permit on a remodel waits for the rest of the job. On a stand-alone panel or charger, a permit open for months usually means the final was never booked. One firm holds 16.9% of the city's electrical permits, so the citywide figures lean on its record. Prices by job size: Orlando electrical cost page.

See every Orlando electrician by days to final →

Next steps

Compare electricians on the Orlando electrical list and check the license in the Orlando contractor license lookup. Older permits on your address: Orlando building permit search; monthly counts: Orlando permit statistics. National prices: electrical work cost; other cities: do I need a permit for electrical work and for an electrical panel upgrade.

What this does not tell you

The file records permits issued in the City of Orlando, not work done without one. Almost every Orlando permit is eventually closed, so we show speed to final instead of a finished share. A final means the inspector passed the work; it says nothing about price.

How we know this

Work types, owner-signature rules, inspection codes and failure reasons are quoted from City of Orlando forms and checklists read 23 October 2026; fees from the residential schedule effective January 2026, with the worked example computed by us; the owner exemption from Florida Statutes § 489.503. Counts are City of Orlando permits on one- and two-family homes classified as electrical, October 2023 to September 2026; days to final are the median from issue; license status is our name match to DBPR.

Numbers come from City of Orlando building permits for one- and two-family homes, data through October 17, 2026. Nobody paid to be on this page and nobody can.

Questions

  • Do I need a permit for electrical work in Orlando?

    For new wiring, circuits, a panel or service change, an EV charger or solar, yes: each is a work type on the City's electrical permit application. Florida's new under-$7,500 exemption excludes electrical work 'regardless of cost'.

  • How much is an electrical permit in Orlando?

    The 2026 residential fee is $66.24 for the first $1,000 of construction cost plus $11.03 for each further $1,000 up to $25,000, and a 3% technology surcharge. A $3,000 job comes to $88.30, about $91 with the surcharge. A change of service and a safety check are $50 each.

  • Can a homeowner pull an electrical permit in Orlando?

    Yes, under Florida's owner exemption in § 489.503(6): an owner acting as their own electrical contractor on a single-family or duplex home for their own use. You must personally appear and sign the application, and the home may not be built or improved for sale or lease.

  • How long does an electrical permit take in Orlando?

    The usual Orlando electrical permit in our file reached final 127 days after issue, slower than plumbing, HVAC or roofing permits in the city; only new homes, additions and pools take longer.

  • Do I need a permit for an EV charger in Orlando?

    Yes. EV charging stations are a line on the City's electrical permit application, which asks for the number of stations and whether they are Level I, II or III.

Build your own list

Every firm with that kind of permit on record. Pick what you value. The list moves.