New home permits in Las Cruces, NM

Data through September 2026 · updated 20 Oct 2026

1,306 new home permits were issued in Las Cruces, October 2024 through September 2026: about 653 a year and 10% of all permits. 649 new home permits in the last 12 months (Oct 2025–Sep 2026), about the same as the 657 in the 12 months before. The busiest month is March. The usual one took 172 days from issue to the city's final.

1,306permits issued
649last 12 months
Marbusiest month
172days, usual issue to final
$300,000usual declared value
Sep 2026records through

New home permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 69Oct2024Nov 2024: 30Dec 2024: 60Jan 2025: 47Jan2025Feb 2025: 62Mar 2025: 62Apr 2025: 64May 2025: 48Jun 2025: 79Jul 2025: 65JulAug 2025: 41Sep 2025: 30Oct 2025: 33Nov 2025: 28Dec 2025: 36Jan 2026: 69Jan2026Feb 2026: 52Mar 2026: 79Apr 2026: 32May 2026: 53Jun 2026: 62Jul 2026: 67JulAug 2026: 52Sep 2026: 86
The same numbers as a table
MonthPermits
Oct 202469
Nov 202430
Dec 202460
Jan 202547
Feb 202562
Mar 202562
Apr 202564
May 202548
Jun 202579
Jul 202565
Aug 202541
Sep 202530
Oct 202533
Nov 202528
Dec 202536
Jan 202669
Feb 202652
Mar 202679
Apr 202632
May 202653
Jun 202662
Jul 202667
Aug 202652
Sep 202686

Download this table (CSV)

When new home permits are filed

By calendar month, 100 = an average month (the thin line). March is the busiest (130), November the quietest (53). A busy month at the permit counter usually means a longer wait for a contractor.

January: 107 (100 = an average month)February: 105 (100 = an average month)March: 130 (100 = an average month)130April: 88 (100 = an average month)May: 93 (100 = an average month)June: 130 (100 = an average month)July: 121 (100 = an average month)August: 85 (100 = an average month)September: 107 (100 = an average month)October: 94 (100 = an average month)November: 53 (100 = an average month)December: 88 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January107
February105
March130
April88
May93
June130
July121
August85
September107
October94
November53
December88

Download this table (CSV)

How long a new home permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 580 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 2025657
Usual days, issue to final172
Middle half, days148–209

Download this table (CSV)

What a new home permit is declared at

The value written on the permit at application, from 1,211 permits with one. Not a quote and not the final bill.

MeasureValue
Usual declared value$300,000
Middle half$160,302–$352,990

Download this table (CSV)

The city's own permit types

How the city filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
New (Residential)1,21193%
Mobile Home957%

Download this table (CSV)

Most active contractors by permits filed

The contractors named on the most new home permits in the City of Las Cruces GIS file, October 2024 through September 2026, with 5 or more each. Share is the part of all 1,306 new home permits; 86% of them name a contractor we can show. This is volume, not quality: more permits doesn't mean better work. Individuals' names, owner-builders and blanks are left out.

ContractorPermitsShare
Hakes Brothers Construction LLC35627%
Desert View Homes LLC15312%
French Brothers, Inc.14511%
KT Homes LLC1028%
Edwards Homes of New Mexico LLC917%
Lorenz Homes, LLC343%
Monarch Development LLC242%
Arista Development LLC171%
A New Begining Custom Homes, LLC161%
Beacon Homes12under 1%

Download this table (CSV)

How Las Cruces compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

How these numbers are made

Source: City of Las Cruces GIS, Information_Services map service (Accela feed): BuildingPermits and CertificateOFoccupancy layers, read 20 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out. The city's permit layer carries no permit status, and only building permits get a certificate of occupancy or completion in the public data, so no finished share is shown.

Building, trade, solar, fence, sign and demolition permits the City of Las Cruces issued inside the city limits. Right-of-way, paving, site-improvement and utility permits are left out. Unincorporated Doña Ana County is permitted by the county and is not in this file.

  • The city's permit layer has no status, so we show no finished share.
  • A final date is the date of the certificate of occupancy or certificate of completion the city issued for a building permit (new homes, additions, alterations); electrical, plumbing, mechanical, roofing and solar permits have none, so time to final is shown only for building work.
  • The value is the project valuation on the permit. The city records no value on electrical, plumbing and mechanical permits, so those are left unpriced.
  • Homes are the permits the city files under its Residential project class plus manufactured-home installations. Solar, fence, window and door, and sign permits carry no residential or commercial class, so they count as other property in the homes figures.
  • The layer gives a street address and map point but no ZIP code, so there are no ZIP pages.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "New home permits in Las Cruces, NM", https://contractorrecords.com/las-cruces/new-home-permits, data through September 2026, from City of Las Cruces Community Development building-permit records.

Link to a table: By month · Season · Days to final · Declared value · Permit types · Most active contractors by permits filed.

Download the tables (CSV): New homes permits by month · New homes permits by calendar month (index) · New homes permits: days to final · New homes permits: declared value · New homes permits by permit type · Most active contractors by permits filed.

Common questions

  • How many new home permits does Las Cruces issue a year?About 653 a year in Las Cruces: 1,306 permits issued October 2024 through September 2026, 649 of them in the last 12 months.
  • How long does a new home permit take in Las Cruces?The usual one took 172 days from issue to the city's final inspection, and the middle half took 148 to 209 days (580 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Las Cruces file the most new home permits?March (130 against an average month of 100); November is the quietest (53). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.