How long do permits take in Montgomery County, MD?

Data through September 2026 · updated 19 Oct 2026

The usual permit in Montgomery County takes 69 days from issue to the county's final inspection; the middle half take 26 to 144 days. That is from 22,323 permits issued Oct 2024–Sep 2025 that reached a final. Solar permits are quickest at 48 days; new home permits take longest at 222 days. This is the time to finish the work and close the permit, not the wait for approval.

69days, usual issue to final
26–144days, middle half
77%finished
22,323permits with a final date
Sep 2026records through

Getting the permit vs finishing the work: two different clocks

“How long does a permit take?” can mean two waits. This page measures the second one.

Getting the permit (not measured): application → issue, the wait for the county to approve the plans. Ask the county for its current review times.

Finishing the work (measured here): issue → final. From the day the county issued the permit to the day it recorded the final inspection. We count only permits issued Oct 2024–Sep 2025, at least 12 months before the file ends, so slow jobs have had time to finish; a permit still open is not in the days.

By kind of work

Permits issued Oct 2024–Sep 2025. Usual days is the middle permit among those with a final date: half finished sooner, half later. Middle half is the range the middle 50% fell in. Kinds of work with fewer than 100 permits in that period are left out.

Kind of workPermitsFinishedUsual days to finalMiddle half (days)
Electrical10,88079.5%6418–124
HVAC7,95073.2%5518–120
Solar3,78480.7%4829–83
Remodels & repairs1,21584.7%11968–196
Garages, sheds & shade structures1,26686.0%5028–111
Additions90681.0%186103–307
New homes93786.2%222175–283
Pools & spas14675.3%216147–319
Other1,56458.2%14182–229

Download this table (CSV)

How long each kind of permit takes

Each kind of work on its own, issue to the county's final.

How long does electrical work take in Montgomery County, from permit to final?

The usual electrical permit in Montgomery County takes 64 days from issue to final; the middle half take 18 to 124 days (8,653 permits with a final date, issued Oct 2024–Sep 2025). 80% of the 10,880 permits issued then have finished. Montgomery County electrical permits →

How long does an HVAC replacement take in Montgomery County, from permit to final?

The usual HVAC permit in Montgomery County takes 55 days from issue to final; the middle half take 18 to 120 days (5,818 permits with a final date, issued Oct 2024–Sep 2025). 73% of the 7,950 permits issued then have finished. Montgomery County HVAC permits →

How long does a solar installation take in Montgomery County, from permit to final?

The usual solar permit in Montgomery County takes 48 days from issue to final; the middle half take 29 to 83 days (3,052 permits with a final date, issued Oct 2024–Sep 2025). 81% of the 3,784 permits issued then have finished. Montgomery County solar permits →

How long does a remodel take in Montgomery County, from permit to final?

The usual remodel and repair permit in Montgomery County takes 119 days from issue to final; the middle half take 68 to 196 days (1,029 permits with a final date, issued Oct 2024–Sep 2025). 85% of the 1,215 permits issued then have finished. Montgomery County remodel and repair permits →

How long does a garage, shed or patio cover take in Montgomery County, from permit to final?

The usual garage, shed and shade structure permit in Montgomery County takes 50 days from issue to final; the middle half take 28 to 111 days (1,089 permits with a final date, issued Oct 2024–Sep 2025). 86% of the 1,266 permits issued then have finished. Montgomery County garage, shed and shade structure permits →

How long does a home addition take in Montgomery County, from permit to final?

The usual home addition permit in Montgomery County takes 186 days from issue to final; the middle half take 103 to 307 days (734 permits with a final date, issued Oct 2024–Sep 2025). 81% of the 906 permits issued then have finished. Montgomery County home addition permits →

How long does building a new home take in Montgomery County, from permit to final?

The usual new home permit in Montgomery County takes 222 days from issue to final; the middle half take 175 to 283 days (808 permits with a final date, issued Oct 2024–Sep 2025). 86% of the 937 permits issued then have finished. Montgomery County new home permits →

How long does a pool or spa take in Montgomery County, from permit to final?

The usual pool and spa permit in Montgomery County takes 216 days from issue to final; the middle half take 147 to 319 days (110 permits with a final date, issued Oct 2024–Sep 2025). 75% of the 146 permits issued then have finished. Montgomery County pool and spa permits →

How long does an ADU or casita take in Montgomery County, from permit to final?

The usual ADU and casita permit in Montgomery County takes 167 days from issue to final; the middle half take 85 to 307 days (62 permits with a final date, issued Oct 2024–Sep 2025). Montgomery County ADU and casita permits →

How Montgomery County compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

Nearby permit data

How long permits take for other places in Washington, DC. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: dataMontgomery: Residential Permit, Commercial Permits, Mechanical Permits and Electrical Building Permits (Department of Permitting Services), read 19 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Building, electrical and mechanical permits issued by the Montgomery County Department of Permitting Services, which covers the county outside the cities that run their own building offices: Silver Spring, Bethesda, Potomac, Germantown, Clarksburg, Chevy Chase, Olney, Wheaton, Takoma Park and the rest. The cities of Rockville and Gaithersburg issue most of their own building permits, so permits inside those cities are largely missing; a Rockville or Gaithersburg mailing address in this file is usually just outside those cities. Plumbing and gas-service permits are issued by WSSC Water, not the county, and are not in the file.

  • The county's files name no contractor, so there are no contractor lists, rankings or firm pages for Montgomery County.
  • Declared value is filled on building permits only; electrical and HVAC permits carry no job value, so costs are shown only for building work.
  • Plumbing permits are issued by WSSC Water, not the county, so plumbing barely appears here (a few gas-appliance jobs on mechanical permits).
  • Solar counts come from electrical permits whose description mentions solar or photovoltaic panels.
  • Decks count with garages and sheds. A final date is the county's final inspection date; a permit at Stop Work counts as open.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "How long do permits take in Montgomery County, MD?", https://contractorrecords.com/montgomery-county-md/how-long-does-a-permit-take, data through September 2026, from Montgomery County Department of Permitting Services building-permit records.

Link to a table: By kind of work · Each kind of permit.

Download the tables (CSV): Days to final by kind of work.

Common questions

  • What is the permit turnaround in Montgomery County?From issue to final inspection, the usual permit takes 69 days (middle half 26 to 144 days), from 22,323 permits issued Oct 2024–Sep 2025. The wait to get a permit issued is not in this file; ask the county for its current review times.
  • Which permits finish fastest in Montgomery County?Solar permits, at 48 days. The slowest are new home permits, at 222 days. Bigger jobs take longer; so does work where the final inspection is easy to forget.
  • How many permits actually get finished in Montgomery County?77% of the 28,829 permits issued Oct 2024–Sep 2025 have finished; the rest are still open (the file doesn't mark permits expired).
  • Why does an open permit matter to me?An unfinished permit stays with the property, not the contractor. It can hold up a sale or a refinance. Ask whoever does the work to call for the final inspection and show you the result.