Home addition permits in Philadelphia, PA

Data through September 2026 · updated 19 Oct 2026

847 home addition permits were issued in Philadelphia, October 2024 through September 2026: about 424 a year and 1% of all permits. 438 home addition permits in the last 12 months (Oct 2025–Sep 2026), 7% more than the 409 in the 12 months before. The busiest month is July. The usual one took 246 days from issue to the city's final. 19146 has the most, 111.

847permits issued
438last 12 months
Julbusiest month
246days, usual issue to final
58%finished
Sep 2026records through

Home addition permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 37Oct2024Nov 2024: 30Dec 2024: 29Jan 2025: 38Jan2025Feb 2025: 36Mar 2025: 24Apr 2025: 31May 2025: 44Jun 2025: 33Jul 2025: 38JulAug 2025: 37Sep 2025: 32Oct 2025: 38Nov 2025: 33Dec 2025: 29Jan 2026: 36Jan2026Feb 2026: 28Mar 2026: 50Apr 2026: 33May 2026: 40Jun 2026: 38Jul 2026: 47JulAug 2026: 30Sep 2026: 36
The same numbers as a table
MonthPermits
Oct 202437
Nov 202430
Dec 202429
Jan 202538
Feb 202536
Mar 202524
Apr 202531
May 202544
Jun 202533
Jul 202538
Aug 202537
Sep 202532
Oct 202538
Nov 202533
Dec 202529
Jan 202636
Feb 202628
Mar 202650
Apr 202633
May 202640
Jun 202638
Jul 202647
Aug 202630
Sep 202636

Download this table (CSV)

When home addition permits are filed

By calendar month, 100 = an average month (the thin line). July is the busiest (120), December the quietest (82). A busy month at the permit counter usually means a longer wait for a contractor.

January: 105 (100 = an average month)February: 91 (100 = an average month)March: 105 (100 = an average month)April: 91 (100 = an average month)May: 119 (100 = an average month)June: 101 (100 = an average month)July: 120 (100 = an average month)120August: 95 (100 = an average month)September: 96 (100 = an average month)October: 106 (100 = an average month)November: 89 (100 = an average month)December: 82 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January105
February91
March105
April91
May119
June101
July120
August95
September96
October106
November89
December82

Download this table (CSV)

How long a home addition permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 236 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 2025409
Finished57.9%
Expired6.4%
Usual days, issue to final246
Middle half, days149–350

Download this table (CSV)

ZIP codes with the most home addition permits

Counted at the property's ZIP code. Share is the part of the city's 847 home addition permits.

ZIP codePermitsShare
1914611113%
191478510%
19125627%
19148597%
19145314%
19134304%
19121293%
19118273%
19130273%
19119243%

Download this table (CSV)

How these numbers are made

Source: City of Philadelphia, Licenses and Inspections Building and Zoning Permits, 2007 to present (OpenDataPhilly; Carto table permits), read 19 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Residential permits the City of Philadelphia Department of Licenses and Inspections (L&I) issues inside the city, which is also Philadelphia County: building, plumbing, electrical, mechanical, EZ minor-work, demolition and solar permits for homes. Commercial permits, zoning and use permits, excavation and site permits, certificates of occupancy and event permits in the same file are not counted. Suburbs in Bucks, Montgomery and Delaware counties run their own permit offices and are not in this file.

  • The city's file lists a contractor on most permits, but these pages show permit counts only: there are no contractor lists, rankings or firm pages for Philadelphia.
  • We count residential permits only, as the city's file marks them; a home job filed as a commercial permit is not counted.
  • The city's open permit file has no declared job value, so we show no costs.
  • A new house gets separate building, plumbing, electrical and mechanical permits, so one project can count several times, once under each kind of work.
  • A final date is the day the city marked the permit completed. Permits that expired or were cancelled carry no final date even where the file shows one, because that date is when they lapsed.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Home addition permits in Philadelphia, PA", https://contractorrecords.com/philadelphia/addition-permits, data through September 2026, from the City of Philadelphia Department of Licenses and Inspections building-permit records.

Link to a table: By month · Season · Days to final · By ZIP code.

Download the tables (CSV): Additions permits by month · Additions permits by calendar month (index) · Additions permits: days to final · Additions permits by ZIP code.

Common questions

  • How many home addition permits does Philadelphia issue a year?About 424 a year in Philadelphia: 847 permits issued October 2024 through September 2026, 438 of them in the last 12 months.
  • How long does a home addition permit take in Philadelphia?The usual one took 246 days from issue to the city's final inspection, and the middle half took 149 to 350 days (236 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Philadelphia file the most home addition permits?July (120 against an average month of 100); December is the quietest (82). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.
  • Which ZIP code has the most home addition permits in Philadelphia?19146, with 111 of the 847 (13%); then 19147 (85).