Demolition permits in Philadelphia, PA

Data through September 2026 · updated 19 Oct 2026

621 demolition permits were issued in Philadelphia, October 2024 through September 2026: about 310 a year and 1% of all permits. 313 demolition permits in the last 12 months (Oct 2025–Sep 2026), about the same as the 308 in the 12 months before. The busiest month is May. The usual one took 32 days from issue to the city's final. 19132 has the most, 101.

621permits issued
313last 12 months
Maybusiest month
32days, usual issue to final
97%finished
Sep 2026records through

Demolition permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 22Oct2024Nov 2024: 11Dec 2024: 15Jan 2025: 26Jan2025Feb 2025: 25Mar 2025: 37Apr 2025: 32May 2025: 36Jun 2025: 21Jul 2025: 29JulAug 2025: 30Sep 2025: 24Oct 2025: 28Nov 2025: 25Dec 2025: 32Jan 2026: 33Jan2026Feb 2026: 17Mar 2026: 22Apr 2026: 18May 2026: 26Jun 2026: 29Jul 2026: 29JulAug 2026: 26Sep 2026: 28
The same numbers as a table
MonthPermits
Oct 202422
Nov 202411
Dec 202415
Jan 202526
Feb 202525
Mar 202537
Apr 202532
May 202536
Jun 202521
Jul 202529
Aug 202530
Sep 202524
Oct 202528
Nov 202525
Dec 202532
Jan 202633
Feb 202617
Mar 202622
Apr 202618
May 202626
Jun 202629
Jul 202629
Aug 202626
Sep 202628

Download this table (CSV)

When demolition permits are filed

By calendar month, 100 = an average month (the thin line). May is the busiest (120), November the quietest (70). A busy month at the permit counter usually means a longer wait for a contractor.

January: 114 (100 = an average month)February: 81 (100 = an average month)March: 114 (100 = an average month)April: 97 (100 = an average month)May: 120 (100 = an average month)120June: 97 (100 = an average month)July: 112 (100 = an average month)August: 108 (100 = an average month)September: 100 (100 = an average month)October: 97 (100 = an average month)November: 70 (100 = an average month)December: 91 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January114
February81
March114
April97
May120
June97
July112
August108
September100
October97
November70
December91

Download this table (CSV)

How long a demolition permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 298 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 2025308
Finished97.1%
Expired1.9%
Usual days, issue to final32
Middle half, days21–54

Download this table (CSV)

ZIP codes with the most demolition permits

Counted at the property's ZIP code. Share is the part of the city's 621 demolition permits.

ZIP codePermitsShare
1913210116%
191216310%
19140478%
19133447%
19134437%
19143376%
19139345%
19104315%
19144244%
19131213%

Download this table (CSV)

The city's own permit types

How the city filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
Demolition: City Demolition46074%
Demolition: Minor Demolition15124%
Demolition: Major Demolition102%

Download this table (CSV)

How these numbers are made

Source: City of Philadelphia, Licenses and Inspections Building and Zoning Permits, 2007 to present (OpenDataPhilly; Carto table permits), read 19 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Residential permits the City of Philadelphia Department of Licenses and Inspections (L&I) issues inside the city, which is also Philadelphia County: building, plumbing, electrical, mechanical, EZ minor-work, demolition and solar permits for homes. Commercial permits, zoning and use permits, excavation and site permits, certificates of occupancy and event permits in the same file are not counted. Suburbs in Bucks, Montgomery and Delaware counties run their own permit offices and are not in this file.

  • The city's file lists a contractor on most permits, but these pages show permit counts only: there are no contractor lists, rankings or firm pages for Philadelphia.
  • We count residential permits only, as the city's file marks them; a home job filed as a commercial permit is not counted.
  • The city's open permit file has no declared job value, so we show no costs.
  • A new house gets separate building, plumbing, electrical and mechanical permits, so one project can count several times, once under each kind of work.
  • A final date is the day the city marked the permit completed. Permits that expired or were cancelled carry no final date even where the file shows one, because that date is when they lapsed.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Demolition permits in Philadelphia, PA", https://contractorrecords.com/philadelphia/demolition-permits, data through September 2026, from the City of Philadelphia Department of Licenses and Inspections building-permit records.

Link to a table: By month · Season · Days to final · By ZIP code · Permit types.

Download the tables (CSV): Demolition permits by month · Demolition permits by calendar month (index) · Demolition permits: days to final · Demolition permits by ZIP code · Demolition permits by permit type.

Common questions

  • How many demolition permits does Philadelphia issue a year?About 310 a year in Philadelphia: 621 permits issued October 2024 through September 2026, 313 of them in the last 12 months.
  • How long does a demolition permit take in Philadelphia?The usual one took 32 days from issue to the city's final inspection, and the middle half took 21 to 54 days (298 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Philadelphia file the most demolition permits?May (120 against an average month of 100); November is the quietest (70). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.
  • Which ZIP code has the most demolition permits in Philadelphia?19132, with 101 of the 621 (16%); then 19121 (63).