Remodel and repair permits in Philadelphia, PA

Data through September 2026 · updated 19 Oct 2026

10,519 remodel and repair permits were issued in Philadelphia, October 2024 through September 2026: about 5,260 a year and 18% of all permits. 5,374 remodel and repair permits in the last 12 months (Oct 2025–Sep 2026), 4% more than the 5,145 in the 12 months before. The busiest month is October. The usual one took 113 days from issue to the city's final. 19143 has the most, 736.

10,519permits issued
5,374last 12 months
Octbusiest month
113days, usual issue to final
67%finished
Sep 2026records through

Remodel and repair permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 467Oct2024Nov 2024: 426Dec 2024: 337Jan 2025: 378Jan2025Feb 2025: 365Mar 2025: 462Apr 2025: 444May 2025: 451Jun 2025: 464Jul 2025: 451JulAug 2025: 405Sep 2025: 495Oct 2025: 544Nov 2025: 426Dec 2025: 424Jan 2026: 386Jan2026Feb 2026: 421Mar 2026: 457Apr 2026: 431May 2026: 424Jun 2026: 463Jul 2026: 469JulAug 2026: 461Sep 2026: 468
The same numbers as a table
MonthPermits
Oct 2024467
Nov 2024426
Dec 2024337
Jan 2025378
Feb 2025365
Mar 2025462
Apr 2025444
May 2025451
Jun 2025464
Jul 2025451
Aug 2025405
Sep 2025495
Oct 2025544
Nov 2025426
Dec 2025424
Jan 2026386
Feb 2026421
Mar 2026457
Apr 2026431
May 2026424
Jun 2026463
Jul 2026469
Aug 2026461
Sep 2026468

Download this table (CSV)

When remodel and repair permits are filed

By calendar month, 100 = an average month (the thin line). October is the busiest (115), January the quietest (87). A busy month at the permit counter usually means a longer wait for a contractor.

January: 87 (100 = an average month)February: 90 (100 = an average month)March: 105 (100 = an average month)April: 100 (100 = an average month)May: 100 (100 = an average month)June: 106 (100 = an average month)July: 105 (100 = an average month)August: 99 (100 = an average month)September: 110 (100 = an average month)October: 115 (100 = an average month)115November: 97 (100 = an average month)December: 87 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January87
February90
March105
April100
May100
June106
July105
August99
September110
October115
November97
December87

Download this table (CSV)

How long a remodel and repair permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 3,442 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 20255,145
Finished67.0%
Expired20.1%
Usual days, issue to final113
Middle half, days35–216

Download this table (CSV)

ZIP codes with the most remodel and repair permits

Counted at the property's ZIP code. Share is the part of the city's 10,519 remodel and repair permits.

ZIP codePermitsShare
191437367%
191466166%
191405205%
191344805%
191484745%
191324494%
191394404%
191474324%
191314204%
191454004%

Download this table (CSV)

The city's own permit types

How the city filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
Residential Building: Addition and/or Alteration5,44352%
Plumbing: EZ Bathroom & Kitchen Remodel1,90618%
Residential Building: Make Safe Permit For RP1,15011%
General Permit Minor: EZ Interior Non-Load-Bearing Wall Demo.1,08610%
General Permit Minor: EZ Wall Covering Replacement6336%
General Permit Minor: EZ Exterior Window and Door Replacement1662%
General Permit Minor: EZ Masonry Facade Replacement1181%
General Permit Minor: EZ Chimney and Vent Extension17under 1%

Download this table (CSV)

How Philadelphia compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

How these numbers are made

Source: City of Philadelphia, Licenses and Inspections Building and Zoning Permits, 2007 to present (OpenDataPhilly; Carto table permits), read 19 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Residential permits the City of Philadelphia Department of Licenses and Inspections (L&I) issues inside the city, which is also Philadelphia County: building, plumbing, electrical, mechanical, EZ minor-work, demolition and solar permits for homes. Commercial permits, zoning and use permits, excavation and site permits, certificates of occupancy and event permits in the same file are not counted. Suburbs in Bucks, Montgomery and Delaware counties run their own permit offices and are not in this file.

  • The city's file lists a contractor on most permits, but these pages show permit counts only: there are no contractor lists, rankings or firm pages for Philadelphia.
  • We count residential permits only, as the city's file marks them; a home job filed as a commercial permit is not counted.
  • The city's open permit file has no declared job value, so we show no costs.
  • A new house gets separate building, plumbing, electrical and mechanical permits, so one project can count several times, once under each kind of work.
  • A final date is the day the city marked the permit completed. Permits that expired or were cancelled carry no final date even where the file shows one, because that date is when they lapsed.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Remodel and repair permits in Philadelphia, PA", https://contractorrecords.com/philadelphia/remodel-permits, data through September 2026, from the City of Philadelphia Department of Licenses and Inspections building-permit records.

Link to a table: By month · Season · Days to final · By ZIP code · Permit types.

Download the tables (CSV): Remodels & repairs permits by month · Remodels & repairs permits by calendar month (index) · Remodels & repairs permits: days to final · Remodels & repairs permits by ZIP code · Remodels & repairs permits by permit type.

Common questions

  • How many remodel and repair permits does Philadelphia issue a year?About 5,260 a year in Philadelphia: 10,519 permits issued October 2024 through September 2026, 5,374 of them in the last 12 months.
  • How long does a remodel and repair permit take in Philadelphia?The usual one took 113 days from issue to the city's final inspection, and the middle half took 35 to 216 days (3,442 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Philadelphia file the most remodel and repair permits?October (115 against an average month of 100); January is the quietest (87). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.
  • Which ZIP code has the most remodel and repair permits in Philadelphia?19143, with 736 of the 10,519 (7%); then 19146 (616).