Cost to Build an ADU in Sacramento County (unincorporated), CA: what the permits say

How much does it cost to build an ADU in Sacramento County? The usual ADU job filed with Sacramento County is $133,039, from 207 priced permits (October 2023 through September 2026); the middle half of firms file between $99,402 and $173,840. A filed value is what the contractor wrote on the permit, not a quote or the final bill.

$133,039usual filed value
$99,402–$173,840middle half of firms' usual jobs
207priced permits (100% of 207)
134firms on file
254days, permit issue to final
Sep 2026records through

How much does it cost to build an ADU in Sacramento County?

The usual ADU job filed with Sacramento County is $133,039, from 207 priced permits, October 2023 through September 2026. The middle half of firms usually file between $99,402 and $173,840. Half of jobs were filed for less, half for more. A filed value is what the contractor wrote on the permit, not a quote or the final bill. An ADU permit here usually takes 254 days from issue to final inspection. How long permits take →

What the spread looks like

Approximately, from each firm's own spread: every firm's range of filed values, weighted by its 207 priced permits across 134 firms, pooled into one. Half of Sacramento County (unincorporated) ADU permits were filed between $85,400 and $186,000.

PercentileFiled valueReads as
10th$56,1001 in 10 permits filed below
25th$85,4001 in 4 filed below
50th$133,000the middle permit
75th$186,0001 in 4 filed above
90th$268,0001 in 10 filed above

Busiest firms and what they usually charge

Top 10 by permits in the last 12 months. Usual is each firm's middle filed value; middle half is the range its middle half of jobs were filed in; both are shown for firms with 5 or more priced permits. Busy is not the same as careful: pick what you value to build a list.

FirmPermitsLast 12 moUsualMiddle halfFinished
A Construction Pro Inc2211$95,136$66,309–$192,37189.9%
Imkat Construction Corp199$133,356$104,361–$165,61895.9%
Golden State Adus42———
Norcal ADU Builders LLC32———
Andrew Lowell22———
West Coast Construction Pro Build22———
Byrne Remodel22———
Skyline Build & Design Inc31———
Dyer Construction Inc31———
Redwood ADU LLC21———

Why filed values run low or high

  • The 10 busiest firms usually file $95,136; the 132 firms with fewer than 10 permits usually file $136,789.
  • One permit type covers small and large jobs: 1 in 10 ADU permits is filed under $56,100 and 1 in 10 over $268,000, 5 times as much.
  • 100.0% of the 207 permits carry a value; the 0 without one are left out of every figure here.

Is your quote normal? Compare it with 207 filed values

Line your quote up against the file. In Sacramento County (unincorporated), 1 in 10 ADU filed values sit under $56,100, the middle half between $85,400 and $186,000, and 1 in 10 over $268,000.

  • $349,000Above $268,000: higher than 9 in 10 filed values for this work in Sacramento County (unincorporated).
  • $133,039Right at the usual $133,039: in the middle of the file.
  • $39,200Below $56,100: lower than 9 in 10. Ask what the quote leaves out.

When to schedule ADU construction in Sacramento County

Sacramento County files the fewest ADU permits in February (64 against an average month of 100) and the most in August (186). If you can choose, ask for quotes in a quiet month. We have no prices by month, so this is about crews' schedules, not a discount. When each trade is busiest in Sacramento County →

How these numbers are made

Source: Sacramento County building permits on single-family, duplex and townhouse homes in the unincorporated county (the County's Accela permit layer). The window is October 2023 through September 2026; a permit filed after that isn't here yet.

Usual is the middle permit: half were filed for less, half for more. Only permits with a filed value count; a value of $0 or none is left out.

The spread is approximate: we keep seven points of each firm's own range of filed values, not every permit, and pool them.

Nobody paid to be on this page and nobody can. How the records work in Sacramento County (unincorporated) →

Common questions

  • How many quotes should I get for an ADU job in Sacramento County (unincorporated)?At least three. In the permit record the middle half of Sacramento County (unincorporated) ADU firms usually file between $99,402 and $173,840 a job, so two ordinary firms can sit 1.7 times apart and both be normal for Sacramento County (unincorporated). A third quote shows which one is the outlier. Filed values are what contractors wrote on permits, not quotes, so use them to judge the spread, not to price your own job.
  • What range is normal for ADU jobs in Sacramento County (unincorporated)?Half of permits were filed between $85,400 and $186,000; 8 in 10 between $56,100 and $268,000. These are approximate, pooled from each firm's own spread.
  • How much do ADU builders charge in Sacramento County?The usual ADU job is filed at $133,039; the middle half of firms usually file between $99,402 and $173,840. The 10 firms with the most permits in the last 12 months usually file $95,136, less than the usual. See every firm's usual job →
  • Why do prices I see online differ from $133,039?$133,039 is the construction value contractors wrote on Sacramento County permits. Online figures are usually all-in ranges whose scope you can't check (design, fees, site work), and our file mixes small and large jobs of this type in one number. Use the spread above to see where a quote sits.
  • How much is the ADU permit fee in Sacramento County?Sacramento County sets permit fees in Sacramento County Code chapter 16.90, Construction Permit Fees (read October 2026). The chapter sets the fee schedule (last amended May 2026); it names no flat fee per trade, so we don't compute one. Ask the permit office for the fee on a job filed at about $133,039, the usual ADU value here.
  • How many ADU firms work in Sacramento County (unincorporated)?134 firms appear on the file; 55 pulled at least one permit in the last 12 months.
  • Where does this data come from?Sacramento County building permits on single-family, duplex and townhouse homes in the unincorporated county (the County's Accela permit layer), read October 2026. How the records work in Sacramento County (unincorporated) →

ADU cost in other cities: Nashville Raleigh Denver San Diego Honolulu Palo Alto Bellingham San Francisco Anaheim Marin County (unincorporated)