Solar permits in the City of Santa Barbara, CA

Data through August 2025 · updated 19 Oct 2026

656 solar permits were issued in the City of Santa Barbara, September 2023 through August 2025: about 328 a year and 13% of all permits. 307 solar permits in the last 12 months on file (Sep 2024–Aug 2025), 12% fewer than the 349 in the 12 months before. The busiest month is January. The usual one took 52 days from issue to the city's final. 93105 has the most, 225.

656permits issued
307last 12 months on file
Janbusiest month
52days, usual issue to final
80%finished
Aug 2025records through

Solar permits by month

Permits issued each month, September 2023 through August 2025.

Sep 2023: 29Sep2023Oct 2023: 40Nov 2023: 37Dec 2023: 21Jan 2024: 53Jan2024Feb 2024: 20Mar 2024: 31Apr 2024: 35May 2024: 21Jun 2024: 24Jul 2024: 18JulAug 2024: 20Sep 2024: 24Oct 2024: 28Nov 2024: 24Dec 2024: 13Jan 2025: 34Jan2025Feb 2025: 24Mar 2025: 18Apr 2025: 34May 2025: 17Jun 2025: 28Jul 2025: 19JulAug 2025: 44
The same numbers as a table
MonthPermits
Sep 202329
Oct 202340
Nov 202337
Dec 202321
Jan 202453
Feb 202420
Mar 202431
Apr 202435
May 202421
Jun 202424
Jul 202418
Aug 202420
Sep 202424
Oct 202428
Nov 202424
Dec 202413
Jan 202534
Feb 202524
Mar 202518
Apr 202534
May 202517
Jun 202528
Jul 202519
Aug 202544

Download this table (CSV)

When solar permits are filed

By calendar month, 100 = an average month (the thin line). January is the busiest (159), December the quietest (62). A busy month at the permit counter usually means a longer wait for a contractor.

January: 159 (100 = an average month)159February: 80 (100 = an average month)March: 90 (100 = an average month)April: 126 (100 = an average month)May: 70 (100 = an average month)June: 95 (100 = an average month)July: 68 (100 = an average month)August: 117 (100 = an average month)September: 97 (100 = an average month)October: 124 (100 = an average month)November: 112 (100 = an average month)December: 62 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January159
February80
March90
April126
May70
June95
July68
August117
September97
October124
November112
December62

Download this table (CSV)

How long a solar permit takes

Permits issued Sep 2023–Aug 2024, at least 12 months before the file ends. Usual days is the middle permit among the 281 with a final date.

MeasureValue
Permits issued Sep 2023–Aug 2024349
Finished80.5%
Usual days, issue to final52
Middle half, days23–104

Download this table (CSV)

ZIP codes with the most solar permits

Counted at the property's ZIP code. Share is the part of the city's 656 solar permits.

ZIP codePermitsShare
9310522534%
9310914622%
9310312018%
9310111017%
93108305%
93110234%

Download this table (CSV)

The city's own permit types

How the city filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
1 & 2 Family Expedited Solar PV and Optional ESS46270%
1 & 2 Family Expedited Battery Energy Storage (ESS) to Existing Solar PV8413%
Electrical8313%
Residential173%
Commercial New102%

Download this table (CSV)

How Santa Barbara compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

How these numbers are made

Source: City of Santa Barbara GIS, Building Permits layer (Building_Permits FeatureServer, Accela BLD records), read 19 Oct 2026. We count permits issued September 2023 through August 2025; denied and withdrawn permits are left out.

Building and trade permits the City of Santa Barbara issues inside city limits: new homes and ADUs, additions, alterations, re-roofs, solar, electrical, mechanical, plumbing, pool, demolition and sign permits. Revisions to an earlier permit, flood-elevation determinations and other administrative records, and grading and paving sitework are not counted. Goleta, Montecito and the rest of unincorporated Santa Barbara County are permitted by other offices and are not in this file.

  • The city's layer names no contractor, so there are no contractor lists, rankings or firm pages for Santa Barbara.
  • The layer has no declared job value, so we show no costs.
  • The city has not added permits to this layer since early September 2025, so these pages end with August 2025.
  • A permit counts as finished when the city marks it complete; the final date is the layer's completed date.
  • Homes are permits the city codes as one- or two-family dwellings (its R and R-3 codes) and its 1 & 2 family express permits; apartment buildings count as other.
  • Electrical, mechanical and plumbing permits are separate from the building permit for the same job, so one project can count more than once.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Solar permits in the City of Santa Barbara, CA", https://contractorrecords.com/santa-barbara/solar-permits, data through August 2025, from City of Santa Barbara Community Development, Building & Safety building-permit records.

Link to a table: By month · Season · Days to final · By ZIP code · Permit types.

Download the tables (CSV): Solar permits by month · Solar permits by calendar month (index) · Solar permits: days to final · Solar permits by ZIP code · Solar permits by permit type.

Common questions

  • How many solar permits does Santa Barbara issue a year?About 328 a year in the City of Santa Barbara: 656 permits issued September 2023 through August 2025, 307 of them in the last 12 months on file (to August 2025).
  • How long does a solar permit take in Santa Barbara?The usual one took 52 days from issue to the city's final inspection, and the middle half took 23 to 104 days (281 permits issued Sep 2023–Aug 2024 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Santa Barbara file the most solar permits?January (159 against an average month of 100); December is the quietest (62). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.
  • Which ZIP code has the most solar permits in Santa Barbara?93105, with 225 of the 656 (34%); then 93109 (146).