EV Charger Installation Cost in Elk Grove, CA: what the permits say

How much does EV charger installation cost in Elk Grove? The usual EV charger job filed with Elk Grove is $925, from 1,351 priced permits (October 2023 through September 2026); the middle half of firms file between $850 and $1,312. A filed value is what the contractor wrote on the permit, not a quote or the final bill.

$925usual filed value
$850–$1,312middle half of firms' usual jobs
1,351priced permits (100% of 1,353)
119firms on file
18days, permit issue to final
Sep 2026records through

How much does EV charger installation cost in Elk Grove?

The usual EV charger job filed with Elk Grove is $925, from 1,351 priced permits, October 2023 through September 2026. The middle half of firms usually file between $850 and $1,312. Half of jobs were filed for less, half for more. A filed value is what the contractor wrote on the permit, not a quote or the final bill. An EV charger permit here usually takes 18 days from issue to final inspection. How long permits take →

What the spread looks like

Approximately, from each firm's own spread: every firm's range of filed values, weighted by its 1,351 priced permits across 118 firms, pooled into one. Half of Elk Grove EV charger permits were filed between $740 and $1,500.

PercentileFiled valueReads as
10th$5401 in 10 permits filed below
25th$7401 in 4 filed below
50th$930the middle permit
75th$1,5001 in 4 filed above
90th$2,2001 in 10 filed above

Busiest firms and what they usually charge

Top 10 by permits in the last 12 months. Usual is each firm's middle filed value; middle half is the range its middle half of jobs were filed in. Busy is not the same as careful: pick what you value to build a list.

FirmPermitsLast 12 moUsualMiddle halfFinished
Illuminate Electric Solutions LLC15572$850$700–$1,00097.1%
Connected Technology12836$1,015$795–$1,62495.4%
CLC Electrical Solutions LLC4231$850$750–$95078.4%
Sagan Electric4228$550$500–$70796.6%
High Energy Electric6524$1,500$1,50098.5%
Huft Home Services6222$1,031$926–$1,37363.2%
Sierra Valley Mechanical1715$2,826$2,665–$3,200—
3JS Electric & Painting Inc10514$750$750–$80095.2%
Bonney Plumbing Electrical Heating & Air6110$1,584$1,323–$2,07283.0%
Charles Young Electric5910$700$602–$84598.7%

Why filed values run low or high

  • The 10 busiest firms usually file $850; the 92 firms with fewer than 10 permits usually file $1,000.
  • One permit type covers small and large jobs: 1 in 10 EV charger permits is filed under $540 and 1 in 10 over $2,200, 4 times as much.
  • 99.9% of the 1,353 permits carry a value; the 2 without one are left out of every figure here.

Is your quote normal? Compare it with 1,351 filed values

Line your quote up against the file. In Elk Grove, 1 in 10 EV charger filed values sit under $540, the middle half between $740 and $1,500, and 1 in 10 over $2,200.

  • $2,800Above $2,200: higher than 9 in 10 filed values for this work in Elk Grove.
  • $925Right at the usual $925: in the middle of the file.
  • $380Below $540: lower than 9 in 10. Ask what the quote leaves out.

When to schedule EV charger installation in Elk Grove

Elk Grove files the fewest EV charger permits in November (66 against an average month of 100) and the most in June (125). If you can choose, ask for quotes in a quiet month. We have no prices by month, so this is about crews' schedules, not a discount. When each trade is busiest in Elk Grove →

How these numbers are made

Source: City of Elk Grove TRAKiT building permits on single-family, duplex, mobile-home and ADU homes. The window is October 2023 through September 2026; a permit filed after that isn't here yet.

Usual is the middle permit: half were filed for less, half for more. Only permits with a filed value count; a value of $0 or none is left out.

The spread is approximate: we keep seven points of each firm's own range of filed values, not every permit, and pool them.

Nobody paid to be on this page and nobody can. How the records work in Elk Grove →

Common questions

  • How many quotes should I get for an EV charger job in Elk Grove?At least three. In the permit record the middle half of Elk Grove EV charger firms usually file between $850 and $1,312 a job, so two ordinary firms can sit 1.5 times apart and both be normal for Elk Grove. A third quote shows which one is the outlier. Filed values are what contractors wrote on permits, not quotes, so use them to judge the spread, not to price your own job.
  • What range is normal for EV charger jobs in Elk Grove?Half of permits were filed between $740 and $1,500; 8 in 10 between $540 and $2,200. These are approximate, pooled from each firm's own spread.
  • How much do EV charger installers charge in Elk Grove?The usual EV charger job is filed at $925; the middle half of firms usually file between $850 and $1,312. The 10 firms with the most permits in the last 12 months usually file $850, less than the usual. See every firm's usual job →
  • How many EV charger firms work in Elk Grove?119 firms appear on the file; 70 pulled at least one permit in the last 12 months.
  • Where does this data come from?City of Elk Grove TRAKiT building permits on single-family, duplex, mobile-home and ADU homes, read October 2026. How the records work in Elk Grove →

EV Charger cost in other cities: Cary Naperville Burlington, VT Marin County (unincorporated) Sacramento County (unincorporated)

Other job costs in Elk Grove: HVAC · Solar & Battery · New Home · Water Heater · Plumbing & Sewer · Remodel & Addition · Windows & Doors · Electrical · Roofing · Patio Cover & Accessory Structure · Pool & Spa