How long do permits take in the Town of Gilbert, AZ?

Data through September 2026 · updated 19 Oct 2026

The usual permit in the Town of Gilbert takes 69 days from issue to the town's final inspection; the middle half take 28 to 173 days. That is from 2,554 permits issued Oct 2024–Sep 2025 that reached a final. Plumbing permits are quickest at 18 days; new home permits take longest at 207 days. This is the time to finish the work and close the permit, not the wait for approval.

69days, usual issue to final
28–173days, middle half
73%finished
2,554permits with a final date
Sep 2026records through

Getting the permit vs finishing the work: two different clocks

“How long does a permit take?” can mean two waits. This page measures the second one.

Getting the permit (not measured): application → issue, the wait for the town to approve the plans. Ask the town for its current review times.

Finishing the work (measured here): issue → final. From the day the town issued the permit to the day it recorded the final inspection. We count only permits issued Oct 2024–Sep 2025, at least 12 months before the file ends, so slow jobs have had time to finish; a permit still open is not in the days.

By kind of work

Permits issued Oct 2024–Sep 2025. Usual days is the middle permit among those with a final date: half finished sooner, half later. Middle half is the range the middle 50% fell in. Kinds of work with fewer than 100 permits in that period are left out.

Kind of workPermitsFinishedExpiredUsual days to finalMiddle half (days)
Electrical72586.3%0.0%3213–65
Plumbing39587.3%0.0%186–48
New homes42180.3%0.0%207178–258
Pools & spas30896.8%1.3%8456–131
Remodels & repairs27756.0%0.0%9851–171
Garages, sheds & shade structures15263.8%0.0%18977–279
Other1,14655.3%0.3%8843–174

Download this table (CSV)

How long each kind of permit takes

Each kind of work on its own, issue to the town's final.

How long does electrical work take in Gilbert, from permit to final?

The usual electrical permit in the Town of Gilbert takes 32 days from issue to final; the middle half take 13 to 65 days (626 permits with a final date, issued Oct 2024–Sep 2025). 86% of the 725 permits issued then have finished and 0% expired. Gilbert electrical permits →

How long does plumbing work take in Gilbert, from permit to final?

The usual plumbing permit in the Town of Gilbert takes 18 days from issue to final; the middle half take 6 to 48 days (345 permits with a final date, issued Oct 2024–Sep 2025). 87% of the 395 permits issued then have finished and 0% expired. Gilbert plumbing permits →

How long does building a new home take in Gilbert, from permit to final?

The usual new home permit in the Town of Gilbert takes 207 days from issue to final; the middle half take 178 to 258 days (338 permits with a final date, issued Oct 2024–Sep 2025). 80% of the 421 permits issued then have finished and 0% expired. Gilbert new home permits →

How long does a pool or spa take in Gilbert, from permit to final?

The usual pool and spa permit in the Town of Gilbert takes 84 days from issue to final; the middle half take 56 to 131 days (298 permits with a final date, issued Oct 2024–Sep 2025). 97% of the 308 permits issued then have finished and 1% expired. Gilbert pool and spa permits →

How long does a remodel take in Gilbert, from permit to final?

The usual remodel and repair permit in the Town of Gilbert takes 98 days from issue to final; the middle half take 51 to 171 days (155 permits with a final date, issued Oct 2024–Sep 2025). 56% of the 277 permits issued then have finished and 0% expired. Gilbert remodel and repair permits →

How long does a garage, shed or patio cover take in Gilbert, from permit to final?

The usual garage, shed and shade structure permit in the Town of Gilbert takes 189 days from issue to final; the middle half take 77 to 279 days (97 permits with a final date, issued Oct 2024–Sep 2025). 64% of the 152 permits issued then have finished and 0% expired. Gilbert garage, shed and shade structure permits →

How Gilbert compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

Nearby permit data

How long permits take for other places in Phoenix. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: Town of Gilbert open data, EnergovPermitData (ArcGIS table), read 19 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Permits the Town of Gilbert issues inside the town limits only. Mesa, Chandler, Queen Creek and unincorporated Maricopa County islands next to Gilbert run their own permit offices and are not in this file.

  • The town's open permit file names no contractor, so there are no contractor lists, rankings or firm pages for Gilbert.
  • New homes include production homes built from a builder's standard plan and custom homes.
  • The town files residential additions and alterations together; they are counted as remodels and repairs.
  • The town's file has no roofing or solar work class, so roof replacements are not shown and solar is counted with residential electrical work.
  • Plan changes and deferred submittals (amendments to a permit already issued), standard plan approvals, and traffic and engineering permits are left out.
  • The value is the valuation on the permit, which sets the fee; trade permits often carry none. It is not a final cost.
  • A final date is the date the permit was finaled.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "How long do permits take in the Town of Gilbert, AZ?", https://contractorrecords.com/gilbert/how-long-does-a-permit-take, data through September 2026, from the Town of Gilbert Development Services building-permit records.

Link to a table: By kind of work · Each kind of permit.

Download the tables (CSV): Days to final by kind of work.

Common questions

  • What is the permit turnaround in Gilbert?From issue to final inspection, the usual permit takes 69 days (middle half 28 to 173 days), from 2,554 permits issued Oct 2024–Sep 2025. The wait to get a permit issued is not in this file; ask the town for its current review times.
  • Which permits finish fastest in Gilbert?Plumbing permits, at 18 days. The slowest are new home permits, at 207 days. Bigger jobs take longer; so does work where the final inspection is easy to forget.
  • How many permits actually get finished in Gilbert?73% of the 3,515 permits issued Oct 2024–Sep 2025 have finished; under 1% expired without a final and the rest are still open.
  • Why does an open permit matter to me?An unfinished permit stays with the property, not the contractor. It can hold up a sale or a refinance. Ask whoever does the work to call for the final inspection and show you the result.