How long do permits take in the City of Tempe, AZ?

Data through September 2026 · updated 19 Oct 2026

The usual permit in the City of Tempe takes 81 days from issue to the city's final inspection; the middle half take 36 to 190 days. That is from 1,434 permits issued Oct 2024–Sep 2025 that reached a final. Electrical permits are quickest at 30 days; pool and spa permits take longest at 88 days. This is the time to finish the work and close the permit, not the wait for approval.

81days, usual issue to final
36–190days, middle half
72%finished
1,434permits with a final date
Sep 2026records through

Getting the permit vs finishing the work: two different clocks

“How long does a permit take?” can mean two waits. This page measures the second one.

Getting the permit (not measured): application → issue, the wait for the city to approve the plans. Ask the city for its current review times.

Finishing the work (measured here): issue → final. From the day the city issued the permit to the day it recorded the final inspection. We count only permits issued Oct 2024–Sep 2025, at least 12 months before the file ends, so slow jobs have had time to finish; a permit still open is not in the days.

By kind of work

Permits issued Oct 2024–Sep 2025. Usual days is the middle permit among those with a final date: half finished sooner, half later. Middle half is the range the middle 50% fell in. Kinds of work with fewer than 100 permits in that period are left out.

Kind of workPermitsFinishedExpiredUsual days to finalMiddle half (days)
Electrical44366.4%20.5%3013–83
Remodels & repairs39779.8%12.6%8551–156
Plumbing27368.5%20.5%4114–136
Solar19789.8%6.1%4427–70
Other60669.8%10.4%12971–260

Download this table (CSV)

How long each kind of permit takes

Each kind of work on its own, issue to the city's final.

How long does electrical work take in Tempe, from permit to final?

The usual electrical permit in the City of Tempe takes 30 days from issue to final; the middle half take 13 to 83 days (222 permits with a final date, issued Oct 2024–Sep 2025). 66% of the 443 permits issued then have finished and 20% expired. Tempe electrical permits →

How long does a remodel take in Tempe, from permit to final?

The usual remodel and repair permit in the City of Tempe takes 85 days from issue to final; the middle half take 51 to 156 days (310 permits with a final date, issued Oct 2024–Sep 2025). 80% of the 397 permits issued then have finished and 13% expired. Tempe remodel and repair permits →

How long does plumbing work take in Tempe, from permit to final?

The usual plumbing permit in the City of Tempe takes 41 days from issue to final; the middle half take 14 to 136 days (138 permits with a final date, issued Oct 2024–Sep 2025). 68% of the 273 permits issued then have finished and 20% expired. Tempe plumbing permits →

How long does a solar installation take in Tempe, from permit to final?

The usual solar permit in the City of Tempe takes 44 days from issue to final; the middle half take 27 to 70 days (173 permits with a final date, issued Oct 2024–Sep 2025). 90% of the 197 permits issued then have finished and 6% expired. Tempe solar permits →

How long does a pool or spa take in Tempe, from permit to final?

The usual pool and spa permit in the City of Tempe takes 88 days from issue to final; the middle half take 45 to 187 days (59 permits with a final date, issued Oct 2024–Sep 2025).

How Tempe compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

Nearby permit data

How long permits take for other places in Phoenix. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: City of Tempe Open Data, Permits Issued by Building Safety (BLDS layer from Accela), read 19 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Building, trade, pool, sign and demolition permits the City of Tempe Building Safety Division issues inside the city limits only. Phoenix, Mesa, Chandler, Scottsdale and unincorporated Maricopa County run their own permit offices and are not in this file. The city's engineering permits (water and sewer, drainage, paving, grading) are left out.

  • The city's open permit file leaves the contractor field blank on building permits, so there are no contractor lists, rankings or firm pages for Tempe.
  • The value is the estimated project cost on the permit; electrical, plumbing and mechanical permits are filed as no-value permits and carry none. It is not a final cost.
  • Kinds of work come from the permit's federal building class; general residential alterations and miscellaneous permits are sorted into trades by keywords in the work description.
  • Few roof replacements appear in the file, so roofing has no page of its own.
  • A final date is the date the city recorded the permit as completed. Permits marked Final, Finaled, CofO Issued or Closed count as finished; some of them carry no completed date and add no days.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "How long do permits take in the City of Tempe, AZ?", https://contractorrecords.com/tempe/how-long-does-a-permit-take, data through September 2026, from the City of Tempe Building Safety Division building-permit records.

Link to a table: By kind of work · Each kind of permit.

Download the tables (CSV): Days to final by kind of work.

Common questions

  • What is the permit turnaround in Tempe?From issue to final inspection, the usual permit takes 81 days (middle half 36 to 190 days), from 1,434 permits issued Oct 2024–Sep 2025. The wait to get a permit issued is not in this file; ask the city for its current review times.
  • Which permits finish fastest in Tempe?Electrical permits, at 30 days. The slowest are pool and spa permits, at 88 days. Bigger jobs take longer; so does work where the final inspection is easy to forget.
  • How many permits actually get finished in Tempe?72% of the 2,282 permits issued Oct 2024–Sep 2025 have finished; 14% expired without a final and the rest are still open.
  • Why does an open permit matter to me?An unfinished permit stays with the property, not the contractor. It can hold up a sale or a refinance. Ask whoever does the work to call for the final inspection and show you the result.