How long do permits take in the City of Kennewick, WA?

Data through September 2026 · updated 19 Oct 2026

The usual permit in the City of Kennewick takes 73 days from issue to the city's final inspection; the middle half take 16 to 168 days. That is from 1,752 permits issued Oct 2024–Sep 2025 that reached a final. Plumbing permits are quickest at 18 days; new home permits take longest at 154 days. This is the time to finish the work and close the permit, not the wait for approval.

73days, usual issue to final
16–168days, middle half
75%finished
1,752permits with a final date
Sep 2026records through

Getting the permit vs finishing the work: two different clocks

“How long does a permit take?” can mean two waits. This page measures the second one.

Getting the permit (not measured): application → issue, the wait for the city to approve the plans. Ask the city for its current review times.

Finishing the work (measured here): issue → final. From the day the city issued the permit to the day it recorded the final inspection. We count only permits issued Oct 2024–Sep 2025, at least 12 months before the file ends, so slow jobs have had time to finish; a permit still open is not in the days.

By kind of work

Permits issued Oct 2024–Sep 2025. Usual days is the middle permit among those with a final date: half finished sooner, half later. Middle half is the range the middle 50% fell in. Kinds of work with fewer than 100 permits in that period are left out.

Kind of workPermitsFinishedExpiredUsual days to finalMiddle half (days)
HVAC58173.5%23.9%208–61
New homes37597.3%0.8%154117–198
Plumbing30073.3%20.7%187–101
Roofing26363.9%35.7%189–48
Remodels & repairs26058.8%40.0%6636–148
Other42876.9%16.4%11142–220

Download this table (CSV)

How long each kind of permit takes

Each kind of work on its own, issue to the city's final.

How long does an HVAC replacement take in Kennewick, from permit to final?

The usual HVAC permit in the City of Kennewick takes 20 days from issue to final; the middle half take 8 to 61 days (427 permits with a final date, issued Oct 2024–Sep 2025). 74% of the 581 permits issued then have finished and 24% expired. Kennewick HVAC permits →

How long does building a new home take in Kennewick, from permit to final?

The usual new home permit in the City of Kennewick takes 154 days from issue to final; the middle half take 117 to 198 days (365 permits with a final date, issued Oct 2024–Sep 2025). 97% of the 375 permits issued then have finished and under 1% expired. Kennewick new home permits →

How long does plumbing work take in Kennewick, from permit to final?

The usual plumbing permit in the City of Kennewick takes 18 days from issue to final; the middle half take 7 to 101 days (220 permits with a final date, issued Oct 2024–Sep 2025). 73% of the 300 permits issued then have finished and 21% expired. Kennewick plumbing permits →

How long does a roof replacement take in Kennewick, from permit to final?

The usual roofing permit in the City of Kennewick takes 18 days from issue to final; the middle half take 9 to 48 days (168 permits with a final date, issued Oct 2024–Sep 2025). 64% of the 263 permits issued then have finished and 36% expired. Kennewick roofing permits →

How long does a remodel take in Kennewick, from permit to final?

The usual remodel and repair permit in the City of Kennewick takes 66 days from issue to final; the middle half take 36 to 148 days (153 permits with a final date, issued Oct 2024–Sep 2025). 59% of the 260 permits issued then have finished and 40% expired. Kennewick remodel and repair permits →

How Kennewick compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

Nearby permit data

How long permits take for other places in the Tri-Cities. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: City of Kennewick EnerGov public permit layer (Public/EnerGovPublicInspection, EnerGovPermits), behind the city's Permit & Plan Explorer, read 19 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Building, mechanical, plumbing, sign and fire-system permits the City of Kennewick issues inside the city limits only. Richland, Pasco, West Richland and unincorporated Benton County run their own permit offices and are not in this file. Public works, utility-connection, right-of-way and grading permits are left out. Electrical permits in Washington are issued by the state Department of Labor & Industries, not the city, so they are not in this file.

  • The city's public permit layer names no contractor, so there are no contractor lists, rankings or firm pages for Kennewick.
  • The layer has no declared job value, so we show no costs.
  • The layer has no street address or ZIP code, so there are no ZIP code pages for Kennewick.
  • Electrical permits are issued by Washington's Department of Labor & Industries, not the city, so electrical and most solar work does not appear here.
  • A final date is the date the city finalized the permit; permits the city voided, cancelled or denied are not counted.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "How long do permits take in the City of Kennewick, WA?", https://contractorrecords.com/kennewick/how-long-does-a-permit-take, data through September 2026, from the City of Kennewick Building Safety Division building-permit records.

Link to a table: By kind of work · Each kind of permit.

Download the tables (CSV): Days to final by kind of work.

Common questions

  • What is the permit turnaround in Kennewick?From issue to final inspection, the usual permit takes 73 days (middle half 16 to 168 days), from 1,752 permits issued Oct 2024–Sep 2025. The wait to get a permit issued is not in this file; ask the city for its current review times.
  • Which permits finish fastest in Kennewick?Plumbing permits, at 18 days. The slowest are new home permits, at 154 days. Bigger jobs take longer; so does work where the final inspection is easy to forget.
  • How many permits actually get finished in Kennewick?75% of the 2,342 permits issued Oct 2024–Sep 2025 have finished; 22% expired without a final and the rest are still open.
  • Why does an open permit matter to me?An unfinished permit stays with the property, not the contractor. It can hold up a sale or a refinance. Ask whoever does the work to call for the final inspection and show you the result.