New home permits in the City of Kennewick, WA

Data through September 2026 · updated 19 Oct 2026

681 new home permits were issued in the City of Kennewick, October 2024 through September 2026: about 340 a year and 15% of all permits. 306 new home permits in the last 12 months (Oct 2025–Sep 2026), 18% fewer than the 375 in the 12 months before. The busiest month is April. The usual one took 154 days from issue to the city's final.

681permits issued
306last 12 months
Aprbusiest month
154days, usual issue to final
97%finished
Sep 2026records through

New home permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 33Oct2024Nov 2024: 26Dec 2024: 16Jan 2025: 9Jan2025Feb 2025: 18Mar 2025: 55Apr 2025: 53May 2025: 34Jun 2025: 46Jul 2025: 29JulAug 2025: 25Sep 2025: 31Oct 2025: 32Nov 2025: 21Dec 2025: 30Jan 2026: 26Jan2026Feb 2026: 26Mar 2026: 24Apr 2026: 34May 2026: 17Jun 2026: 24Jul 2026: 41JulAug 2026: 21Sep 2026: 10
The same numbers as a table
MonthPermits
Oct 202433
Nov 202426
Dec 202416
Jan 20259
Feb 202518
Mar 202555
Apr 202553
May 202534
Jun 202546
Jul 202529
Aug 202525
Sep 202531
Oct 202532
Nov 202521
Dec 202530
Jan 202626
Feb 202626
Mar 202624
Apr 202634
May 202617
Jun 202624
Jul 202641
Aug 202621
Sep 202610

Download this table (CSV)

When new home permits are filed

By calendar month, 100 = an average month (the thin line). April is the busiest (153), January the quietest (62). A busy month at the permit counter usually means a longer wait for a contractor.

January: 62 (100 = an average month)February: 78 (100 = an average month)March: 139 (100 = an average month)April: 153 (100 = an average month)153May: 90 (100 = an average month)June: 123 (100 = an average month)July: 123 (100 = an average month)August: 81 (100 = an average month)September: 72 (100 = an average month)October: 115 (100 = an average month)November: 83 (100 = an average month)December: 81 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January62
February78
March139
April153
May90
June123
July123
August81
September72
October115
November83
December81

Download this table (CSV)

How long a new home permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 365 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 2025375
Finished97.3%
Expired0.8%
Usual days, issue to final154
Middle half, days117–198

Download this table (CSV)

The city's own permit types

How the city filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
Residential - Express Detached Single Family Dwelling33749%
Residential - Detached Single Family Dwelling16124%
Residential - Attached Single Family Dwelling467%
Residential - Townhome446%
Residential - Express Attached Single Family Dwelling416%
Residential - Duplex355%
Residential - Express Townhome112%
Residential - Manufactured Homes/In-fill2under 1%
Residential - Express Duplex2under 1%
Residential - Manufactured Homes/RTP2under 1%

Download this table (CSV)

How Kennewick compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

Nearby permit data

New home permits for other places in the Tri-Cities. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: City of Kennewick EnerGov public permit layer (Public/EnerGovPublicInspection, EnerGovPermits), behind the city's Permit & Plan Explorer, read 19 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Building, mechanical, plumbing, sign and fire-system permits the City of Kennewick issues inside the city limits only. Richland, Pasco, West Richland and unincorporated Benton County run their own permit offices and are not in this file. Public works, utility-connection, right-of-way and grading permits are left out. Electrical permits in Washington are issued by the state Department of Labor & Industries, not the city, so they are not in this file.

  • The city's public permit layer names no contractor, so there are no contractor lists, rankings or firm pages for Kennewick.
  • The layer has no declared job value, so we show no costs.
  • The layer has no street address or ZIP code, so there are no ZIP code pages for Kennewick.
  • Electrical permits are issued by Washington's Department of Labor & Industries, not the city, so electrical and most solar work does not appear here.
  • A final date is the date the city finalized the permit; permits the city voided, cancelled or denied are not counted.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "New home permits in the City of Kennewick, WA", https://contractorrecords.com/kennewick/new-home-permits, data through September 2026, from the City of Kennewick Building Safety Division building-permit records.

Link to a table: By month · Season · Days to final · Permit types.

Download the tables (CSV): New homes permits by month · New homes permits by calendar month (index) · New homes permits: days to final · New homes permits by permit type.

Common questions

  • How many new home permits does Kennewick issue a year?About 340 a year in the City of Kennewick: 681 permits issued October 2024 through September 2026, 306 of them in the last 12 months.
  • How long does a new home permit take in Kennewick?The usual one took 154 days from issue to the city's final inspection, and the middle half took 117 to 198 days (365 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Kennewick file the most new home permits?April (153 against an average month of 100); January is the quietest (62). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.