ADU and casita permits in the City of Los Angeles, CA

Data through September 2026 · updated 18 Oct 2026

13,265 ADU and casita permits were issued in the City of Los Angeles, October 2024 through September 2026: about 6,632 a year and 13% of all permits. 6,389 ADU and casita permits in the last 12 months (Oct 2025–Sep 2026), 7% fewer than the 6,876 in the 12 months before. The busiest month is May. The usual one took 286 days from issue to the city's final. 91335 has the most, 538.

What this file covers: This is the LADBS building-permit file. Electrical, plumbing and mechanical permits are kept in separate files and not counted, so those trades show only when a building permit names them.

13,265permits issued
6,389last 12 months
Maybusiest month
286days, usual issue to final
60%finished
$75,000usual declared value
Sep 2026records through

ADU and casita permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 533Oct2024Nov 2024: 495Dec 2024: 507Jan 2025: 578Jan2025Feb 2025: 586Mar 2025: 623Apr 2025: 608May 2025: 609Jun 2025: 552Jul 2025: 612JulAug 2025: 604Sep 2025: 569Oct 2025: 560Nov 2025: 477Dec 2025: 547Jan 2026: 527Jan2026Feb 2026: 536Mar 2026: 548Apr 2026: 538May 2026: 573Jun 2026: 529Jul 2026: 532JulAug 2026: 497Sep 2026: 525
The same numbers as a table
MonthPermits
Oct 2024533
Nov 2024495
Dec 2024507
Jan 2025578
Feb 2025586
Mar 2025623
Apr 2025608
May 2025609
Jun 2025552
Jul 2025612
Aug 2025604
Sep 2025569
Oct 2025560
Nov 2025477
Dec 2025547
Jan 2026527
Feb 2026536
Mar 2026548
Apr 2026538
May 2026573
Jun 2026529
Jul 2026532
Aug 2026497
Sep 2026525

Download this table (CSV)

When ADU and casita permits are filed

By calendar month, 100 = an average month (the thin line). May is the busiest (107), November the quietest (88). A busy month at the permit counter usually means a longer wait for a contractor.

January: 100 (100 = an average month)February: 102 (100 = an average month)March: 106 (100 = an average month)April: 104 (100 = an average month)May: 107 (100 = an average month)107June: 98 (100 = an average month)July: 103 (100 = an average month)August: 100 (100 = an average month)September: 99 (100 = an average month)October: 99 (100 = an average month)November: 88 (100 = an average month)December: 95 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January100
February102
March106
April104
May107
June98
July103
August100
September99
October99
November88
December95

Download this table (CSV)

How long an ADU and casita permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 4,090 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 20256,876
Finished59.5%
Expired0.0%
Usual days, issue to final286
Middle half, days195–392

Download this table (CSV)

What an ADU and casita permit is declared at

The value written on the permit at application, from 13,081 permits with one. Not a quote and not the final bill.

MeasureValue
Usual declared value$75,000
Middle half$40,000–$140,000

Download this table (CSV)

ZIP codes with the most ADU and casita permits

Counted at the property's ZIP code. Share is the part of the city's 13,265 ADU and casita permits.

ZIP codePermitsShare
913355384%
913444794%
913314213%
902723623%
913423433%
913063192%
916053092%
913523092%
914063092%
913432942%

Download this table (CSV)

The city's own permit types

How the city filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
Bldg-Alter/Repair4,70335%
Bldg-New4,28132%
Bldg-Addition4,28132%

Download this table (CSV)

Nearby permit data

ADU and casita permits for other places in Los Angeles and the Inland Empire. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: LADBS, Building and Safety - Building Permits Issued from 2020 to Present (N), data.lacity.org, read 18 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Building permits the City of Los Angeles Department of Building and Safety (LADBS) issues inside the city limits only. Other cities in Los Angeles County (Long Beach, Pasadena, Santa Monica, Glendale and the rest) and unincorporated county land run their own permit offices and are not in this file. Electrical, plumbing and mechanical permits are kept by LADBS in separate files and are not counted here, so those trades show only when a building permit names them.

  • The city's open permit file names no contractor, so there are no contractor lists, rankings or firm pages for Los Angeles.
  • Only building permits are counted. LADBS keeps electrical and mechanical (heating, air conditioning, plumbing) permits in separate files, so solar, HVAC, plumbing and electrical work is undercounted: it shows only when a building permit names it.
  • Supplemental permits (a revision or transfer of an earlier permit) and grading permits are left out.
  • The value is the job valuation the permit was issued on, which sets the fee. It is not a final cost.
  • A final date is the date the permit was finaled or its certificate of occupancy issued.
  • Permits after the January 2025 wildfires include rebuilding work in Pacific Palisades and other burn areas.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "ADU and casita permits in the City of Los Angeles, CA", https://contractorrecords.com/los-angeles/adu-permits, data through September 2026, from the City of Los Angeles Department of Building and Safety building-permit records.

Link to a table: By month · Season · Days to final · Declared value · By ZIP code · Permit types.

Download the tables (CSV): ADUs & casitas permits by month · ADUs & casitas permits by calendar month (index) · ADUs & casitas permits: days to final · ADUs & casitas permits: declared value · ADUs & casitas permits by ZIP code · ADUs & casitas permits by permit type.

Common questions

  • How many ADU and casita permits does Los Angeles issue a year?About 6,632 a year in the City of Los Angeles: 13,265 permits issued October 2024 through September 2026, 6,389 of them in the last 12 months.
  • How long does an ADU and casita permit take in Los Angeles?The usual one took 286 days from issue to the city's final inspection, and the middle half took 195 to 392 days (4,090 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Los Angeles file the most ADU and casita permits?May (107 against an average month of 100); November is the quietest (88). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.
  • Which ZIP code has the most ADU and casita permits in Los Angeles?91335, with 538 of the 13,265 (4%); then 91344 (479).