Remodel and repair permits in the City of Los Angeles, CA

Data through September 2026 · updated 18 Oct 2026

21,914 remodel and repair permits were issued in the City of Los Angeles, October 2024 through September 2026: about 10,957 a year and 22% of all permits. 10,685 remodel and repair permits in the last 12 months (Oct 2025–Sep 2026), 5% fewer than the 11,229 in the 12 months before. The busiest month is October. The usual one took 85 days from issue to the city's final. 90272 has the most, 728.

What this file covers: This is the LADBS building-permit file. Electrical, plumbing and mechanical permits are kept in separate files and not counted, so those trades show only when a building permit names them.

21,914permits issued
10,685last 12 months
Octbusiest month
85days, usual issue to final
73%finished
$7,000usual declared value
Sep 2026records through

Remodel and repair permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 1,108Oct2024Nov 2024: 845Dec 2024: 872Jan 2025: 826Jan2025Feb 2025: 827Mar 2025: 976Apr 2025: 944May 2025: 973Jun 2025: 983Jul 2025: 963JulAug 2025: 929Sep 2025: 983Oct 2025: 1,025Nov 2025: 788Dec 2025: 854Jan 2026: 860Jan2026Feb 2026: 779Mar 2026: 930Apr 2026: 934May 2026: 833Jun 2026: 890Jul 2026: 895JulAug 2026: 990Sep 2026: 907
The same numbers as a table
MonthPermits
Oct 20241,108
Nov 2024845
Dec 2024872
Jan 2025826
Feb 2025827
Mar 2025976
Apr 2025944
May 2025973
Jun 2025983
Jul 2025963
Aug 2025929
Sep 2025983
Oct 20251,025
Nov 2025788
Dec 2025854
Jan 2026860
Feb 2026779
Mar 2026930
Apr 2026934
May 2026833
Jun 2026890
Jul 2026895
Aug 2026990
Sep 2026907

Download this table (CSV)

When remodel and repair permits are filed

By calendar month, 100 = an average month (the thin line). October is the busiest (117), February the quietest (88). A busy month at the permit counter usually means a longer wait for a contractor.

January: 92 (100 = an average month)February: 88 (100 = an average month)March: 104 (100 = an average month)April: 103 (100 = an average month)May: 99 (100 = an average month)June: 103 (100 = an average month)July: 102 (100 = an average month)August: 105 (100 = an average month)September: 103 (100 = an average month)October: 117 (100 = an average month)117November: 89 (100 = an average month)December: 95 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January92
February88
March104
April103
May99
June103
July102
August105
September103
October117
November89
December95

Download this table (CSV)

How long a remodel and repair permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 8,204 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 202511,229
Finished73.1%
Expired0.1%
Usual days, issue to final85
Middle half, days44–169

Download this table (CSV)

What a remodel and repair permit is declared at

The value written on the permit at application, from 21,561 permits with one. Not a quote and not the final bill.

MeasureValue
Usual declared value$7,000
Middle half$3,000–$17,000

Download this table (CSV)

ZIP codes with the most remodel and repair permits

Counted at the property's ZIP code. Share is the part of the city's 21,914 remodel and repair permits.

ZIP codePermitsShare
902727283%
900425483%
900495362%
900655072%
913445042%
900664972%
900264932%
900454922%
913644612%
913354142%

Download this table (CSV)

How Los Angeles compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

Nearby permit data

Remodel and repair permits for other places in Los Angeles and the Inland Empire. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: LADBS, Building and Safety - Building Permits Issued from 2020 to Present (N), data.lacity.org, read 18 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Building permits the City of Los Angeles Department of Building and Safety (LADBS) issues inside the city limits only. Other cities in Los Angeles County (Long Beach, Pasadena, Santa Monica, Glendale and the rest) and unincorporated county land run their own permit offices and are not in this file. Electrical, plumbing and mechanical permits are kept by LADBS in separate files and are not counted here, so those trades show only when a building permit names them.

  • The city's open permit file names no contractor, so there are no contractor lists, rankings or firm pages for Los Angeles.
  • Only building permits are counted. LADBS keeps electrical and mechanical (heating, air conditioning, plumbing) permits in separate files, so solar, HVAC, plumbing and electrical work is undercounted: it shows only when a building permit names it.
  • Supplemental permits (a revision or transfer of an earlier permit) and grading permits are left out.
  • The value is the job valuation the permit was issued on, which sets the fee. It is not a final cost.
  • A final date is the date the permit was finaled or its certificate of occupancy issued.
  • Permits after the January 2025 wildfires include rebuilding work in Pacific Palisades and other burn areas.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Remodel and repair permits in the City of Los Angeles, CA", https://contractorrecords.com/los-angeles/remodel-permits, data through September 2026, from the City of Los Angeles Department of Building and Safety building-permit records.

Link to a table: By month · Season · Days to final · Declared value · By ZIP code.

Download the tables (CSV): Remodels & repairs permits by month · Remodels & repairs permits by calendar month (index) · Remodels & repairs permits: days to final · Remodels & repairs permits: declared value · Remodels & repairs permits by ZIP code.

Common questions

  • How many remodel and repair permits does Los Angeles issue a year?About 10,957 a year in the City of Los Angeles: 21,914 permits issued October 2024 through September 2026, 10,685 of them in the last 12 months.
  • How long does a remodel and repair permit take in Los Angeles?The usual one took 85 days from issue to the city's final inspection, and the middle half took 44 to 169 days (8,204 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Los Angeles file the most remodel and repair permits?October (117 against an average month of 100); February is the quietest (88). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.
  • Which ZIP code has the most remodel and repair permits in Los Angeles?90272, with 728 of the 21,914 (3%); then 90042 (548).