Fence and wall permits in the City of Los Angeles, CA

Data through September 2026 · updated 18 Oct 2026

2,420 fence and wall permits were issued in the City of Los Angeles, October 2024 through September 2026: about 1,210 a year and 2% of all permits. 1,189 fence and wall permits in the last 12 months (Oct 2025–Sep 2026), 3% fewer than the 1,231 in the 12 months before. The busiest month is February. The usual one took 160 days from issue to the city's final. 90272 has the most, 386.

What this file covers: This is the LADBS building-permit file. Electrical, plumbing and mechanical permits are kept in separate files and not counted, so those trades show only when a building permit names them.

2,420permits issued
1,189last 12 months
Febbusiest month
160days, usual issue to final
53%finished
$15,000usual declared value
Sep 2026records through

Fence and wall permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 92Oct2024Nov 2024: 89Dec 2024: 77Jan 2025: 95Jan2025Feb 2025: 122Mar 2025: 96Apr 2025: 112May 2025: 119Jun 2025: 119Jul 2025: 103JulAug 2025: 113Sep 2025: 94Oct 2025: 104Nov 2025: 86Dec 2025: 97Jan 2026: 86Jan2026Feb 2026: 107Mar 2026: 107Apr 2026: 90May 2026: 86Jun 2026: 105Jul 2026: 118JulAug 2026: 110Sep 2026: 93
The same numbers as a table
MonthPermits
Oct 202492
Nov 202489
Dec 202477
Jan 202595
Feb 2025122
Mar 202596
Apr 2025112
May 2025119
Jun 2025119
Jul 2025103
Aug 2025113
Sep 202594
Oct 2025104
Nov 202586
Dec 202597
Jan 202686
Feb 2026107
Mar 2026107
Apr 202690
May 202686
Jun 2026105
Jul 2026118
Aug 2026110
Sep 202693

Download this table (CSV)

When fence and wall permits are filed

By calendar month, 100 = an average month (the thin line). February is the busiest (114), December the quietest (86). A busy month at the permit counter usually means a longer wait for a contractor.

January: 90 (100 = an average month)February: 114 (100 = an average month)114March: 101 (100 = an average month)April: 100 (100 = an average month)May: 102 (100 = an average month)June: 111 (100 = an average month)July: 110 (100 = an average month)August: 111 (100 = an average month)September: 93 (100 = an average month)October: 97 (100 = an average month)November: 87 (100 = an average month)December: 86 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January90
February114
March101
April100
May102
June111
July110
August111
September93
October97
November87
December86

Download this table (CSV)

How long a fence and wall permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 648 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 20251,231
Finished52.6%
Expired0.2%
Usual days, issue to final160
Middle half, days71–310

Download this table (CSV)

What a fence and wall permit is declared at

The value written on the permit at application, from 2,411 permits with one. Not a quote and not the final bill.

MeasureValue
Usual declared value$15,000
Middle half$6,800–$30,000

Download this table (CSV)

ZIP codes with the most fence and wall permits

Counted at the property's ZIP code. Share is the part of the city's 2,420 fence and wall permits.

ZIP codePermitsShare
9027238616%
900491426%
913261155%
90210733%
90026723%
91311713%
90077562%
90065552%
90046522%
91604512%

Download this table (CSV)

The city's own permit types

How the city filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
Nonbldg-New2,30195%
Nonbldg-Alter/Repair1105%
Nonbldg-Addition9under 1%

Download this table (CSV)

Nearby permit data

Fence and wall permits for other places in Los Angeles and the Inland Empire. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: LADBS, Building and Safety - Building Permits Issued from 2020 to Present (N), data.lacity.org, read 18 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Building permits the City of Los Angeles Department of Building and Safety (LADBS) issues inside the city limits only. Other cities in Los Angeles County (Long Beach, Pasadena, Santa Monica, Glendale and the rest) and unincorporated county land run their own permit offices and are not in this file. Electrical, plumbing and mechanical permits are kept by LADBS in separate files and are not counted here, so those trades show only when a building permit names them.

  • The city's open permit file names no contractor, so there are no contractor lists, rankings or firm pages for Los Angeles.
  • Only building permits are counted. LADBS keeps electrical and mechanical (heating, air conditioning, plumbing) permits in separate files, so solar, HVAC, plumbing and electrical work is undercounted: it shows only when a building permit names it.
  • Supplemental permits (a revision or transfer of an earlier permit) and grading permits are left out.
  • The value is the job valuation the permit was issued on, which sets the fee. It is not a final cost.
  • A final date is the date the permit was finaled or its certificate of occupancy issued.
  • Permits after the January 2025 wildfires include rebuilding work in Pacific Palisades and other burn areas.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Fence and wall permits in the City of Los Angeles, CA", https://contractorrecords.com/los-angeles/fence-permits, data through September 2026, from the City of Los Angeles Department of Building and Safety building-permit records.

Link to a table: By month · Season · Days to final · Declared value · By ZIP code · Permit types.

Download the tables (CSV): Fences & walls permits by month · Fences & walls permits by calendar month (index) · Fences & walls permits: days to final · Fences & walls permits: declared value · Fences & walls permits by ZIP code · Fences & walls permits by permit type.

Common questions

  • How many fence and wall permits does Los Angeles issue a year?About 1,210 a year in the City of Los Angeles: 2,420 permits issued October 2024 through September 2026, 1,189 of them in the last 12 months.
  • How long does a fence and wall permit take in Los Angeles?The usual one took 160 days from issue to the city's final inspection, and the middle half took 71 to 310 days (648 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Los Angeles file the most fence and wall permits?February (114 against an average month of 100); December is the quietest (86). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.
  • Which ZIP code has the most fence and wall permits in Los Angeles?90272, with 386 of the 2,420 (16%); then 90049 (142).