New home permits in the City of Los Angeles, CA

Data through September 2026 · updated 18 Oct 2026

2,853 new home permits were issued in the City of Los Angeles, October 2024 through September 2026: about 1,426 a year and 3% of all permits. 1,600 new home permits in the last 12 months (Oct 2025–Sep 2026), 28% more than the 1,253 in the 12 months before. The busiest month is February. The usual one took 380 days from issue to the city's final. 90272 has the most, 1,165.

What this file covers: This is the LADBS building-permit file. Electrical, plumbing and mechanical permits are kept in separate files and not counted, so those trades show only when a building permit names them.

2,853permits issued
1,600last 12 months
Febbusiest month
380days, usual issue to final
40%finished
$450,000usual declared value
Sep 2026records through

New home permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 76Oct2024Nov 2024: 100Dec 2024: 71Jan 2025: 88Jan2025Feb 2025: 116Mar 2025: 135Apr 2025: 91May 2025: 109Jun 2025: 106Jul 2025: 115JulAug 2025: 127Sep 2025: 119Oct 2025: 142Nov 2025: 113Dec 2025: 153Jan 2026: 120Jan2026Feb 2026: 194Mar 2026: 166Apr 2026: 109May 2026: 103Jun 2026: 129Jul 2026: 122JulAug 2026: 119Sep 2026: 130
The same numbers as a table
MonthPermits
Oct 202476
Nov 2024100
Dec 202471
Jan 202588
Feb 2025116
Mar 2025135
Apr 202591
May 2025109
Jun 2025106
Jul 2025115
Aug 2025127
Sep 2025119
Oct 2025142
Nov 2025113
Dec 2025153
Jan 2026120
Feb 2026194
Mar 2026166
Apr 2026109
May 2026103
Jun 2026129
Jul 2026122
Aug 2026119
Sep 2026130

Download this table (CSV)

When new home permits are filed

By calendar month, 100 = an average month (the thin line). February is the busiest (130), April the quietest (84). A busy month at the permit counter usually means a longer wait for a contractor.

January: 87 (100 = an average month)February: 130 (100 = an average month)130March: 127 (100 = an average month)April: 84 (100 = an average month)May: 89 (100 = an average month)June: 99 (100 = an average month)July: 100 (100 = an average month)August: 103 (100 = an average month)September: 105 (100 = an average month)October: 92 (100 = an average month)November: 90 (100 = an average month)December: 94 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January87
February130
March127
April84
May89
June99
July100
August103
September105
October92
November90
December94

Download this table (CSV)

How long a new home permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 508 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 20251,253
Finished40.5%
Expired0.0%
Usual days, issue to final380
Middle half, days276–472

Download this table (CSV)

What a new home permit is declared at

The value written on the permit at application, from 2,852 permits with one. Not a quote and not the final bill.

MeasureValue
Usual declared value$450,000
Middle half$300,000–$660,000

Download this table (CSV)

ZIP codes with the most new home permits

Counted at the property's ZIP code. Share is the part of the city's 2,853 new home permits.

ZIP codePermitsShare
902721,16541%
91326542%
90026532%
90049482%
91601472%
91311472%
90003452%
90016432%
91401401%
90066381%

Download this table (CSV)

How Los Angeles compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

Nearby permit data

New home permits for other places in Los Angeles and the Inland Empire. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: LADBS, Building and Safety - Building Permits Issued from 2020 to Present (N), data.lacity.org, read 18 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Building permits the City of Los Angeles Department of Building and Safety (LADBS) issues inside the city limits only. Other cities in Los Angeles County (Long Beach, Pasadena, Santa Monica, Glendale and the rest) and unincorporated county land run their own permit offices and are not in this file. Electrical, plumbing and mechanical permits are kept by LADBS in separate files and are not counted here, so those trades show only when a building permit names them.

  • The city's open permit file names no contractor, so there are no contractor lists, rankings or firm pages for Los Angeles.
  • Only building permits are counted. LADBS keeps electrical and mechanical (heating, air conditioning, plumbing) permits in separate files, so solar, HVAC, plumbing and electrical work is undercounted: it shows only when a building permit names it.
  • Supplemental permits (a revision or transfer of an earlier permit) and grading permits are left out.
  • The value is the job valuation the permit was issued on, which sets the fee. It is not a final cost.
  • A final date is the date the permit was finaled or its certificate of occupancy issued.
  • Permits after the January 2025 wildfires include rebuilding work in Pacific Palisades and other burn areas.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "New home permits in the City of Los Angeles, CA", https://contractorrecords.com/los-angeles/new-home-permits, data through September 2026, from the City of Los Angeles Department of Building and Safety building-permit records.

Link to a table: By month · Season · Days to final · Declared value · By ZIP code.

Download the tables (CSV): New homes permits by month · New homes permits by calendar month (index) · New homes permits: days to final · New homes permits: declared value · New homes permits by ZIP code.

Common questions

  • How many new home permits does Los Angeles issue a year?About 1,426 a year in the City of Los Angeles: 2,853 permits issued October 2024 through September 2026, 1,600 of them in the last 12 months.
  • How long does a new home permit take in Los Angeles?The usual one took 380 days from issue to the city's final inspection, and the middle half took 276 to 472 days (508 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Los Angeles file the most new home permits?February (130 against an average month of 100); April is the quietest (84). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.
  • Which ZIP code has the most new home permits in Los Angeles?90272, with 1,165 of the 2,853 (41%); then 91326 (54).