Contractor Records
Home › Los Angeles › HVAC

HVAC permits in the City of Los Angeles, CA

Data through September 2026 · updated 18 Oct 2026

483 HVAC permits were issued in the City of Los Angeles, October 2024 through September 2026: about 242 a year and under 1% of all permits. 231 HVAC permits in the last 12 months (Oct 2025–Sep 2026), 8% fewer than the 252 in the 12 months before. The busiest month is March. The usual one took 114 days from issue to the city's final. 90045 has the most, 23.

What this file covers: This is the LADBS building-permit file. Electrical, plumbing and mechanical permits are kept in separate files and not counted, so those trades show only when a building permit names them.

483permits issued
231last 12 months
Marbusiest month
114days, usual issue to final
70%finished
$15,000usual declared value
Sep 2026records through

HVAC permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 22Oct2024Nov 2024: 14Dec 2024: 23Jan 2025: 23Jan2025Feb 2025: 21Mar 2025: 31Apr 2025: 20May 2025: 22Jun 2025: 23Jul 2025: 21JulAug 2025: 11Sep 2025: 21Oct 2025: 19Nov 2025: 16Dec 2025: 15Jan 2026: 14Jan2026Feb 2026: 21Mar 2026: 21Apr 2026: 24May 2026: 24Jun 2026: 20Jul 2026: 21JulAug 2026: 21Sep 2026: 15
The same numbers as a table
MonthPermits
Oct 202422
Nov 202414
Dec 202423
Jan 202523
Feb 202521
Mar 202531
Apr 202520
May 202522
Jun 202523
Jul 202521
Aug 202511
Sep 202521
Oct 202519
Nov 202516
Dec 202515
Jan 202614
Feb 202621
Mar 202621
Apr 202624
May 202624
Jun 202620
Jul 202621
Aug 202621
Sep 202615

Download this table (CSV)

When HVAC permits are filed

By calendar month, 100 = an average month (the thin line). March is the busiest (129), November the quietest (75). A busy month at the permit counter usually means a longer wait for a contractor.

January: 92 (100 = an average month)February: 104 (100 = an average month)March: 129 (100 = an average month)129April: 109 (100 = an average month)May: 114 (100 = an average month)June: 107 (100 = an average month)July: 104 (100 = an average month)August: 80 (100 = an average month)September: 89 (100 = an average month)October: 102 (100 = an average month)November: 75 (100 = an average month)December: 94 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January92
February104
March129
April109
May114
June107
July104
August80
September89
October102
November75
December94

Download this table (CSV)

How long an HVAC permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 177 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 2025252
Finished70.2%
Expired1.2%
Usual days, issue to final114
Middle half, days63–236

Download this table (CSV)

What an HVAC permit is declared at

The value written on the permit at application, from 483 permits with one. Not a quote and not the final bill.

MeasureValue
Usual declared value$15,000
Middle half$7,500–$50,000

Download this table (CSV)

ZIP codes with the most HVAC permits

Counted at the property's ZIP code. Share is the part of the city's 483 HVAC permits.

ZIP codePermitsShare
90045235%
90049204%
90272174%
90036163%
90066143%
90019133%
90731122%
90024122%
90004112%
90042112%

Download this table (CSV)

How Los Angeles compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

Nearby permit data

HVAC permits for other places in Los Angeles and the Inland Empire. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: LADBS, Building and Safety - Building Permits Issued from 2020 to Present (N), data.lacity.org, read 18 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Building permits the City of Los Angeles Department of Building and Safety (LADBS) issues inside the city limits only. Other cities in Los Angeles County (Long Beach, Pasadena, Santa Monica, Glendale and the rest) and unincorporated county land run their own permit offices and are not in this file. Electrical, plumbing and mechanical permits are kept by LADBS in separate files and are not counted here, so those trades show only when a building permit names them.

  • The city's open permit file names no contractor, so there are no contractor lists, rankings or firm pages for Los Angeles.
  • Only building permits are counted. LADBS keeps electrical and mechanical (heating, air conditioning, plumbing) permits in separate files, so solar, HVAC, plumbing and electrical work is undercounted: it shows only when a building permit names it.
  • Supplemental permits (a revision or transfer of an earlier permit) and grading permits are left out.
  • The value is the job valuation the permit was issued on, which sets the fee. It is not a final cost.
  • A final date is the date the permit was finaled or its certificate of occupancy issued.
  • Permits after the January 2025 wildfires include rebuilding work in Pacific Palisades and other burn areas.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "HVAC permits in the City of Los Angeles, CA", https://contractorrecords.com/los-angeles/hvac-permits, data through September 2026, from the City of Los Angeles Department of Building and Safety building-permit records.

Link to a table: By month · Season · Days to final · Declared value · By ZIP code.

Download the tables (CSV): HVAC permits by month · HVAC permits by calendar month (index) · HVAC permits: days to final · HVAC permits: declared value · HVAC permits by ZIP code.

Common questions

  • How many HVAC permits does Los Angeles issue a year?About 242 a year in the City of Los Angeles: 483 permits issued October 2024 through September 2026, 231 of them in the last 12 months.
  • How long does an HVAC permit take in Los Angeles?The usual one took 114 days from issue to the city's final inspection, and the middle half took 63 to 236 days (177 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Los Angeles file the most HVAC permits?March (129 against an average month of 100); November is the quietest (75). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.
  • Which ZIP code has the most HVAC permits in Los Angeles?90045, with 23 of the 483 (5%); then 90049 (20).