How long do permits take in the City of Los Angeles, CA?

Data through September 2026 · updated 18 Oct 2026

The usual permit in the City of Los Angeles takes 90 days from issue to the city's final inspection; the middle half take 27 to 233 days. That is from 33,536 permits issued Oct 2024–Sep 2025 that reached a final. Roofing permits are quickest at 22 days; new home permits take longest at 380 days. This is the time to finish the work and close the permit, not the wait for approval.

90days, usual issue to final
27–233days, middle half
67%finished
33,536permits with a final date
Sep 2026records through

Getting the permit vs finishing the work: two different clocks

“How long does a permit take?” can mean two waits. This page measures the second one.

Getting the permit (not measured): application → issue, the wait for the city to approve the plans. Ask the city for its current review times.

Finishing the work (measured here): issue → final. From the day the city issued the permit to the day it recorded the final inspection. We count only permits issued Oct 2024–Sep 2025, at least 12 months before the file ends, so slow jobs have had time to finish; a permit still open is not in the days.

By kind of work

Permits issued Oct 2024–Sep 2025. Usual days is the middle permit among those with a final date: half finished sooner, half later. Middle half is the range the middle 50% fell in. Kinds of work with fewer than 100 permits in that period are left out.

Kind of workPermitsFinishedExpiredUsual days to finalMiddle half (days)
Roofing12,28679.4%0.1%2213–44
Remodels & repairs11,22973.1%0.1%8544–169
ADUs & casitas6,87659.5%0.0%286195–392
Additions2,53950.8%0.0%293198–398
Pools & spas1,66454.1%0.1%243141–352
Demolition1,86378.4%0.1%6724–192
New homes1,25340.5%0.0%380276–472
Fences & walls1,23152.6%0.2%16071–310
Garages, sheds & shade structures51840.2%0.0%282199–384
HVAC25270.2%1.2%11463–236
Other9,92662.8%0.1%12156–228

Download this table (CSV)

How long each kind of permit takes

Each kind of work on its own, issue to the city's final.

How long does a roof replacement take in Los Angeles, from permit to final?

The usual roofing permit in the City of Los Angeles takes 22 days from issue to final; the middle half take 13 to 44 days (9,757 permits with a final date, issued Oct 2024–Sep 2025). 79% of the 12,286 permits issued then have finished and under 1% expired. Los Angeles roofing permits →

How long does a remodel take in Los Angeles, from permit to final?

The usual remodel and repair permit in the City of Los Angeles takes 85 days from issue to final; the middle half take 44 to 169 days (8,204 permits with a final date, issued Oct 2024–Sep 2025). 73% of the 11,229 permits issued then have finished and under 1% expired. Los Angeles remodel and repair permits →

How long does an ADU or casita take in Los Angeles, from permit to final?

The usual ADU and casita permit in the City of Los Angeles takes 286 days from issue to final; the middle half take 195 to 392 days (4,090 permits with a final date, issued Oct 2024–Sep 2025). 60% of the 6,876 permits issued then have finished and 0% expired. Los Angeles ADU and casita permits →

How long does a home addition take in Los Angeles, from permit to final?

The usual home addition permit in the City of Los Angeles takes 293 days from issue to final; the middle half take 198 to 398 days (1,290 permits with a final date, issued Oct 2024–Sep 2025). 51% of the 2,539 permits issued then have finished and 0% expired. Los Angeles home addition permits →

How long does a pool or spa take in Los Angeles, from permit to final?

The usual pool and spa permit in the City of Los Angeles takes 243 days from issue to final; the middle half take 141 to 352 days (901 permits with a final date, issued Oct 2024–Sep 2025). 54% of the 1,664 permits issued then have finished and under 1% expired. Los Angeles pool and spa permits →

How long does a demolition take in Los Angeles, from permit to final?

The usual demolition permit in the City of Los Angeles takes 67 days from issue to final; the middle half take 24 to 192 days (1,459 permits with a final date, issued Oct 2024–Sep 2025). 78% of the 1,863 permits issued then have finished and under 1% expired. Los Angeles demolition permits →

How long does building a new home take in Los Angeles, from permit to final?

The usual new home permit in the City of Los Angeles takes 380 days from issue to final; the middle half take 276 to 472 days (508 permits with a final date, issued Oct 2024–Sep 2025). 40% of the 1,253 permits issued then have finished and 0% expired. Los Angeles new home permits →

How long does a fence or wall take in Los Angeles, from permit to final?

The usual fence and wall permit in the City of Los Angeles takes 160 days from issue to final; the middle half take 71 to 310 days (648 permits with a final date, issued Oct 2024–Sep 2025). 53% of the 1,231 permits issued then have finished and under 1% expired. Los Angeles fence and wall permits →

How long does a garage, shed or patio cover take in Los Angeles, from permit to final?

The usual garage, shed and shade structure permit in the City of Los Angeles takes 282 days from issue to final; the middle half take 199 to 384 days (208 permits with a final date, issued Oct 2024–Sep 2025). 40% of the 518 permits issued then have finished and 0% expired. Los Angeles garage, shed and shade structure permits →

How long does an HVAC replacement take in Los Angeles, from permit to final?

The usual HVAC permit in the City of Los Angeles takes 114 days from issue to final; the middle half take 63 to 236 days (177 permits with a final date, issued Oct 2024–Sep 2025). 70% of the 252 permits issued then have finished and 1% expired. Los Angeles HVAC permits →

How Los Angeles compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

Nearby permit data

How long permits take for other places in Los Angeles and the Inland Empire. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: LADBS, Building and Safety - Building Permits Issued from 2020 to Present (N), data.lacity.org, read 18 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Building permits the City of Los Angeles Department of Building and Safety (LADBS) issues inside the city limits only. Other cities in Los Angeles County (Long Beach, Pasadena, Santa Monica, Glendale and the rest) and unincorporated county land run their own permit offices and are not in this file. Electrical, plumbing and mechanical permits are kept by LADBS in separate files and are not counted here, so those trades show only when a building permit names them.

  • The city's open permit file names no contractor, so there are no contractor lists, rankings or firm pages for Los Angeles.
  • Only building permits are counted. LADBS keeps electrical and mechanical (heating, air conditioning, plumbing) permits in separate files, so solar, HVAC, plumbing and electrical work is undercounted: it shows only when a building permit names it.
  • Supplemental permits (a revision or transfer of an earlier permit) and grading permits are left out.
  • The value is the job valuation the permit was issued on, which sets the fee. It is not a final cost.
  • A final date is the date the permit was finaled or its certificate of occupancy issued.
  • Permits after the January 2025 wildfires include rebuilding work in Pacific Palisades and other burn areas.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "How long do permits take in the City of Los Angeles, CA?", https://contractorrecords.com/los-angeles/how-long-does-a-permit-take, data through September 2026, from the City of Los Angeles Department of Building and Safety building-permit records.

Link to a table: By kind of work · Each kind of permit.

Download the tables (CSV): Days to final by kind of work.

Common questions

  • What is the permit turnaround in Los Angeles?From issue to final inspection, the usual permit takes 90 days (middle half 27 to 233 days), from 33,536 permits issued Oct 2024–Sep 2025. The wait to get a permit issued is not in this file; ask the city for its current review times.
  • Which permits finish fastest in Los Angeles?Roofing permits, at 22 days. The slowest are new home permits, at 380 days. Bigger jobs take longer; so does work where the final inspection is easy to forget.
  • How many permits actually get finished in Los Angeles?67% of the 49,737 permits issued Oct 2024–Sep 2025 have finished; under 1% expired without a final and the rest are still open.
  • Why does an open permit matter to me?An unfinished permit stays with the property, not the contractor. It can hold up a sale or a refinance. Ask whoever does the work to call for the final inspection and show you the result.