New home permits in Lynchburg, VA

Data through September 2026 · updated 20 Oct 2026

392 new home permits were issued in Lynchburg, October 2024 through September 2026: about 196 a year and 13% of all permits. 204 new home permits in the last 12 months (Oct 2025–Sep 2026), 9% more than the 188 in the 12 months before. The busiest month is June. The usual one took 161 days from issue to the city's final.

392permits issued
204last 12 months
Junbusiest month
161days, usual issue to final
97%finished
$180,000usual declared value
Sep 2026records through

New home permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 16Oct2024Nov 2024: 23Dec 2024: 11Jan 2025: 10Jan2025Feb 2025: 4Mar 2025: 21Apr 2025: 28May 2025: 16Jun 2025: 30Jul 2025: 6JulAug 2025: 8Sep 2025: 15Oct 2025: 24Nov 2025: 6Dec 2025: 8Jan 2026: 7Jan2026Feb 2026: 15Mar 2026: 31Apr 2026: 26May 2026: 6Jun 2026: 34Jul 2026: 13JulAug 2026: 19Sep 2026: 15
The same numbers as a table
MonthPermits
Oct 202416
Nov 202423
Dec 202411
Jan 202510
Feb 20254
Mar 202521
Apr 202528
May 202516
Jun 202530
Jul 20256
Aug 20258
Sep 202515
Oct 202524
Nov 20256
Dec 20258
Jan 20267
Feb 202615
Mar 202631
Apr 202626
May 20266
Jun 202634
Jul 202613
Aug 202619
Sep 202615

Download this table (CSV)

When new home permits are filed

By calendar month, 100 = an average month (the thin line). June is the busiest (196), January the quietest (52). A busy month at the permit counter usually means a longer wait for a contractor.

January: 52 (100 = an average month)February: 58 (100 = an average month)March: 159 (100 = an average month)April: 165 (100 = an average month)May: 67 (100 = an average month)June: 196 (100 = an average month)196July: 58 (100 = an average month)August: 83 (100 = an average month)September: 92 (100 = an average month)October: 122 (100 = an average month)November: 89 (100 = an average month)December: 58 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January52
February58
March159
April165
May67
June196
July58
August83
September92
October122
November89
December58

Download this table (CSV)

How long a new home permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 183 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 2025188
Finished97.3%
Expired0.0%
Usual days, issue to final161
Middle half, days104–259

Download this table (CSV)

What a new home permit is declared at

The value written on the permit at application, from 392 permits with one. Not a quote and not the final bill.

MeasureValue
Usual declared value$180,000
Middle half$125,000–$250,000

Download this table (CSV)

The city's own permit types

How the city filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
Building / New construction37195%
Manuf housing215%

Download this table (CSV)

How Lynchburg compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

How these numbers are made

Source: City of Lynchburg GIS open data, Building Permits - Tabluar (ODPDynamic MapServer layer 37, from the city's TRAKiT permit system), read 20 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Building and trade permits the City of Lynchburg Department of Community Development issued inside the city. Lynchburg is an independent city; homes with a Lynchburg mailing address in Bedford, Campbell or Amherst County get their permits from those counties and are not in this file.

  • The city's file names no contractor, so there are no contractor lists, rankings or firm pages for Lynchburg.
  • The file has no homes-versus-other flag on building permits, so a permit counts as a home when its parcel is a residential property class (or when it is a residential EZ permit).
  • Kinds of work within building permits (roofing, decks and garages, pools, fences) are picked out by the short job name.
  • Job value is the value declared on the permit; many trade permits carry none. A final date is the city's end date on a finaled permit.
  • The file has no ZIP code, so there are no ZIP code pages.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "New home permits in Lynchburg, VA", https://contractorrecords.com/lynchburg/new-home-permits, data through September 2026, from City of Lynchburg Community Development building-permit records.

Link to a table: By month · Season · Days to final · Declared value · Permit types.

Download the tables (CSV): New homes permits by month · New homes permits by calendar month (index) · New homes permits: days to final · New homes permits: declared value · New homes permits by permit type.

Common questions

  • How many new home permits does Lynchburg issue a year?About 196 a year in Lynchburg: 392 permits issued October 2024 through September 2026, 204 of them in the last 12 months.
  • How long does a new home permit take in Lynchburg?The usual one took 161 days from issue to the city's final inspection, and the middle half took 104 to 259 days (183 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Lynchburg file the most new home permits?June (196 against an average month of 100); January is the quietest (52). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.