Solar permits in Lynchburg, VA

Data through September 2026 · updated 20 Oct 2026

256 solar permits were issued in Lynchburg, October 2024 through September 2026: about 128 a year and 9% of all permits. 126 solar permits in the last 12 months (Oct 2025–Sep 2026), 3% fewer than the 130 in the 12 months before. The busiest month is July. The usual one took 64 days from issue to the city's final.

256permits issued
126last 12 months
Julbusiest month
64days, usual issue to final
96%finished
$27,074usual declared value
Sep 2026records through

Solar permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 8Oct2024Nov 2024: 13Dec 2024: 5Jan 2025: 5Jan2025Feb 2025: 4Mar 2025: 10Apr 2025: 11May 2025: 23Jun 2025: 18Jul 2025: 18JulAug 2025: 8Sep 2025: 7Oct 2025: 22Nov 2025: 13Dec 2025: 9Jan 2026: 4Jan2026Feb 2026: 6Mar 2026: 8Apr 2026: 21May 2026: 7Jun 2026: 8Jul 2026: 17JulAug 2026: 7Sep 2026: 4
The same numbers as a table
MonthPermits
Oct 20248
Nov 202413
Dec 20245
Jan 20255
Feb 20254
Mar 202510
Apr 202511
May 202523
Jun 202518
Jul 202518
Aug 20258
Sep 20257
Oct 202522
Nov 202513
Dec 20259
Jan 20264
Feb 20266
Mar 20268
Apr 202621
May 20267
Jun 20268
Jul 202617
Aug 20267
Sep 20264

Download this table (CSV)

When solar permits are filed

By calendar month, 100 = an average month (the thin line). July is the busiest (164), January the quietest (42). A busy month at the permit counter usually means a longer wait for a contractor.

January: 42 (100 = an average month)February: 47 (100 = an average month)March: 84 (100 = an average month)April: 150 (100 = an average month)May: 141 (100 = an average month)June: 122 (100 = an average month)July: 164 (100 = an average month)164August: 70 (100 = an average month)September: 52 (100 = an average month)October: 141 (100 = an average month)November: 122 (100 = an average month)December: 66 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January42
February47
March84
April150
May141
June122
July164
August70
September52
October141
November122
December66

Download this table (CSV)

How long a solar permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 125 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 2025130
Finished96.2%
Expired0.8%
Usual days, issue to final64
Middle half, days35–90

Download this table (CSV)

What a solar permit is declared at

The value written on the permit at application, from 256 permits with one. Not a quote and not the final bill.

MeasureValue
Usual declared value$27,074
Middle half$19,330–$36,018

Download this table (CSV)

The city's own permit types

How the city filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
Building / Renovation24395%
Building / Addition104%
Electrical residential EZ permit1under 1%
Building / Repair1under 1%
Electrical1under 1%

Download this table (CSV)

How Lynchburg compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

How these numbers are made

Source: City of Lynchburg GIS open data, Building Permits - Tabluar (ODPDynamic MapServer layer 37, from the city's TRAKiT permit system), read 20 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Building and trade permits the City of Lynchburg Department of Community Development issued inside the city. Lynchburg is an independent city; homes with a Lynchburg mailing address in Bedford, Campbell or Amherst County get their permits from those counties and are not in this file.

  • The city's file names no contractor, so there are no contractor lists, rankings or firm pages for Lynchburg.
  • The file has no homes-versus-other flag on building permits, so a permit counts as a home when its parcel is a residential property class (or when it is a residential EZ permit).
  • Kinds of work within building permits (roofing, decks and garages, pools, fences) are picked out by the short job name.
  • Job value is the value declared on the permit; many trade permits carry none. A final date is the city's end date on a finaled permit.
  • The file has no ZIP code, so there are no ZIP code pages.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Solar permits in Lynchburg, VA", https://contractorrecords.com/lynchburg/solar-permits, data through September 2026, from City of Lynchburg Community Development building-permit records.

Link to a table: By month · Season · Days to final · Declared value · Permit types.

Download the tables (CSV): Solar permits by month · Solar permits by calendar month (index) · Solar permits: days to final · Solar permits: declared value · Solar permits by permit type.

Common questions

  • How many solar permits does Lynchburg issue a year?About 128 a year in Lynchburg: 256 permits issued October 2024 through September 2026, 126 of them in the last 12 months.
  • How long does a solar permit take in Lynchburg?The usual one took 64 days from issue to the city's final inspection, and the middle half took 35 to 90 days (125 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Lynchburg file the most solar permits?July (164 against an average month of 100); January is the quietest (42). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.