Demolition permits in the City of Miami Beach, FL

Data through September 2026 · updated 20 Oct 2026

336 demolition permits were issued in the City of Miami Beach, October 2024 through September 2026: about 168 a year and 2% of all permits. 189 demolition permits in the last 12 months (Oct 2025–Sep 2026), 29% more than the 147 in the 12 months before. The busiest month is October. The usual one took 130 days from issue to the city's final. 33140 has the most, 154.

336permits issued
189last 12 months
Octbusiest month
130days, usual issue to final
54%finished
Sep 2026records through

Demolition permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 17Oct2024Nov 2024: 9Dec 2024: 8Jan 2025: 13Jan2025Feb 2025: 11Mar 2025: 10Apr 2025: 11May 2025: 16Jun 2025: 6Jul 2025: 11JulAug 2025: 21Sep 2025: 14Oct 2025: 20Nov 2025: 16Dec 2025: 16Jan 2026: 20Jan2026Feb 2026: 9Mar 2026: 14Apr 2026: 24May 2026: 15Jun 2026: 18Jul 2026: 12JulAug 2026: 13Sep 2026: 12
The same numbers as a table
MonthPermits
Oct 202417
Nov 20249
Dec 20248
Jan 202513
Feb 202511
Mar 202510
Apr 202511
May 202516
Jun 20256
Jul 202511
Aug 202521
Sep 202514
Oct 202520
Nov 202516
Dec 202516
Jan 202620
Feb 20269
Mar 202614
Apr 202624
May 202615
Jun 202618
Jul 202612
Aug 202613
Sep 202612

Download this table (CSV)

When demolition permits are filed

By calendar month, 100 = an average month (the thin line). October is the busiest (132), February the quietest (71). A busy month at the permit counter usually means a longer wait for a contractor.

January: 118 (100 = an average month)February: 71 (100 = an average month)March: 86 (100 = an average month)April: 125 (100 = an average month)May: 111 (100 = an average month)June: 86 (100 = an average month)July: 82 (100 = an average month)August: 121 (100 = an average month)September: 93 (100 = an average month)October: 132 (100 = an average month)132November: 89 (100 = an average month)December: 86 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January118
February71
March86
April125
May111
June86
July82
August121
September93
October132
November89
December86

Download this table (CSV)

How long a demolition permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 78 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 2025147
Finished53.7%
Expired6.1%
Usual days, issue to final130
Middle half, days47–268

Download this table (CSV)

ZIP codes with the most demolition permits

Counted at the property's ZIP code. Share is the part of the city's 336 demolition permits.

ZIP codePermitsShare
3314015446%
3314110331%
331397924%

Download this table (CSV)

The city's own permit types

How the city filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
Demolition Permit15045%
Building - Residential - Demolition13941%
Building - Commercial - Demolition309%
Electrical - Commercial - Demolition103%
Plumbing - Commercial - Demolition3under 1%
Electrical - Residential - Demolition3under 1%
Plumbing - Residential - Demolition1under 1%

Download this table (CSV)

Nearby permit data

Demolition permits for other places in South Florida. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: City of Miami Beach Civic Access (EnerGov) public permit search, read 20 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Building and trade permits the City of Miami Beach Building Department issues inside the city limits only. The City of Miami, Surfside, Bal Harbour and unincorporated Miami-Dade County run their own permit offices and are not in this file.

  • The city's public permit search names no contractor, so there are no contractor lists, rankings or firm pages for Miami Beach.
  • The search rows carry no job value, so we show no costs.
  • Trade work on a larger job is often filed as its own sub-permit (electrical, plumbing, mechanical), so one job can count several times.
  • Homes are permits the city files as single-family or duplex work, plus interior work inside a single condominium unit. Work on a whole condominium building is filed as commercial and is not counted as homes.
  • Revisions, certificates of occupancy, parking-space rentals, roll-off dumpsters, special events and right-of-way permits are left out.
  • A final date is the date the permit was finaled or closed.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Demolition permits in the City of Miami Beach, FL", https://contractorrecords.com/miami-beach/demolition-permits, data through September 2026, from the City of Miami Beach Building Department building-permit records.

Link to a table: By month · Season · Days to final · By ZIP code · Permit types.

Download the tables (CSV): Demolition permits by month · Demolition permits by calendar month (index) · Demolition permits: days to final · Demolition permits by ZIP code · Demolition permits by permit type.

Common questions

  • How many demolition permits does Miami Beach issue a year?About 168 a year in the City of Miami Beach: 336 permits issued October 2024 through September 2026, 189 of them in the last 12 months.
  • How long does a demolition permit take in Miami Beach?The usual one took 130 days from issue to the city's final inspection, and the middle half took 47 to 268 days (78 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Miami Beach file the most demolition permits?October (132 against an average month of 100); February is the quietest (71). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.
  • Which ZIP code has the most demolition permits in Miami Beach?33140, with 154 of the 336 (46%); then 33141 (103).