Plumbing permits in the City of Miami Beach, FL

Data through September 2026 · updated 20 Oct 2026

3,546 plumbing permits were issued in the City of Miami Beach, October 2024 through September 2026: about 1,773 a year and 17% of all permits. 1,817 plumbing permits in the last 12 months (Oct 2025–Sep 2026), 5% more than the 1,729 in the 12 months before. The busiest month is July. The usual one took 124 days from issue to the city's final. 33139 has the most, 1,643.

3,546permits issued
1,817last 12 months
Julbusiest month
124days, usual issue to final
78%finished
Sep 2026records through

Plumbing permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 148Oct2024Nov 2024: 137Dec 2024: 102Jan 2025: 127Jan2025Feb 2025: 139Mar 2025: 155Apr 2025: 159May 2025: 146Jun 2025: 138Jul 2025: 172JulAug 2025: 134Sep 2025: 172Oct 2025: 177Nov 2025: 107Dec 2025: 154Jan 2026: 152Jan2026Feb 2026: 156Mar 2026: 159Apr 2026: 143May 2026: 130Jun 2026: 147Jul 2026: 156JulAug 2026: 181Sep 2026: 155
The same numbers as a table
MonthPermits
Oct 2024148
Nov 2024137
Dec 2024102
Jan 2025127
Feb 2025139
Mar 2025155
Apr 2025159
May 2025146
Jun 2025138
Jul 2025172
Aug 2025134
Sep 2025172
Oct 2025177
Nov 2025107
Dec 2025154
Jan 2026152
Feb 2026156
Mar 2026159
Apr 2026143
May 2026130
Jun 2026147
Jul 2026156
Aug 2026181
Sep 2026155

Download this table (CSV)

When plumbing permits are filed

By calendar month, 100 = an average month (the thin line). July is the busiest (111), November the quietest (83). A busy month at the permit counter usually means a longer wait for a contractor.

January: 94 (100 = an average month)February: 100 (100 = an average month)March: 106 (100 = an average month)April: 102 (100 = an average month)May: 93 (100 = an average month)June: 96 (100 = an average month)July: 111 (100 = an average month)111August: 107 (100 = an average month)September: 111 (100 = an average month)October: 110 (100 = an average month)November: 83 (100 = an average month)December: 87 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January94
February100
March106
April102
May93
June96
July111
August107
September111
October110
November83
December87

Download this table (CSV)

How long a plumbing permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 1,350 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 20251,729
Finished78.2%
Expired3.9%
Usual days, issue to final124
Middle half, days49–249

Download this table (CSV)

ZIP codes with the most plumbing permits

Counted at the property's ZIP code. Share is the part of the city's 3,546 plumbing permits.

ZIP codePermitsShare
331391,64346%
331401,22735%
3314165218%
3310910under 1%
331541under 1%

Download this table (CSV)

The city's own permit types

How the city filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
Sub-Permit- Commercial - Plumbing - New Installations (including condominiums)78722%
Plumbing Sub-Permit Commercial General Primary Sub Permit55016%
Sub-Permit- Commercial - Plumbing - Alterations (including condominiums)44312%
Sub-Permit- Residential - Plumbing - New Installations (single family or duplex)40011%
Plumbing - Commercial - Alteration3199%
Plumbing Sub-Permit Residential General Primary Sub Permit1725%
Plumbing - Commercial - New1605%
Plumbing Sub-Permit Residential Pool Piping742%
Plumbing Sub-Permit Residential Well732%
Plumbing - Residential - Fuel Gas652%

Download this table (CSV)

How Miami Beach compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

Nearby permit data

Plumbing permits for other places in South Florida. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: City of Miami Beach Civic Access (EnerGov) public permit search, read 20 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Building and trade permits the City of Miami Beach Building Department issues inside the city limits only. The City of Miami, Surfside, Bal Harbour and unincorporated Miami-Dade County run their own permit offices and are not in this file.

  • The city's public permit search names no contractor, so there are no contractor lists, rankings or firm pages for Miami Beach.
  • The search rows carry no job value, so we show no costs.
  • Trade work on a larger job is often filed as its own sub-permit (electrical, plumbing, mechanical), so one job can count several times.
  • Homes are permits the city files as single-family or duplex work, plus interior work inside a single condominium unit. Work on a whole condominium building is filed as commercial and is not counted as homes.
  • Revisions, certificates of occupancy, parking-space rentals, roll-off dumpsters, special events and right-of-way permits are left out.
  • A final date is the date the permit was finaled or closed.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Plumbing permits in the City of Miami Beach, FL", https://contractorrecords.com/miami-beach/plumbing-permits, data through September 2026, from the City of Miami Beach Building Department building-permit records.

Link to a table: By month · Season · Days to final · By ZIP code · Permit types.

Download the tables (CSV): Plumbing permits by month · Plumbing permits by calendar month (index) · Plumbing permits: days to final · Plumbing permits by ZIP code · Plumbing permits by permit type.

Common questions

  • How many plumbing permits does Miami Beach issue a year?About 1,773 a year in the City of Miami Beach: 3,546 permits issued October 2024 through September 2026, 1,817 of them in the last 12 months.
  • How long does a plumbing permit take in Miami Beach?The usual one took 124 days from issue to the city's final inspection, and the middle half took 49 to 249 days (1,350 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Miami Beach file the most plumbing permits?July (111 against an average month of 100); November is the quietest (83). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.
  • Which ZIP code has the most plumbing permits in Miami Beach?33139, with 1,643 of the 3,546 (46%); then 33140 (1,227).