Remodel and repair permits in the City of Miami Beach, FL

Data through September 2026 · updated 20 Oct 2026

2,692 remodel and repair permits were issued in the City of Miami Beach, October 2024 through September 2026: about 1,346 a year and 13% of all permits. 1,248 remodel and repair permits in the last 12 months (Oct 2025–Sep 2026), 14% fewer than the 1,444 in the 12 months before. The busiest month is August. The usual one took 161 days from issue to the city's final. 33140 has the most, 1,067.

2,692permits issued
1,248last 12 months
Augbusiest month
161days, usual issue to final
78%finished
Sep 2026records through

Remodel and repair permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 128Oct2024Nov 2024: 116Dec 2024: 115Jan 2025: 97Jan2025Feb 2025: 84Mar 2025: 117Apr 2025: 138May 2025: 140Jun 2025: 121Jul 2025: 133JulAug 2025: 141Sep 2025: 114Oct 2025: 117Nov 2025: 99Dec 2025: 98Jan 2026: 91Jan2026Feb 2026: 106Mar 2026: 81Apr 2026: 102May 2026: 97Jun 2026: 114Jul 2026: 105JulAug 2026: 120Sep 2026: 118
The same numbers as a table
MonthPermits
Oct 2024128
Nov 2024116
Dec 2024115
Jan 202597
Feb 202584
Mar 2025117
Apr 2025138
May 2025140
Jun 2025121
Jul 2025133
Aug 2025141
Sep 2025114
Oct 2025117
Nov 202599
Dec 202598
Jan 202691
Feb 2026106
Mar 202681
Apr 2026102
May 202697
Jun 2026114
Jul 2026105
Aug 2026120
Sep 2026118

Download this table (CSV)

When remodel and repair permits are filed

By calendar month, 100 = an average month (the thin line). August is the busiest (116), January the quietest (84). A busy month at the permit counter usually means a longer wait for a contractor.

January: 84 (100 = an average month)February: 85 (100 = an average month)March: 88 (100 = an average month)April: 107 (100 = an average month)May: 106 (100 = an average month)June: 105 (100 = an average month)July: 106 (100 = an average month)August: 116 (100 = an average month)116September: 103 (100 = an average month)October: 109 (100 = an average month)November: 96 (100 = an average month)December: 95 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January84
February85
March88
April107
May106
June105
July106
August116
September103
October109
November96
December95

Download this table (CSV)

How long a remodel and repair permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 1,123 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 20251,444
Finished78.4%
Expired6.3%
Usual days, issue to final161
Middle half, days74–275

Download this table (CSV)

ZIP codes with the most remodel and repair permits

Counted at the property's ZIP code. Share is the part of the city's 2,692 remodel and repair permits.

ZIP codePermitsShare
331401,06740%
331391,06640%
3314155120%
331094under 1%

Download this table (CSV)

The city's own permit types

How the city filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
Building – Condominium - Interior Alteration Non-Structural1,25447%
Residential (Single-Family) - Alterations2439%
Building - Residential - Windows/Doors2148%
Individual unit flooring replacement (no bathroom/no balcony)1987%
Building - Residential - Marine1736%
Building - Residential - Windows/Curtain Walls/Storefronts/Glass Glazing1204%
Building Sub Permit Residential Windows/Curtain Walls/Storefronts/Glass Glazing1074%
Building - Residential - Driveway/Approach964%
Building - Residential - Doors703%
Building - Residential - Railings592%

Download this table (CSV)

How Miami Beach compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

Nearby permit data

Remodel and repair permits for other places in South Florida. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: City of Miami Beach Civic Access (EnerGov) public permit search, read 20 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Building and trade permits the City of Miami Beach Building Department issues inside the city limits only. The City of Miami, Surfside, Bal Harbour and unincorporated Miami-Dade County run their own permit offices and are not in this file.

  • The city's public permit search names no contractor, so there are no contractor lists, rankings or firm pages for Miami Beach.
  • The search rows carry no job value, so we show no costs.
  • Trade work on a larger job is often filed as its own sub-permit (electrical, plumbing, mechanical), so one job can count several times.
  • Homes are permits the city files as single-family or duplex work, plus interior work inside a single condominium unit. Work on a whole condominium building is filed as commercial and is not counted as homes.
  • Revisions, certificates of occupancy, parking-space rentals, roll-off dumpsters, special events and right-of-way permits are left out.
  • A final date is the date the permit was finaled or closed.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Remodel and repair permits in the City of Miami Beach, FL", https://contractorrecords.com/miami-beach/remodel-permits, data through September 2026, from the City of Miami Beach Building Department building-permit records.

Link to a table: By month · Season · Days to final · By ZIP code · Permit types.

Download the tables (CSV): Remodels & repairs permits by month · Remodels & repairs permits by calendar month (index) · Remodels & repairs permits: days to final · Remodels & repairs permits by ZIP code · Remodels & repairs permits by permit type.

Common questions

  • How many remodel and repair permits does Miami Beach issue a year?About 1,346 a year in the City of Miami Beach: 2,692 permits issued October 2024 through September 2026, 1,248 of them in the last 12 months.
  • How long does a remodel and repair permit take in Miami Beach?The usual one took 161 days from issue to the city's final inspection, and the middle half took 74 to 275 days (1,123 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Miami Beach file the most remodel and repair permits?August (116 against an average month of 100); January is the quietest (84). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.
  • Which ZIP code has the most remodel and repair permits in Miami Beach?33140, with 1,067 of the 2,692 (40%); then 33139 (1,066).