Naperville, IL building permit statistics

7,312 permits from 1,531 contractors across 13 kinds of work in the City of Naperville, October 2023 through September 2026: about 2,437 a year. Fence is the biggest trade with 1,331 permits. The busiest month for filings is April.

7,312permits read
1,531contractors on record
13kinds of work
Aprbusiest month
Sep 2026records through

By trade

Firms are distinct business names on the file. A linked usual filed value opens what that work costs. Finished is the share of permits a year or more old that the city closed out. Days to finish run from issue to the city's completion date, not from application.

TradePermitsFirmsActive last 12 moUsual filed valueFinishedDays to finishBusiest month
Fence1,33110540$6,20045.0%405April
Driveway & Sidewalk1,175258105$4,49876.0%99April
Remodel & Repair1,057467240$46,30078.5%175May
New Home9559239$255,60014.0%672July
Electrical66819662$2,00064.8%144October
Deck, Pergola & Gazebo34815253$25,00075.5%169April
Solar3415726$21,45078.2%107November
Lawn Irrigation3005529$6,48535.4%—April
Addition29918974$94,50065.3%422October
EV Charger2667032$1,60069.9%59January
Patio25215549$25,84259.9%355May
Plumbing & Sewer2099448$6,50068.4%360November
Pool & Hot Tub1116926$89,05028.8%418July

Permits by year

The file we publish splits exactly into the last 12 months on file and the 24 months before them, so these are 12-month periods ending September 2026, not calendar years. Per year scales each period to 12 months. Counts cover the 13 kinds of home work we track, not every permit Naperville issues.

PeriodMonthsPermitsPer year
Oct 2023–Sep 2025245,2092,604
Oct 2025–Sep 2026 (last 12 months)122,1032,103

By month

Share of filings by month, 100 = an average month (the thin line). The 6 biggest trades, October 2023 through September 2026. A tall bar is a busy month at the permit counter, which usually means a longer wait for a contractor.

Fence

1,331 permits · busiest April, quietest January

January: 16 (100 = an average month)February: 35 (100 = an average month)March: 95 (100 = an average month)April: 188 (100 = an average month)188May: 126 (100 = an average month)June: 157 (100 = an average month)July: 104 (100 = an average month)August: 127 (100 = an average month)September: 92 (100 = an average month)October: 119 (100 = an average month)November: 104 (100 = an average month)December: 38 (100 = an average month)JFMAMJJASOND

Driveway & Sidewalk

1,175 permits · busiest April, quietest December

January: 6 (100 = an average month)February: 17 (100 = an average month)March: 36 (100 = an average month)April: 216 (100 = an average month)216May: 133 (100 = an average month)June: 156 (100 = an average month)July: 110 (100 = an average month)August: 154 (100 = an average month)September: 185 (100 = an average month)October: 161 (100 = an average month)November: 21 (100 = an average month)December: 3 (100 = an average month)JFMAMJJASOND

Remodel & Repair

1,057 permits · busiest May, quietest November

January: 98 (100 = an average month)February: 92 (100 = an average month)March: 100 (100 = an average month)April: 111 (100 = an average month)May: 118 (100 = an average month)118June: 96 (100 = an average month)July: 89 (100 = an average month)August: 108 (100 = an average month)September: 96 (100 = an average month)October: 114 (100 = an average month)November: 86 (100 = an average month)December: 92 (100 = an average month)JFMAMJJASOND

New Home

955 permits · busiest July, quietest October

January: 88 (100 = an average month)February: 109 (100 = an average month)March: 137 (100 = an average month)April: 114 (100 = an average month)May: 103 (100 = an average month)June: 78 (100 = an average month)July: 158 (100 = an average month)158August: 92 (100 = an average month)September: 63 (100 = an average month)October: 48 (100 = an average month)November: 97 (100 = an average month)December: 113 (100 = an average month)JFMAMJJASOND

Electrical

668 permits · busiest October, quietest September

January: 70 (100 = an average month)February: 92 (100 = an average month)March: 97 (100 = an average month)April: 97 (100 = an average month)May: 95 (100 = an average month)June: 115 (100 = an average month)July: 88 (100 = an average month)August: 106 (100 = an average month)September: 61 (100 = an average month)October: 156 (100 = an average month)156November: 133 (100 = an average month)December: 90 (100 = an average month)JFMAMJJASOND

Deck, Pergola & Gazebo

348 permits · busiest April, quietest January

January: 17 (100 = an average month)February: 52 (100 = an average month)March: 38 (100 = an average month)April: 169 (100 = an average month)169May: 134 (100 = an average month)June: 159 (100 = an average month)July: 103 (100 = an average month)August: 131 (100 = an average month)September: 121 (100 = an average month)October: 103 (100 = an average month)November: 114 (100 = an average month)December: 59 (100 = an average month)JFMAMJJASOND
The same numbers as a table
TradeJanFebMarAprMayJunJulAugSepOctNovDec
Fence1635951881261571041279211910438
Driveway & Sidewalk61736216133156110154185161213
Remodel & Repair98921001111189689108961148692
New Home881091371141037815892634897113
Electrical7092979795115881066115613390
Deck, Pergola & Gazebo17523816913415910313112110311459

When Naperville schedules each kind of work

For each trade, the month with the most permit filings and the month with the fewest, October 2023 through September 2026. Trades do not all peak together, so the busy season depends on the job. Busiest is not the same as best: these are counts of filings, not prices or weather, though a quiet month at the permit counter can mean contractors have more room in the schedule.

When is the busiest season for fence companies in Naperville?

April: Naperville fence permits peak in April (188 against an average month of 100, about 16% of a year's filings); January is the quietest (16). That is from 1,331 permits, October 2023 through September 2026. If you can choose when to schedule fence installation, January has the fewest filings; the usual permit then takes 405 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the fence chart →

When is the busiest season for driveway contractors in Naperville?

April: Naperville driveway & sidewalk permits peak in April (216 against an average month of 100, about 18% of a year's filings); December is the quietest (3). That is from 1,175 permits, October 2023 through September 2026. If you can choose when to schedule driveway work, December has the fewest filings; the usual permit then takes 99 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the driveway & sidewalk chart →

When is the busiest season for remodeling contractors in Naperville?

May: Naperville remodel & repair permits peak in May (118 against an average month of 100, about 10% of a year's filings); November is the quietest (86). That is from 1,057 permits, October 2023 through September 2026. If you can choose when to schedule a home remodel, November has the fewest filings; the usual permit then takes 175 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the remodel & repair chart →

When is the busiest season for home builders in Naperville?

July: Naperville new home permits peak in July (158 against an average month of 100, about 13% of a year's filings); October is the quietest (48). That is from 955 permits, October 2023 through September 2026. If you can choose when to schedule new home construction, October has the fewest filings; the usual permit then takes 672 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the new home chart →

When is the busiest season for electricians in Naperville?

October: Naperville electrical permits peak in October (156 against an average month of 100, about 13% of a year's filings); September is the quietest (61). That is from 668 permits, October 2023 through September 2026. If you can choose when to schedule electrical work, September has the fewest filings; the usual permit then takes 144 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the electrical chart →

When is the busiest season for deck builders in Naperville?

April: Naperville deck, pergola & gazebo permits peak in April (169 against an average month of 100, about 14% of a year's filings); January is the quietest (17). That is from 348 permits, October 2023 through September 2026. If you can choose when to schedule a deck build, January has the fewest filings; the usual permit then takes 169 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the deck, pergola & gazebo chart →

When is the busiest season for solar installers in Naperville?

November: Naperville solar permits peak in November (274 against an average month of 100, about 23% of a year's filings); July is the quietest (28). That is from 341 permits, October 2023 through September 2026. If you can choose when to schedule solar installation, July has the fewest filings; the usual permit then takes 107 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month.

When is the busiest season for irrigation contractors in Naperville?

April: Naperville lawn irrigation permits peak in April (220 against an average month of 100, about 18% of a year's filings); January is the quietest (8). That is from 300 permits, October 2023 through September 2026. If you can choose when to schedule irrigation work, January has the fewest filings. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month.

When is the busiest season for home addition contractors in Naperville?

October: Naperville addition permits peak in October (177 against an average month of 100, about 15% of a year's filings); March is the quietest (44). That is from 299 permits, October 2023 through September 2026. If you can choose when to schedule a home addition, March has the fewest filings; the usual permit then takes 422 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month.

When is the busiest season for EV charger installers in Naperville?

January: Naperville EV charger permits peak in January (171 against an average month of 100, about 14% of a year's filings); June is the quietest (50). That is from 266 permits, October 2023 through September 2026. If you can choose when to schedule EV charger installation, June has the fewest filings; the usual permit then takes 59 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month.

When is the busiest season for patio contractors in Naperville?

May: Naperville patio permits peak in May (200 against an average month of 100, about 17% of a year's filings); January is the quietest (5). That is from 252 permits, October 2023 through September 2026. If you can choose when to schedule patio work, January has the fewest filings; the usual permit then takes 355 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month.

When is the busiest season for plumbers in Naperville?

November: Naperville plumbing & sewer permits peak in November (166 against an average month of 100, about 14% of a year's filings); August is the quietest (57). That is from 209 permits, October 2023 through September 2026. If you can choose when to schedule plumbing work, August has the fewest filings; the usual permit then takes 360 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month.

When is the busiest season for pool builders in Naperville?

July: Naperville pool & hot tub permits peak in July (162 against an average month of 100, about 14% of a year's filings); January is the quietest (54). That is from 111 permits, October 2023 through September 2026. If you can choose when to schedule a pool build, January has the fewest filings; the usual permit then takes 418 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month.

Most active contractors in Naperville, last 12 months

Top 10 by permits pulled in the last 12 months, all trades. This is volume, not quality: a busy firm is not a careful one. Pick what you value on the compare page to build a ranking.

ContractorTradesLast 12 moAll permits
Pulte GroupNew Home, Electrical116486
KinzieNew Home107107
M/I HomesNew Home7988
Dubois Paving CoDriveway & Sidewalk4761
Reliable Home ImprovementRemodel & Repair, Addition3281
Spring Creek Landscape IncDriveway & Sidewalk3094
Twin Bros Paving & ConcreteDriveway & Sidewalk2735
Peerless Enterprises LLCFence2642
Ioc ConstructionDriveway & Sidewalk, Deck, Pergola & Gazebo2635
Paramount FenceFence25156

Permits by ZIP code

Each permit counted at its property's ZIP code, October 2023 through September 2026, for the 13 kinds of home work we track. All 4 ZIP codes with 100 or more permits; each opens permits by trade and the most active contractors there.

ZIP codePermitsShareTop tradeUsual home value
605642,12829%New Home$510,000
605402,06828%Fence$592,000
605651,62422%Fence$513,000
605631,48320%New Home$479,000

Naperville ZIP codes →

How these numbers are made

Source: City of Naperville building permits (the current permit system plus the city's older records). The window is October 2023 through September 2026; a permit filed after that isn't here yet.

A filed value is what the contractor wrote on the permit when they applied. It is not a quote and not the final bill.

Counts are permits, not jobs: one job can need several permits, and one permit can cover several visits.

Nobody paid to be on this page and nobody can. How the records work in Naperville →

Common questions

  • How many building permits does Naperville issue a year?About 2,437 a year for the 13 kinds of home work we track (7,312 permits over 36 months, October 2023 through September 2026); 2,103 in the last 12 months. That is not the city's count of every permit: it covers fence, driveway & sidewalk, remodel & repair, new home, electrical, deck, pergola & gazebo, solar, lawn irrigation, addition, EV charger, patio, plumbing & sewer, pool & hot tub, not commercial work or trades we don't read.
  • When should you schedule work in Naperville?If you can choose, book in a quiet month at the permit counter: for fence installation, January (busiest April); for driveway work, December (busiest April); for a home remodel, November (busiest May). Each trade has its own season; the questions above give every trade we track, with the usual days to sign-off.
  • Who are the most active contractors in Naperville?By permits pulled in the last 12 months: Pulte Group (116); Kinzie (107); M/I Homes (79). That is volume, not quality: compare finished share and filed values before you hire.
  • Which trade pulls the most permits in Naperville?Fence: 1,331 permits from 105 firms, with a usual filed value of $6,200.
  • What is the busiest month for permits in Naperville?April, counting every trade. January is the quietest. The chart above shows each trade; they do not all peak together.
  • How many contractors are active in Naperville?1,531 distinct business names appear on the file; 703 of them pulled at least one permit in the last 12 months.
  • How many permits get finished?For fence, 45.0% of permits a year or more old were closed out by the city. How long permits take in Naperville →
  • Where does this data come from?City of Naperville building permits (the current permit system plus the city's older records), read October 2026. How the records work in Naperville →

Other cities: Nashville Orlando New York City Chicago Austin Raleigh Cincinnati Cleveland Pittsburgh Miami Minneapolis St. Louis Denver San Diego Colorado Springs Honolulu Albuquerque Boulder Greensboro Saint Paul Arlington, VA Scottsdale Henderson Cambridge Somerville Cary Mesa Bellevue Cape Coral Provo Palo Alto Bellingham Bend Ames Denton Sugar Land Burlington, VT Seattle San Francisco Medford Anaheim Elk Grove Wilmington, NC Bismarck Tyler, TX Columbus, OH Wheaton, IL San Diego County (unincorporated) Marin County (unincorporated) Sacramento County (unincorporated) Citrus Heights, CA Waco, TX