Cleveland, OH building permit statistics

27,300 permits from 1,984 contractors across 12 kinds of work in the City of Cleveland, October 2023 through September 2026: about 9,100 a year. Plumbing is the biggest trade with 5,315 permits. The busiest month for filings is October.

27,300permits read
1,984contractors on record
12kinds of work
Octbusiest month
Sep 2026records through

By trade

Firms are distinct business names on the file. A linked usual filed value opens what that work costs. Finished is the share of permits a year or more old that the city closed out. Days to finish run from issue to the city's completion date, not from application.

TradePermitsFirmsActive last 12 moUsual filed valueFinishedDays to finishBusiest month
Plumbing5,315296172$2,50058.7%234March
Roofing4,923586298$10,50078.0%91October
HVAC4,916235144$5,70681.1%142December
Electrical4,049361225$3,00064.5%146October
Windows & Doors2,938236116$5,90075.5%140June
Demolition1,57212059$9,00093.0%42April
Remodel & Repair1,443556236$17,46557.5%391July
Fence8907924$4,24274.9%168May
Siding45114864$13,86674.7%159July
New Home3436528$250,00082.1%344September
Garage3039449$22,27582.6%139October
Solar1572512$13,57870.9%185October

Permits by year

The file we publish splits exactly into the last 12 months on file and the 24 months before them, so these are 12-month periods ending September 2026, not calendar years. Per year scales each period to 12 months. Counts cover the 12 kinds of home work we track, not every permit Cleveland issues.

PeriodMonthsPermitsPer year
Oct 2023–Sep 20252418,7159,358
Oct 2025–Sep 2026 (last 12 months)128,5858,585

By month

Share of filings by month, 100 = an average month (the thin line). The 8 biggest trades (every trade with 500 or more permits), October 2023 through September 2026. A tall bar is a busy month at the permit counter, which usually means a longer wait for a contractor.

Plumbing

5,315 permits · busiest March, quietest January

January: 70 (100 = an average month)February: 105 (100 = an average month)March: 129 (100 = an average month)129April: 110 (100 = an average month)May: 94 (100 = an average month)June: 95 (100 = an average month)July: 113 (100 = an average month)August: 88 (100 = an average month)September: 98 (100 = an average month)October: 96 (100 = an average month)November: 100 (100 = an average month)December: 103 (100 = an average month)JFMAMJJASOND

Roofing

4,923 permits · busiest October, quietest January

January: 35 (100 = an average month)February: 46 (100 = an average month)March: 95 (100 = an average month)April: 102 (100 = an average month)May: 119 (100 = an average month)June: 121 (100 = an average month)July: 129 (100 = an average month)August: 121 (100 = an average month)September: 126 (100 = an average month)October: 135 (100 = an average month)135November: 114 (100 = an average month)December: 58 (100 = an average month)JFMAMJJASOND

HVAC

4,916 permits · busiest December, quietest January

January: 72 (100 = an average month)February: 104 (100 = an average month)March: 112 (100 = an average month)April: 114 (100 = an average month)May: 81 (100 = an average month)June: 94 (100 = an average month)July: 101 (100 = an average month)August: 101 (100 = an average month)September: 92 (100 = an average month)October: 104 (100 = an average month)November: 106 (100 = an average month)December: 119 (100 = an average month)119JFMAMJJASOND

Electrical

4,049 permits · busiest October, quietest January

January: 71 (100 = an average month)February: 95 (100 = an average month)March: 112 (100 = an average month)April: 106 (100 = an average month)May: 105 (100 = an average month)June: 87 (100 = an average month)July: 107 (100 = an average month)August: 104 (100 = an average month)September: 102 (100 = an average month)October: 123 (100 = an average month)123November: 97 (100 = an average month)December: 92 (100 = an average month)JFMAMJJASOND

Windows & Doors

2,938 permits · busiest June, quietest January

January: 36 (100 = an average month)February: 81 (100 = an average month)March: 93 (100 = an average month)April: 105 (100 = an average month)May: 101 (100 = an average month)June: 131 (100 = an average month)131July: 115 (100 = an average month)August: 107 (100 = an average month)September: 105 (100 = an average month)October: 120 (100 = an average month)November: 120 (100 = an average month)December: 87 (100 = an average month)JFMAMJJASOND

Demolition

1,572 permits · busiest April, quietest June

January: 72 (100 = an average month)February: 91 (100 = an average month)March: 121 (100 = an average month)April: 131 (100 = an average month)131May: 80 (100 = an average month)June: 69 (100 = an average month)July: 97 (100 = an average month)August: 94 (100 = an average month)September: 123 (100 = an average month)October: 107 (100 = an average month)November: 98 (100 = an average month)December: 117 (100 = an average month)JFMAMJJASOND

Remodel & Repair

1,443 permits · busiest July, quietest January

January: 60 (100 = an average month)February: 91 (100 = an average month)March: 106 (100 = an average month)April: 102 (100 = an average month)May: 98 (100 = an average month)June: 86 (100 = an average month)July: 124 (100 = an average month)124August: 122 (100 = an average month)September: 120 (100 = an average month)October: 113 (100 = an average month)November: 90 (100 = an average month)December: 88 (100 = an average month)JFMAMJJASOND

Fence

890 permits · busiest May, quietest January

January: 26 (100 = an average month)February: 55 (100 = an average month)March: 71 (100 = an average month)April: 117 (100 = an average month)May: 145 (100 = an average month)145June: 145 (100 = an average month)July: 113 (100 = an average month)August: 121 (100 = an average month)September: 110 (100 = an average month)October: 145 (100 = an average month)November: 93 (100 = an average month)December: 60 (100 = an average month)JFMAMJJASOND
The same numbers as a table
TradeJanFebMarAprMayJunJulAugSepOctNovDec
Plumbing701051291109495113889896100103
Roofing35469510211912112912112613511458
HVAC72104112114819410110192104106119
Electrical7195112106105871071041021239792
Windows & Doors36819310510113111510710512012087
Demolition72911211318069979412310798117
Remodel & Repair609110610298861241221201139088
Fence2655711171451451131211101459360

When Cleveland schedules each kind of work

For each trade, the month with the most permit filings and the month with the fewest, October 2023 through September 2026. Trades do not all peak together, so the busy season depends on the job. Busiest is not the same as best: these are counts of filings, not prices or weather, though a quiet month at the permit counter can mean contractors have more room in the schedule.

When is the busiest season for plumbers in Cleveland?

March: Cleveland plumbing permits peak in March (129 against an average month of 100, about 11% of a year's filings); January is the quietest (70). That is from 5,315 permits, October 2023 through September 2026. If you can choose when to schedule plumbing work, January has the fewest filings; the usual permit then takes 234 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the plumbing chart →

When is the busiest season for roofers in Cleveland?

October: Cleveland roofing permits peak in October (135 against an average month of 100, about 11% of a year's filings); January is the quietest (35). That is from 4,923 permits, October 2023 through September 2026. If you can choose when to schedule roofing work, January has the fewest filings; the usual permit then takes 91 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the roofing chart →

When is the busiest season for HVAC contractors in Cleveland?

December: Cleveland HVAC permits peak in December (119 against an average month of 100, about 10% of a year's filings); January is the quietest (72). That is from 4,916 permits, October 2023 through September 2026. If you can choose when to schedule HVAC work, January has the fewest filings; the usual permit then takes 142 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the HVAC chart →

When is the busiest season for electricians in Cleveland?

October: Cleveland electrical permits peak in October (123 against an average month of 100, about 10% of a year's filings); January is the quietest (71). That is from 4,049 permits, October 2023 through September 2026. If you can choose when to schedule electrical work, January has the fewest filings; the usual permit then takes 146 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the electrical chart →

When is the busiest season for window installers in Cleveland?

June: Cleveland windows & doors permits peak in June (131 against an average month of 100, about 11% of a year's filings); January is the quietest (36). That is from 2,938 permits, October 2023 through September 2026. If you can choose when to schedule window replacement, January has the fewest filings; the usual permit then takes 140 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the windows & doors chart →

When is the busiest season for demolition contractors in Cleveland?

April: Cleveland demolition permits peak in April (131 against an average month of 100, about 11% of a year's filings); June is the quietest (69). That is from 1,572 permits, October 2023 through September 2026. If you can choose when to schedule demolition, June has the fewest filings; the usual permit then takes 42 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the demolition chart →

When is the busiest season for remodeling contractors in Cleveland?

July: Cleveland remodel & repair permits peak in July (124 against an average month of 100, about 10% of a year's filings); January is the quietest (60). That is from 1,443 permits, October 2023 through September 2026. If you can choose when to schedule a home remodel, January has the fewest filings; the usual permit then takes 391 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the remodel & repair chart →

When is the busiest season for fence companies in Cleveland?

May: Cleveland fence permits peak in May (145 against an average month of 100, about 12% of a year's filings); January is the quietest (26). That is from 890 permits, October 2023 through September 2026. If you can choose when to schedule fence installation, January has the fewest filings; the usual permit then takes 168 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the fence chart →

When is the busiest season for siding contractors in Cleveland?

July: Cleveland siding permits peak in July (143 against an average month of 100, about 12% of a year's filings); January is the quietest (26). That is from 451 permits, October 2023 through September 2026. If you can choose when to schedule siding work, January has the fewest filings; the usual permit then takes 159 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month.

When is the busiest season for home builders in Cleveland?

September: Cleveland new home permits peak in September (220 against an average month of 100, about 18% of a year's filings); April is the quietest (31). That is from 343 permits, October 2023 through September 2026. If you can choose when to schedule new home construction, April has the fewest filings; the usual permit then takes 344 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month.

When is the busiest season for garage builders in Cleveland?

October: Cleveland garage permits peak in October (170 against an average month of 100, about 14% of a year's filings); January is the quietest (16). That is from 303 permits, October 2023 through September 2026. If you can choose when to schedule garage construction, January has the fewest filings; the usual permit then takes 139 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month.

When is the busiest season for solar installers in Cleveland?

October: Cleveland solar permits peak in October (222 against an average month of 100, about 18% of a year's filings); April is the quietest (23). That is from 157 permits, October 2023 through September 2026. If you can choose when to schedule solar installation, April has the fewest filings; the usual permit then takes 185 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month.

Most active contractors in Cleveland, last 12 months

Top 10 by permits pulled in the last 12 months, all trades. This is volume, not quality: a busy firm is not a careful one. Pick what you value on the compare page to build a ranking.

ContractorTradesLast 12 moAll permits
Sal's Heating & Cooling Inc.Plumbing, HVAC211593
Window Nation LLCRoofing, Windows & Doors167414
H. Jack's Plumbing & Heating Co of Mentor, Inc.Plumbing, HVAC146445
New Phoenix Enterprise Inc.Plumbing131387
Northlake Plumbing LLC.Plumbing, HVAC129273
By-Tor Contracting Inc.Roofing, Windows & Doors122341
Great Day Improvements, LLCRoofing, Windows & Doors, Remodel & Repair, Siding116126
Aba Builders LLCRoofing, Windows & Doors, Remodel & Repair, Siding114276
B.B.C. Electric Co, Inc.Electrical, New Home111403
Third Estimate CorporationRoofing, Windows & Doors, Siding108270

Permits by ZIP code

Each permit counted at its property's ZIP code, October 2023 through September 2026, for the 12 kinds of home work we track. The 10 busiest of 20 ZIP codes with 100 or more permits; each opens permits by trade and the most active contractors there.

ZIP codePermitsShareTop tradeUsual home value
441113,42913%Roofing$124,000
441022,98711%Plumbing$94,000
441092,5299%Roofing$118,000
441352,3839%Roofing$122,000
441052,1438%Plumbing$54,000
441201,9387%HVAC$62,000
441281,6016%Plumbing$81,000
441081,4935%Plumbing$49,000
441101,4815%Plumbing$60,000
441131,4285%HVAC$295,000

All 20 Cleveland ZIP codes →

How these numbers are made

Source: City of Cleveland building permits. The window is October 2023 through September 2026; a permit filed after that isn't here yet.

A filed value is what the contractor wrote on the permit when they applied. It is not a quote and not the final bill.

Counts are permits, not jobs: one job can need several permits, and one permit can cover several visits.

Nobody paid to be on this page and nobody can. How the records work in Cleveland →

Common questions

  • How many building permits does Cleveland issue a year?About 9,100 a year for the 12 kinds of home work we track (27,300 permits over 36 months, October 2023 through September 2026); 8,585 in the last 12 months. That is not the city's count of every permit: it covers plumbing, roofing, HVAC, electrical, windows & doors, demolition, remodel & repair, fence, siding, new home, garage, solar, not commercial work or trades we don't read.
  • When should you schedule work in Cleveland?If you can choose, book in a quiet month at the permit counter: for plumbing work, January (busiest March); for roofing work, January (busiest October); for HVAC work, January (busiest December). Each trade has its own season; the questions above give every trade we track, with the usual days to sign-off.
  • Who are the most active contractors in Cleveland?By permits pulled in the last 12 months: Sal's Heating & Cooling Inc. (211); Window Nation LLC (167); H. Jack's Plumbing & Heating Co of Mentor, Inc. (146). That is volume, not quality: compare finished share and filed values before you hire.
  • Which trade pulls the most permits in Cleveland?Plumbing: 5,315 permits from 296 firms, with a usual filed value of $2,500.
  • What is the busiest month for permits in Cleveland?October, counting every trade. January is the quietest. The chart above shows each trade; they do not all peak together.
  • How many contractors are active in Cleveland?1,984 distinct business names appear on the file; 1,088 of them pulled at least one permit in the last 12 months.
  • How many permits get finished?For plumbing, 58.7% of permits a year or more old were closed out by the city. How long permits take in Cleveland →
  • Where does this data come from?City of Cleveland building permits, read October 2026. How the records work in Cleveland →

Other cities: Nashville Orlando New York City Chicago Austin Raleigh Cincinnati Pittsburgh Miami Minneapolis St. Louis Denver San Diego Colorado Springs Honolulu Albuquerque Boulder Greensboro Saint Paul Arlington, VA Scottsdale Henderson Cambridge Somerville Cary Mesa Naperville Bellevue Cape Coral Provo Palo Alto Bellingham Bend Ames Denton Sugar Land Burlington, VT Seattle San Francisco Medford Anaheim Elk Grove Wilmington, NC Bismarck Tyler, TX Columbus, OH Wheaton, IL San Diego County (unincorporated) Marin County (unincorporated) Sacramento County (unincorporated) Citrus Heights, CA Waco, TX