Wheaton, IL building permit statistics

5,250 permits from 1,054 contractors across 12 kinds of work in the City of Wheaton, October 2023 through September 2026: about 1,750 a year. Heating & Cooling is the biggest trade with 1,060 permits. The busiest month for filings is October.

5,250permits read
1,054contractors on record
12kinds of work
Octbusiest month
23%firms matched to an active license
Sep 2026records through

By trade

Firms are distinct business names on the file. A linked usual filed value opens what that work costs. Finished is the share of permits a year or more old that the city closed out. Days to finish run from issue to the city's completion date, not from application.

TradePermitsFirmsActive last 12 moUsual filed valueFinishedDays to finishBusiest month
Heating & Cooling1,0606927$9,57847.4%398June
Roofing917295116$15,432——October
Windows & Doors63011043$12,90561.6%83September
Fence5527434$6,00380.7%375March
Driveway, Walk & Stoop4059633—74.2%279August
Electrical39811437$4,05052.1%159April
Remodel (Kitchen, Bath, Basement)28314254$44,06393.1%132October
Sewer & Water Service2617035—79.7%14October
Plumbing & Water Heater2176225$2,59970.8%34March
Patio18810024$15,47775.1%104June
Deck, Porch & Pergola1879128$18,95588.9%111September
Foundation & Waterproofing1523013$11,52984.9%83July

Permits by year

The file we publish splits exactly into the last 12 months on file and the 24 months before them, so these are 12-month periods ending September 2026, not calendar years. Per year scales each period to 12 months. Counts cover the 12 kinds of home work we track, not every permit Wheaton, IL issues.

PeriodMonthsPermitsPer year
Oct 2023–Sep 2025243,5571,778
Oct 2025–Sep 2026 (last 12 months)121,6931,693

By month

Share of filings by month, 100 = an average month (the thin line). The 6 biggest trades, October 2023 through September 2026. A tall bar is a busy month at the permit counter, which usually means a longer wait for a contractor.

Heating & Cooling

1,060 permits · busiest June, quietest February

January: 72 (100 = an average month)February: 68 (100 = an average month)March: 72 (100 = an average month)April: 69 (100 = an average month)May: 108 (100 = an average month)June: 142 (100 = an average month)142July: 118 (100 = an average month)August: 116 (100 = an average month)September: 112 (100 = an average month)October: 122 (100 = an average month)November: 96 (100 = an average month)December: 105 (100 = an average month)JFMAMJJASOND

Roofing

917 permits · busiest October, quietest December

January: 20 (100 = an average month)February: 48 (100 = an average month)March: 107 (100 = an average month)April: 98 (100 = an average month)May: 97 (100 = an average month)June: 106 (100 = an average month)July: 116 (100 = an average month)August: 149 (100 = an average month)September: 168 (100 = an average month)October: 181 (100 = an average month)181November: 93 (100 = an average month)December: 17 (100 = an average month)JFMAMJJASOND

Windows & Doors

630 permits · busiest September, quietest November

January: 128 (100 = an average month)February: 74 (100 = an average month)March: 116 (100 = an average month)April: 110 (100 = an average month)May: 105 (100 = an average month)June: 82 (100 = an average month)July: 109 (100 = an average month)August: 88 (100 = an average month)September: 145 (100 = an average month)145October: 103 (100 = an average month)November: 69 (100 = an average month)December: 72 (100 = an average month)JFMAMJJASOND

Fence

552 permits · busiest March, quietest January

January: 15 (100 = an average month)February: 50 (100 = an average month)March: 183 (100 = an average month)183April: 167 (100 = an average month)May: 117 (100 = an average month)June: 150 (100 = an average month)July: 102 (100 = an average month)August: 98 (100 = an average month)September: 87 (100 = an average month)October: 126 (100 = an average month)November: 80 (100 = an average month)December: 24 (100 = an average month)JFMAMJJASOND

Driveway, Walk & Stoop

405 permits · busiest August, quietest January

January: 3 (100 = an average month)February: 18 (100 = an average month)March: 38 (100 = an average month)April: 118 (100 = an average month)May: 127 (100 = an average month)June: 130 (100 = an average month)July: 154 (100 = an average month)August: 284 (100 = an average month)284September: 136 (100 = an average month)October: 145 (100 = an average month)November: 42 (100 = an average month)December: 3 (100 = an average month)JFMAMJJASOND

Electrical

398 permits · busiest April, quietest May

January: 69 (100 = an average month)February: 75 (100 = an average month)March: 54 (100 = an average month)April: 377 (100 = an average month)377May: 42 (100 = an average month)June: 78 (100 = an average month)July: 72 (100 = an average month)August: 121 (100 = an average month)September: 81 (100 = an average month)October: 78 (100 = an average month)November: 100 (100 = an average month)December: 51 (100 = an average month)JFMAMJJASOND
The same numbers as a table
TradeJanFebMarAprMayJunJulAugSepOctNovDec
Heating & Cooling7268726910814211811611212296105
Roofing204810798971061161491681819317
Windows & Doors1287411611010582109881451036972
Fence155018316711715010298871268024
Driveway, Walk & Stoop31838118127130154284136145423
Electrical697554377427872121817810051

When Wheaton, IL schedules each kind of work

For each trade, the month with the most permit filings and the month with the fewest, October 2023 through September 2026. Trades do not all peak together, so the busy season depends on the job. Busiest is not the same as best: these are counts of filings, not prices or weather, though a quiet month at the permit counter can mean contractors have more room in the schedule.

When is the busiest season for HVAC contractors in Wheaton, IL?

June: Wheaton, IL heating & cooling permits peak in June (142 against an average month of 100, about 12% of a year's filings); February is the quietest (68). That is from 1,060 permits, October 2023 through September 2026. If you can choose when to schedule HVAC work, February has the fewest filings; the usual permit then takes 398 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the heating & cooling chart →

When is the busiest season for roofers in Wheaton, IL?

October: Wheaton, IL roofing permits peak in October (181 against an average month of 100, about 15% of a year's filings); December is the quietest (17). That is from 917 permits, October 2023 through September 2026. If you can choose when to schedule roofing work, December has the fewest filings. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the roofing chart →

When is the busiest season for window installers in Wheaton, IL?

September: Wheaton, IL windows & doors permits peak in September (145 against an average month of 100, about 12% of a year's filings); November is the quietest (69). That is from 630 permits, October 2023 through September 2026. If you can choose when to schedule window replacement, November has the fewest filings; the usual permit then takes 83 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the windows & doors chart →

When is the busiest season for fence companies in Wheaton, IL?

March: Wheaton, IL fence permits peak in March (183 against an average month of 100, about 15% of a year's filings); January is the quietest (15). That is from 552 permits, October 2023 through September 2026. If you can choose when to schedule fence installation, January has the fewest filings; the usual permit then takes 375 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the fence chart →

When is the busiest season for driveway contractors in Wheaton, IL?

August: Wheaton, IL driveway, walk & stoop permits peak in August (284 against an average month of 100, about 24% of a year's filings); January is the quietest (3). That is from 405 permits, October 2023 through September 2026. If you can choose when to schedule driveway work, January has the fewest filings; the usual permit then takes 279 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the driveway, walk & stoop chart →

When is the busiest season for electricians in Wheaton, IL?

April: Wheaton, IL electrical permits peak in April (377 against an average month of 100, about 31% of a year's filings); May is the quietest (42). That is from 398 permits, October 2023 through September 2026. If you can choose when to schedule electrical work, May has the fewest filings; the usual permit then takes 159 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the electrical chart →

When is the busiest season for remodeling contractors in Wheaton, IL?

October: Wheaton, IL remodel (kitchen, bath, basement) permits peak in October (182 against an average month of 100, about 15% of a year's filings); June is the quietest (72). That is from 283 permits, October 2023 through September 2026. If you can choose when to schedule a home remodel, June has the fewest filings; the usual permit then takes 132 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month.

When is the busiest season for sewer line contractors in Wheaton, IL?

October: Wheaton, IL sewer & water service permits peak in October (147 against an average month of 100, about 12% of a year's filings); May is the quietest (51). That is from 261 permits, October 2023 through September 2026. If you can choose when to schedule sewer and water service work, May has the fewest filings; the usual permit then takes 14 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month.

When is the busiest season for plumbers in Wheaton, IL?

March: Wheaton, IL plumbing & water heater permits peak in March (149 against an average month of 100, about 12% of a year's filings); May is the quietest (66). That is from 217 permits, October 2023 through September 2026. If you can choose when to schedule plumbing work, May has the fewest filings; the usual permit then takes 34 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month.

When is the busiest season for patio contractors in Wheaton, IL?

June: Wheaton, IL patio permits peak in June (153 against an average month of 100, about 13% of a year's filings); January is the quietest (13). That is from 188 permits, October 2023 through September 2026. If you can choose when to schedule patio work, January has the fewest filings; the usual permit then takes 104 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month.

When is the busiest season for deck builders in Wheaton, IL?

September: Wheaton, IL deck, porch & pergola permits peak in September (250 against an average month of 100, about 21% of a year's filings); January is the quietest (13). That is from 187 permits, October 2023 through September 2026. If you can choose when to schedule a deck build, January has the fewest filings; the usual permit then takes 111 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month.

When is the busiest season for foundation contractors in Wheaton, IL?

July: Wheaton, IL foundation & waterproofing permits peak in July (158 against an average month of 100, about 13% of a year's filings); December is the quietest (32). That is from 152 permits, October 2023 through September 2026. If you can choose when to schedule foundation work, December has the fewest filings; the usual permit then takes 83 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month.

Most active contractors in Wheaton, IL, last 12 months

Top 10 by permits pulled in the last 12 months, all trades. This is volume, not quality: a busy firm is not a careful one. Pick what you value on the compare page to build a ranking.

ContractorTradesLast 12 moAll permits
Borter HeatingHeating & Cooling, Plumbing & Water Heater153375
FTC Oury GorupRoofing, Windows & Doors, Deck, Porch & Pergola71147
Peerless FenceFence56148
Precision Today Heating Cooling Plumbing Electrical LLC dba Precision Today / Awe / Five StarHeating & Cooling, Roofing, Electrical, Sewer & Water Service, Plumbing & Water Heater, Foundation & Waterproofing48142
Renewal by AndersenWindows & Doors47157
McNally's Heating and CoolingHeating & Cooling, Plumbing & Water Heater3365
Isadore IncDriveway, Walk & Stoop, Deck, Porch & Pergola3249
Shamrock Heating and Air ConditioningHeating & Cooling3172
Woodland Windows & DoorsWindows & Doors3171
ABC Plumbing Heating & Cooling IncHeating & Cooling, Electrical, Sewer & Water Service, Plumbing & Water Heater29101

Permits by ZIP code

Each permit counted at its property's ZIP code, October 2023 through September 2026, for the 12 kinds of home work we track. All 2 ZIP codes with 100 or more permits; each opens permits by trade and the most active contractors there.

ZIP codePermitsShareTop tradeUsual home value
601893,02758%Roofing$462,000
601872,20542%Heating & Cooling$445,000

Wheaton, IL ZIP codes →

How these numbers are made

Source: City of Wheaton permits on homes (the city's permit application and inspection exports). The window is October 2023 through September 2026; a permit filed after that isn't here yet.

A filed value is what the contractor wrote on the permit when they applied. It is not a quote and not the final bill.

Counts are permits, not jobs: one job can need several permits, and one permit can cover several visits. 22.9% of the 1,054 firms on the file match an active license at the Illinois IDFPR professional licensing file (licensed roofing contractors only); the match goes by name and can miss one.

Nobody paid to be on this page and nobody can. How the records work in Wheaton, IL →

Common questions

  • How many building permits does Wheaton, IL issue a year?About 1,750 a year for the 12 kinds of home work we track (5,250 permits over 36 months, October 2023 through September 2026); 1,693 in the last 12 months. That is not the city's count of every permit: it covers heating & cooling, roofing, windows & doors, fence, driveway, walk & stoop, electrical, remodel (kitchen, bath, basement), sewer & water service, plumbing & water heater, patio, deck, porch & pergola, foundation & waterproofing, not commercial work or trades we don't read.
  • When should you schedule work in Wheaton, IL?If you can choose, book in a quiet month at the permit counter: for HVAC work, February (busiest June); for roofing work, December (busiest October); for window replacement, November (busiest September). Each trade has its own season; the questions above give every trade we track, with the usual days to sign-off.
  • Who are the most active contractors in Wheaton, IL?By permits pulled in the last 12 months: Borter Heating (153); FTC Oury Gorup (71); Peerless Fence (56). That is volume, not quality: compare finished share and filed values before you hire.
  • Which trade pulls the most permits in Wheaton, IL?Heating & Cooling: 1,060 permits from 69 firms, with a usual filed value of $9,578.
  • What is the busiest month for permits in Wheaton, IL?October, counting every trade. December is the quietest. The chart above shows each trade; they do not all peak together.
  • How many contractors are active in Wheaton, IL?1,054 distinct business names appear on the file; 406 of them pulled at least one permit in the last 12 months. 22.9% of the 1,054 firms on the file match an active license at the Illinois IDFPR professional licensing file (licensed roofing contractors only); the match goes by name and can miss one.
  • How many permits get finished?For heating & cooling, 47.4% of permits a year or more old were closed out by the city. How long permits take in Wheaton, IL →
  • Where does this data come from?City of Wheaton permits on homes (the city's permit application and inspection exports), read October 2026. How the records work in Wheaton, IL →

Other cities: Nashville Orlando New York City Chicago Austin Raleigh Cincinnati Cleveland Pittsburgh Miami Minneapolis St. Louis Denver San Diego Colorado Springs Honolulu Albuquerque Boulder Greensboro Saint Paul Arlington, VA Scottsdale Henderson Cambridge Somerville Cary Mesa Naperville Bellevue Cape Coral Provo Palo Alto Bellingham Bend Ames Denton Sugar Land Burlington, VT Seattle San Francisco Medford Anaheim Elk Grove Wilmington, NC Bismarck Tyler, TX Columbus, OH San Diego County (unincorporated) Marin County (unincorporated) Sacramento County (unincorporated) Citrus Heights, CA Waco, TX