Saint Paul, MN building permit statistics

72,000 permits from 3,553 contractors across 18 kinds of work in the City of Saint Paul, July 2022 through June 2025: about 24,000 a year. Electrical is the biggest trade with 17,041 permits. The busiest month for filings is October. Records run through June 2025; the city's file has nothing newer for us to read.

72,000permits read
3,553contractors on record
18kinds of work
Octbusiest month
67%firms matched to an active license
Jun 2025records through

By trade

Firms are distinct business names on the file. A linked usual filed value opens what that work costs. Finished is the share of permits a year or more old that the city closed out. Days to finish run from issue to the city's completion date, not from application.

TradePermitsFirmsActive last 12 moUsual filed valueFinishedDays to finishBusiest month
Electrical17,041671504$1,10084.6%54August
Roofing16,9281,322674$12,60076.3%128September
HVAC & Gas14,402253171$6,30064.1%150November
Plumbing9,210384286$2,50099.7%77January
Windows & Doors4,513463223$7,50068.0%109October
Remodel & Repair3,037950480$15,00060.1%206October
Fence1,9648137$6,697——July
Siding1,112366163$14,70065.5%186May
Solar8233223$5,00093.8%69February
Drain Tile & Waterproofing7474322$8,26063.4%106August
Garage & Accessory53814456$16,12873.1%207August
Deck, Porch & Steps465269112$9,67553.1%196July
Fireplace & Stove3172211$6,70075.6%55January
Stucco & Plaster2724425$5,00092.9%134October
Addition22014967$94,00054.0%429August
New Home1726724$342,00049.7%559September
Radon Mitigation1383627$60098.7%224September
Demolition1014523$12,00075.0%263March

Permits by year

The file we publish splits exactly into the last 12 months on file and the 24 months before them, so these are 12-month periods ending June 2025, not calendar years. Per year scales each period to 12 months. Counts cover the 18 kinds of home work we track, not every permit Saint Paul issues.

PeriodMonthsPermitsPer year
Jul 2022–Jun 20242451,26825,634
Jul 2024–Jun 2025 (last 12 months on file)1220,73220,732

By month

Share of filings by month, 100 = an average month (the thin line). The 11 biggest trades (every trade with 500 or more permits), July 2022 through June 2025. A tall bar is a busy month at the permit counter, which usually means a longer wait for a contractor.

Electrical

17,041 permits · busiest August, quietest February

January: 91 (100 = an average month)February: 76 (100 = an average month)March: 83 (100 = an average month)April: 103 (100 = an average month)May: 107 (100 = an average month)June: 112 (100 = an average month)July: 111 (100 = an average month)August: 121 (100 = an average month)121September: 99 (100 = an average month)October: 113 (100 = an average month)November: 100 (100 = an average month)December: 84 (100 = an average month)JFMAMJJASOND

Roofing

16,928 permits · busiest September, quietest January

January: 12 (100 = an average month)February: 20 (100 = an average month)March: 49 (100 = an average month)April: 86 (100 = an average month)May: 114 (100 = an average month)June: 100 (100 = an average month)July: 151 (100 = an average month)August: 184 (100 = an average month)September: 196 (100 = an average month)196October: 191 (100 = an average month)November: 78 (100 = an average month)December: 20 (100 = an average month)JFMAMJJASOND

HVAC & Gas

14,402 permits · busiest November, quietest May

January: 113 (100 = an average month)February: 90 (100 = an average month)March: 88 (100 = an average month)April: 87 (100 = an average month)May: 86 (100 = an average month)June: 102 (100 = an average month)July: 104 (100 = an average month)August: 97 (100 = an average month)September: 87 (100 = an average month)October: 116 (100 = an average month)November: 126 (100 = an average month)126December: 103 (100 = an average month)JFMAMJJASOND

Plumbing

9,210 permits · busiest January, quietest December

January: 115 (100 = an average month)115February: 101 (100 = an average month)March: 112 (100 = an average month)April: 102 (100 = an average month)May: 97 (100 = an average month)June: 96 (100 = an average month)July: 91 (100 = an average month)August: 95 (100 = an average month)September: 92 (100 = an average month)October: 106 (100 = an average month)November: 103 (100 = an average month)December: 89 (100 = an average month)JFMAMJJASOND

Windows & Doors

4,513 permits · busiest October, quietest January

January: 67 (100 = an average month)February: 71 (100 = an average month)March: 92 (100 = an average month)April: 99 (100 = an average month)May: 86 (100 = an average month)June: 115 (100 = an average month)July: 104 (100 = an average month)August: 116 (100 = an average month)September: 120 (100 = an average month)October: 133 (100 = an average month)133November: 106 (100 = an average month)December: 92 (100 = an average month)JFMAMJJASOND

Remodel & Repair

3,037 permits · busiest October, quietest November

January: 106 (100 = an average month)February: 93 (100 = an average month)March: 104 (100 = an average month)April: 99 (100 = an average month)May: 100 (100 = an average month)June: 106 (100 = an average month)July: 107 (100 = an average month)August: 110 (100 = an average month)September: 94 (100 = an average month)October: 111 (100 = an average month)111November: 84 (100 = an average month)December: 84 (100 = an average month)JFMAMJJASOND

Fence

1,964 permits · busiest July, quietest February

January: 20 (100 = an average month)February: 12 (100 = an average month)March: 75 (100 = an average month)April: 112 (100 = an average month)May: 178 (100 = an average month)June: 159 (100 = an average month)July: 183 (100 = an average month)183August: 136 (100 = an average month)September: 96 (100 = an average month)October: 119 (100 = an average month)November: 67 (100 = an average month)December: 42 (100 = an average month)JFMAMJJASOND

Siding

1,112 permits · busiest May, quietest February

January: 76 (100 = an average month)February: 50 (100 = an average month)March: 107 (100 = an average month)April: 99 (100 = an average month)May: 128 (100 = an average month)128June: 108 (100 = an average month)July: 107 (100 = an average month)August: 108 (100 = an average month)September: 116 (100 = an average month)October: 124 (100 = an average month)November: 106 (100 = an average month)December: 70 (100 = an average month)JFMAMJJASOND

Solar

823 permits · busiest February, quietest January

January: 66 (100 = an average month)February: 141 (100 = an average month)141March: 86 (100 = an average month)April: 73 (100 = an average month)May: 111 (100 = an average month)June: 95 (100 = an average month)July: 105 (100 = an average month)August: 106 (100 = an average month)September: 117 (100 = an average month)October: 118 (100 = an average month)November: 111 (100 = an average month)December: 71 (100 = an average month)JFMAMJJASOND

Drain Tile & Waterproofing

747 permits · busiest August, quietest February

January: 79 (100 = an average month)February: 58 (100 = an average month)March: 112 (100 = an average month)April: 100 (100 = an average month)May: 95 (100 = an average month)June: 114 (100 = an average month)July: 104 (100 = an average month)August: 132 (100 = an average month)132September: 116 (100 = an average month)October: 130 (100 = an average month)November: 69 (100 = an average month)December: 92 (100 = an average month)JFMAMJJASOND

Garage & Accessory

538 permits · busiest August, quietest January

January: 0 (100 = an average month)February: 42 (100 = an average month)March: 104 (100 = an average month)April: 82 (100 = an average month)May: 124 (100 = an average month)June: 130 (100 = an average month)July: 181 (100 = an average month)August: 190 (100 = an average month)190September: 174 (100 = an average month)October: 121 (100 = an average month)November: 44 (100 = an average month)December: 9 (100 = an average month)JFMAMJJASOND
The same numbers as a table
TradeJanFebMarAprMayJunJulAugSepOctNovDec
Electrical9176831031071121111219911310084
Roofing122049861141001511841961917820
HVAC & Gas113908887861021049787116126103
Plumbing115101112102979691959210610389
Windows & Doors677192998611510411612013310692
Remodel & Repair1069310499100106107110941118484
Fence201275112178159183136961196742
Siding76501079912810810710811612410670
Solar6614186731119510510611711811171
Drain Tile & Waterproofing7958112100951141041321161306992
Garage & Accessory04210482124130181190174121449

When Saint Paul schedules each kind of work

For each trade, the month with the most permit filings and the month with the fewest, July 2022 through June 2025. Trades do not all peak together, so the busy season depends on the job. Busiest is not the same as best: these are counts of filings, not prices or weather, though a quiet month at the permit counter can mean contractors have more room in the schedule.

When is the busiest season for electricians in Saint Paul?

August: Saint Paul electrical permits peak in August (121 against an average month of 100, about 10% of a year's filings); February is the quietest (76). That is from 17,041 permits, July 2022 through June 2025. If you can choose when to schedule electrical work, February has the fewest filings; the usual permit then takes 54 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the electrical chart →

When is the busiest season for roofers in Saint Paul?

September: Saint Paul roofing permits peak in September (196 against an average month of 100, about 16% of a year's filings); January is the quietest (12). That is from 16,928 permits, July 2022 through June 2025. If you can choose when to schedule roofing work, January has the fewest filings; the usual permit then takes 128 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the roofing chart →

When is the busiest season for HVAC contractors in Saint Paul?

November: Saint Paul HVAC & gas permits peak in November (126 against an average month of 100, about 10% of a year's filings); May is the quietest (86). That is from 14,402 permits, July 2022 through June 2025. If you can choose when to schedule HVAC work, May has the fewest filings; the usual permit then takes 150 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the HVAC & gas chart →

When is the busiest season for plumbers in Saint Paul?

January: Saint Paul plumbing permits peak in January (115 against an average month of 100, about 10% of a year's filings); December is the quietest (89). That is from 9,210 permits, July 2022 through June 2025. If you can choose when to schedule plumbing work, December has the fewest filings; the usual permit then takes 77 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the plumbing chart →

When is the busiest season for window installers in Saint Paul?

October: Saint Paul windows & doors permits peak in October (133 against an average month of 100, about 11% of a year's filings); January is the quietest (67). That is from 4,513 permits, July 2022 through June 2025. If you can choose when to schedule window replacement, January has the fewest filings; the usual permit then takes 109 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the windows & doors chart →

When is the busiest season for remodeling contractors in Saint Paul?

October: Saint Paul remodel & repair permits peak in October (111 against an average month of 100, about 9% of a year's filings); November is the quietest (84). That is from 3,037 permits, July 2022 through June 2025. If you can choose when to schedule a home remodel, November has the fewest filings; the usual permit then takes 206 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the remodel & repair chart →

When is the busiest season for fence companies in Saint Paul?

July: Saint Paul fence permits peak in July (183 against an average month of 100, about 15% of a year's filings); February is the quietest (12). That is from 1,964 permits, July 2022 through June 2025. If you can choose when to schedule fence installation, February has the fewest filings. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the fence chart →

When is the busiest season for siding contractors in Saint Paul?

May: Saint Paul siding permits peak in May (128 against an average month of 100, about 11% of a year's filings); February is the quietest (50). That is from 1,112 permits, July 2022 through June 2025. If you can choose when to schedule siding work, February has the fewest filings; the usual permit then takes 186 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the siding chart →

When is the busiest season for solar installers in Saint Paul?

February: Saint Paul solar permits peak in February (141 against an average month of 100, about 12% of a year's filings); January is the quietest (66). That is from 823 permits, July 2022 through June 2025. If you can choose when to schedule solar installation, January has the fewest filings; the usual permit then takes 69 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the solar chart →

When is the busiest season for waterproofing contractors in Saint Paul?

August: Saint Paul drain tile & waterproofing permits peak in August (132 against an average month of 100, about 11% of a year's filings); February is the quietest (58). That is from 747 permits, July 2022 through June 2025. If you can choose when to schedule waterproofing work, February has the fewest filings; the usual permit then takes 106 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the drain tile & waterproofing chart →

When is the busiest season for garage builders in Saint Paul?

August: Saint Paul garage & accessory permits peak in August (190 against an average month of 100, about 16% of a year's filings); January is the quietest (0). That is from 538 permits, July 2022 through June 2025. If you can choose when to schedule garage construction, January has the fewest filings; the usual permit then takes 207 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the garage & accessory chart →

When is the busiest season for deck builders in Saint Paul?

July: Saint Paul deck, porch & steps permits peak in July (163 against an average month of 100, about 14% of a year's filings); February is the quietest (26). That is from 465 permits, July 2022 through June 2025. If you can choose when to schedule a deck build, February has the fewest filings; the usual permit then takes 196 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month.

When is the busiest season for fireplace installers in Saint Paul?

January: Saint Paul fireplace & stove permits peak in January (148 against an average month of 100, about 12% of a year's filings); May is the quietest (34). That is from 317 permits, July 2022 through June 2025. If you can choose when to schedule fireplace and stove work, May has the fewest filings; the usual permit then takes 55 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month.

When is the busiest season for stucco contractors in Saint Paul?

October: Saint Paul stucco & plaster permits peak in October (168 against an average month of 100, about 14% of a year's filings); December is the quietest (18). That is from 272 permits, July 2022 through June 2025. If you can choose when to schedule stucco work, December has the fewest filings; the usual permit then takes 134 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month.

When is the busiest season for home addition contractors in Saint Paul?

August: Saint Paul addition permits peak in August (151 against an average month of 100, about 13% of a year's filings); January is the quietest (54). That is from 220 permits, July 2022 through June 2025. If you can choose when to schedule a home addition, January has the fewest filings; the usual permit then takes 429 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month.

When is the busiest season for home builders in Saint Paul?

September: Saint Paul new home permits peak in September (236 against an average month of 100, about 20% of a year's filings); February is the quietest (7). That is from 172 permits, July 2022 through June 2025. If you can choose when to schedule new home construction, February has the fewest filings; the usual permit then takes 559 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month.

When is the busiest season for radon mitigation contractors in Saint Paul?

September: Saint Paul radon mitigation permits peak in September (200 against an average month of 100, about 17% of a year's filings); May is the quietest (35). That is from 138 permits, July 2022 through June 2025. If you can choose when to schedule radon mitigation work, May has the fewest filings; the usual permit then takes 224 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month.

When is the busiest season for demolition contractors in Saint Paul?

March: Saint Paul demolition permits peak in March (128 against an average month of 100, about 11% of a year's filings); September is the quietest (47). That is from 101 permits, July 2022 through June 2025. If you can choose when to schedule demolition, September has the fewest filings; the usual permit then takes 263 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month.

Most active contractors in Saint Paul, Jul 2024–Jun 2025

Top 10 by permits pulled in the last 12 months on file (Jul 2024–Jun 2025), all trades. This is volume, not quality: a busy firm is not a careful one. Pick what you value on the compare page to build a ranking.

ContractorTradesLast 12 moAll permits
Bonfes Plbg & Htg IncElectrical, HVAC & Gas, Plumbing5501,759
St Paul Plbg & Htg Co - MSP PlbgHVAC & Gas, Plumbing5121,611
Powerhouse Electric IncElectrical4241,216
Hero Home Services dba Hero Plumbing Heating & CoolingElectrical, HVAC & Gas, Plumbing4061,171
Standard Heating & Air Conditioning IncHVAC & Gas, Plumbing3991,354
Dean's Professional PlumbingElectrical, HVAC & Gas, Plumbing351798
Renewal by Andersen LLCWindows & Doors, Remodel & Repair3341,048
Boehm Heating CoHVAC & Gas303909
McQuillan Home Services LLCElectrical, HVAC & Gas, Plumbing2961,082
Spark Electric CoElectrical283970

Permits by ZIP code

Each permit counted at its property's ZIP code, July 2022 through June 2025, for the 18 kinds of home work we track. The 10 busiest of 12 ZIP codes with 100 or more permits; each opens permits by trade and the most active contractors there.

ZIP codePermitsShareTop tradeUsual home value
5510411,53116%Electrical$288,000
5510511,32416%Electrical$452,000
5510611,09615%Roofing$240,000
5511610,06814%Electrical$434,000
551196,1999%Roofing$262,000
551176,1629%Roofing$253,000
551083,8875%Electrical$372,000
551023,2735%Electrical$262,000
551073,0684%Electrical$242,000
551302,2483%Roofing$228,000

All 12 Saint Paul ZIP codes →

How these numbers are made

Source: City of Saint Paul approved building permits. The window is July 2022 through June 2025; a permit filed after that isn't here yet.

A filed value is what the contractor wrote on the permit when they applied. It is not a quote and not the final bill.

Counts are permits, not jobs: one job can need several permits, and one permit can cover several visits. 67.1% of the 3,553 firms on the file match an active license at Minnesota Department of Labor and Industry contractor files; the match goes by name and can miss one.

Nobody paid to be on this page and nobody can. How the records work in Saint Paul →

Common questions

  • How many building permits does Saint Paul issue a year?About 24,000 a year for the 18 kinds of home work we track (72,000 permits over 36 months, July 2022 through June 2025); 20,732 in the last 12 months on file. That is not the city's count of every permit: it covers electrical, roofing, HVAC & gas, plumbing, windows & doors, remodel & repair, fence, siding, solar, drain tile & waterproofing, garage & accessory, deck, porch & steps, fireplace & stove, stucco & plaster, addition, new home, radon mitigation, demolition, not commercial work or trades we don't read.
  • When should you schedule work in Saint Paul?If you can choose, book in a quiet month at the permit counter: for electrical work, February (busiest August); for roofing work, January (busiest September); for HVAC work, May (busiest November). Each trade has its own season; the questions above give every trade we track, with the usual days to sign-off.
  • Who are the most active contractors in Saint Paul?By permits pulled in Jul 2024–Jun 2025, the last 12 months on file: Bonfes Plbg & Htg Inc (550); St Paul Plbg & Htg Co - MSP Plbg (512); Powerhouse Electric Inc (424). That is volume, not quality: compare finished share and filed values before you hire.
  • Which trade pulls the most permits in Saint Paul?Electrical: 17,041 permits from 671 firms, with a usual filed value of $1,100.
  • What is the busiest month for permits in Saint Paul?October, counting every trade. February is the quietest. The chart above shows each trade; they do not all peak together.
  • How many contractors are active in Saint Paul?3,553 distinct business names appear on the file; 2,214 of them pulled at least one permit in the last 12 months on file. 67.1% of the 3,553 firms on the file match an active license at Minnesota Department of Labor and Industry contractor files; the match goes by name and can miss one.
  • How many permits get finished?For electrical, 84.6% of permits a year or more old were closed out by the city. How long permits take in Saint Paul →
  • Where does this data come from?City of Saint Paul approved building permits, read June 2025. How the records work in Saint Paul →

Other cities: Nashville Orlando New York City Chicago Austin Raleigh Cincinnati Cleveland Pittsburgh Miami Minneapolis St. Louis Denver San Diego Colorado Springs Honolulu Albuquerque Boulder Greensboro Arlington, VA Scottsdale Henderson Cambridge Somerville Cary Mesa Naperville Bellevue Cape Coral Provo Palo Alto Bellingham Bend Ames Denton Sugar Land Burlington, VT Seattle San Francisco Medford Anaheim Elk Grove Wilmington, NC Bismarck Tyler, TX Columbus, OH Wheaton, IL San Diego County (unincorporated) Marin County (unincorporated) Sacramento County (unincorporated) Citrus Heights, CA Waco, TX