St. Louis, MO building permit statistics

5,943 permits from 1,919 contractors across 10 kinds of work in the City of St. Louis, October 2023 through September 2026: about 1,981 a year. Remodel & Alteration is the biggest trade with 1,904 permits. The busiest month for filings is October.

5,943permits read
1,919contractors on record
10kinds of work
Octbusiest month
Sep 2026records through

By trade

Firms are distinct business names on the file. A linked usual filed value opens what that work costs. Finished is the share of permits a year or more old that the city closed out. Days to finish run from issue to the city's completion date, not from application.

TradePermitsFirmsActive last 12 moUsual filed valueFinishedDays to finishBusiest month
Remodel & Alteration1,904984290$30,00065.6%361October
Fence86620653$5,69371.9%213October
Demolition7443733—95.9%164June
Deck & Porch703438129$11,85068.1%234October
Roofing49120465$20,00073.2%294August
Garage & Carport35514947$13,00070.3%335April
Windows & Doors33012743$9,94470.9%382August
Foundation & Waterproofing3045521$11,27960.3%296December
Solar1485128$20,00082.9%154November

Fewer than 100 permits, so no row: Masonry & Tuckpointing (98).

Permits by year

The file we publish splits exactly into the last 12 months on file and the 24 months before them, so these are 12-month periods ending September 2026, not calendar years. Per year scales each period to 12 months. Counts cover the 10 kinds of home work we track, not every permit St. Louis issues.

PeriodMonthsPermitsPer year
Oct 2023–Sep 2025243,8041,902
Oct 2025–Sep 2026 (last 12 months)122,1392,139

By month

Share of filings by month, 100 = an average month (the thin line). The 6 biggest trades, October 2023 through September 2026. A tall bar is a busy month at the permit counter, which usually means a longer wait for a contractor.

Remodel & Alteration

1,904 permits · busiest October, quietest March

January: 109 (100 = an average month)February: 87 (100 = an average month)March: 76 (100 = an average month)April: 93 (100 = an average month)May: 98 (100 = an average month)June: 86 (100 = an average month)July: 105 (100 = an average month)August: 99 (100 = an average month)September: 96 (100 = an average month)October: 132 (100 = an average month)132November: 110 (100 = an average month)December: 108 (100 = an average month)JFMAMJJASOND

Fence

866 permits · busiest October, quietest January

January: 60 (100 = an average month)February: 67 (100 = an average month)March: 105 (100 = an average month)April: 130 (100 = an average month)May: 119 (100 = an average month)June: 95 (100 = an average month)July: 126 (100 = an average month)August: 99 (100 = an average month)September: 92 (100 = an average month)October: 133 (100 = an average month)133November: 95 (100 = an average month)December: 78 (100 = an average month)JFMAMJJASOND

Demolition

744 permits · busiest June, quietest October

January: 19 (100 = an average month)February: 48 (100 = an average month)March: 71 (100 = an average month)April: 106 (100 = an average month)May: 161 (100 = an average month)June: 227 (100 = an average month)227July: 164 (100 = an average month)August: 211 (100 = an average month)September: 134 (100 = an average month)October: 16 (100 = an average month)November: 16 (100 = an average month)December: 24 (100 = an average month)JFMAMJJASOND

Deck & Porch

703 permits · busiest October, quietest January

January: 61 (100 = an average month)February: 66 (100 = an average month)March: 98 (100 = an average month)April: 107 (100 = an average month)May: 68 (100 = an average month)June: 104 (100 = an average month)July: 116 (100 = an average month)August: 102 (100 = an average month)September: 85 (100 = an average month)October: 179 (100 = an average month)179November: 121 (100 = an average month)December: 93 (100 = an average month)JFMAMJJASOND

Roofing

491 permits · busiest August, quietest December

January: 96 (100 = an average month)February: 120 (100 = an average month)March: 82 (100 = an average month)April: 63 (100 = an average month)May: 91 (100 = an average month)June: 103 (100 = an average month)July: 124 (100 = an average month)August: 134 (100 = an average month)134September: 120 (100 = an average month)October: 117 (100 = an average month)November: 89 (100 = an average month)December: 61 (100 = an average month)JFMAMJJASOND

Garage & Carport

355 permits · busiest April, quietest February

January: 91 (100 = an average month)February: 62 (100 = an average month)March: 65 (100 = an average month)April: 146 (100 = an average month)146May: 94 (100 = an average month)June: 94 (100 = an average month)July: 94 (100 = an average month)August: 127 (100 = an average month)September: 117 (100 = an average month)October: 124 (100 = an average month)November: 114 (100 = an average month)December: 72 (100 = an average month)JFMAMJJASOND
The same numbers as a table
TradeJanFebMarAprMayJunJulAugSepOctNovDec
Remodel & Alteration10987769398861059996132110108
Fence60671051301199512699921339578
Demolition194871106161227164211134161624
Deck & Porch616698107681041161028517912193
Roofing961208263911031241341201178961
Garage & Carport91626514694949412711712411472

When St. Louis schedules each kind of work

For each trade, the month with the most permit filings and the month with the fewest, October 2023 through September 2026. Trades do not all peak together, so the busy season depends on the job. Busiest is not the same as best: these are counts of filings, not prices or weather, though a quiet month at the permit counter can mean contractors have more room in the schedule.

When is the busiest season for remodeling contractors in St. Louis?

October: St. Louis remodel & alteration permits peak in October (132 against an average month of 100, about 11% of a year's filings); March is the quietest (76). That is from 1,904 permits, October 2023 through September 2026. If you can choose when to schedule a home remodel, March has the fewest filings; the usual permit then takes 361 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the remodel & alteration chart →

When is the busiest season for fence companies in St. Louis?

October: St. Louis fence permits peak in October (133 against an average month of 100, about 11% of a year's filings); January is the quietest (60). That is from 866 permits, October 2023 through September 2026. If you can choose when to schedule fence installation, January has the fewest filings; the usual permit then takes 213 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the fence chart →

When is the busiest season for demolition contractors in St. Louis?

June: St. Louis demolition permits peak in June (227 against an average month of 100, about 19% of a year's filings); October is the quietest (16). That is from 744 permits, October 2023 through September 2026. If you can choose when to schedule demolition, October has the fewest filings; the usual permit then takes 164 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the demolition chart →

When is the busiest season for deck builders in St. Louis?

October: St. Louis deck & porch permits peak in October (179 against an average month of 100, about 15% of a year's filings); January is the quietest (61). That is from 703 permits, October 2023 through September 2026. If you can choose when to schedule a deck build, January has the fewest filings; the usual permit then takes 234 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the deck & porch chart →

When is the busiest season for roofers in St. Louis?

August: St. Louis roofing permits peak in August (134 against an average month of 100, about 11% of a year's filings); December is the quietest (61). That is from 491 permits, October 2023 through September 2026. If you can choose when to schedule roofing work, December has the fewest filings; the usual permit then takes 294 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the roofing chart →

When is the busiest season for garage builders in St. Louis?

April: St. Louis garage & carport permits peak in April (146 against an average month of 100, about 12% of a year's filings); February is the quietest (62). That is from 355 permits, October 2023 through September 2026. If you can choose when to schedule garage construction, February has the fewest filings; the usual permit then takes 335 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the garage & carport chart →

When is the busiest season for window installers in St. Louis?

August: St. Louis windows & doors permits peak in August (134 against an average month of 100, about 11% of a year's filings); December is the quietest (63). That is from 330 permits, October 2023 through September 2026. If you can choose when to schedule window replacement, December has the fewest filings; the usual permit then takes 382 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month.

When is the busiest season for foundation contractors in St. Louis?

December: St. Louis foundation & waterproofing permits peak in December (148 against an average month of 100, about 12% of a year's filings); June is the quietest (51). That is from 304 permits, October 2023 through September 2026. If you can choose when to schedule foundation work, June has the fewest filings; the usual permit then takes 296 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month.

When is the busiest season for solar installers in St. Louis?

November: St. Louis solar permits peak in November (224 against an average month of 100, about 19% of a year's filings); August is the quietest (16). That is from 148 permits, October 2023 through September 2026. If you can choose when to schedule solar installation, August has the fewest filings; the usual permit then takes 154 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month.

Most active contractors in St. Louis, last 12 months

Top 10 by permits pulled in the last 12 months, all trades. This is volume, not quality: a busy firm is not a careful one. Pick what you value on the compare page to build a ranking.

ContractorTradesLast 12 moAll permits
Bellon Wrecking LLCRemodel & Alteration, Demolition8086
Premier Demolition, Inc.Demolition7575
Hillsdale Demolition Contracting LLCDemolition7079
Jath Construction Company, LLC.Demolition6566
Sultan General Construction Co LLCDemolition5253
Eis – Environmental Infrastructure SolutionsDemolition4848
Signature Demolition & Trucking LLCDemolition4748
City CarportFence, Garage & Carport42122
Renewal by AndersenRemodel & Alteration, Windows & Doors4172
Easter Fence Deck and RenovationsFence, Deck & Porch3943

Permits by ZIP code

Each permit counted at its property's ZIP code, October 2023 through September 2026, for the 10 kinds of home work we track. The 10 busiest of 13 ZIP codes with 100 or more permits; each opens permits by trade and the most active contractors there.

ZIP codePermitsShareTop tradeUsual home value
6311666611%Remodel & Alteration$183,000
6310962310%Remodel & Alteration$259,000
631045569%Remodel & Alteration$326,000
631085319%Remodel & Alteration$532,000
631155189%Demolition$13,000
631124918%Remodel & Alteration$297,000
631394798%Remodel & Alteration$200,000
631104538%Remodel & Alteration$284,000
631184217%Remodel & Alteration$204,000
631133937%Demolition$12,000

All 13 St. Louis ZIP codes →

How these numbers are made

Source: City of St. Louis building permits. The window is October 2023 through September 2026; a permit filed after that isn't here yet.

A filed value is what the contractor wrote on the permit when they applied. It is not a quote and not the final bill.

Counts are permits, not jobs: one job can need several permits, and one permit can cover several visits.

Nobody paid to be on this page and nobody can. How the records work in St. Louis →

Common questions

  • How many building permits does St. Louis issue a year?About 1,981 a year for the 10 kinds of home work we track (5,943 permits over 36 months, October 2023 through September 2026); 2,139 in the last 12 months. That is not the city's count of every permit: it covers remodel & alteration, fence, demolition, deck & porch, roofing, garage & carport, windows & doors, foundation & waterproofing, solar, masonry & tuckpointing, not commercial work or trades we don't read.
  • When should you schedule work in St. Louis?If you can choose, book in a quiet month at the permit counter: for a home remodel, March (busiest October); for fence installation, January (busiest October); for demolition, October (busiest June). Each trade has its own season; the questions above give every trade we track, with the usual days to sign-off.
  • Who are the most active contractors in St. Louis?By permits pulled in the last 12 months: Bellon Wrecking LLC (80); Premier Demolition, Inc. (75); Hillsdale Demolition Contracting LLC (70). That is volume, not quality: compare finished share and filed values before you hire.
  • Which trade pulls the most permits in St. Louis?Remodel & Alteration: 1,904 permits from 984 firms, with a usual filed value of $30,000.
  • What is the busiest month for permits in St. Louis?October, counting every trade. March is the quietest. The chart above shows each trade; they do not all peak together.
  • How many contractors are active in St. Louis?1,919 distinct business names appear on the file; 605 of them pulled at least one permit in the last 12 months.
  • How many permits get finished?For remodel & alteration, 65.6% of permits a year or more old were closed out by the city. How long permits take in St. Louis →
  • Where does this data come from?City of St. Louis building permits, read October 2026. How the records work in St. Louis →

Other cities: Nashville Orlando New York City Chicago Austin Raleigh Cincinnati Cleveland Pittsburgh Miami Minneapolis Denver San Diego Colorado Springs Honolulu Albuquerque Boulder Greensboro Saint Paul Arlington, VA Scottsdale Henderson Cambridge Somerville Cary Mesa Naperville Bellevue Cape Coral Provo Palo Alto Bellingham Bend Ames Denton Sugar Land Burlington, VT Seattle San Francisco Medford Anaheim Elk Grove Wilmington, NC Bismarck Tyler, TX Columbus, OH Wheaton, IL San Diego County (unincorporated) Marin County (unincorporated) Sacramento County (unincorporated) Citrus Heights, CA Waco, TX