87,588 permits from 4,869 contractors across 10 kinds of work in the City of Austin, October 2023 through September 2026: about 29,196 a year. Electrical is the biggest trade with 24,726 permits. The busiest month for filings is June.
Firms are distinct business names on the file. A linked usual filed value opens what that work costs. Finished is the share of permits a year or more old that the city closed out. Days to finish run from issue to the city's completion date, not from application.
| Trade | Permits | Firms | Active last 12 mo | Finished | Days to finish | Busiest month |
|---|---|---|---|---|---|---|
| Electrical | 24,726 | 1,193 | 694 | 90.6% | 76 | June |
| Plumbing | 23,406 | 991 | 588 | 87.1% | 75 | April |
| HVAC | 18,237 | 819 | 479 | 80.4% | 118 | June |
| Remodel & Repair | 7,109 | 837 | 410 | 82.9% | 67 | March |
| New Home | 4,352 | 645 | 298 | 82.3% | 356 | March |
| Home Addition | 3,209 | 1,378 | 627 | 86.8% | 238 | July |
| Driveway & Sidewalk | 2,137 | 472 | 170 | 98.7% | 69 | April |
| Swimming Pool | 2,022 | 431 | 204 | 79.2% | 300 | March |
| Demolition | 1,925 | 506 | 233 | 83.2% | 133 | May |
| Backyard Unit (ADU) | 465 | 322 | 80 | 79.6% | 405 | February |
The file we publish splits exactly into the last 12 months on file and the 24 months before them, so these are 12-month periods ending September 2026, not calendar years. Per year scales each period to 12 months. Counts cover the 10 kinds of home work we track, not every permit Austin issues.
| Period | Months | Permits | Per year |
|---|---|---|---|
| Oct 2023–Sep 2025 | 24 | 56,939 | 28,470 |
| Oct 2025–Sep 2026 (last 12 months) | 12 | 30,649 | 30,649 |
Share of filings by month, 100 = an average month (the thin line). The 9 biggest trades (every trade with 500 or more permits), October 2023 through September 2026. A tall bar is a busy month at the permit counter, which usually means a longer wait for a contractor.
24,726 permits · busiest June, quietest December
23,406 permits · busiest April, quietest November
18,237 permits · busiest June, quietest February
7,109 permits · busiest March, quietest February
4,352 permits · busiest March, quietest August
3,209 permits · busiest July, quietest November
2,137 permits · busiest April, quietest December
2,022 permits · busiest March, quietest December
1,925 permits · busiest May, quietest December
| Trade | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Electrical | 91 | 93 | 104 | 105 | 105 | 112 | 107 | 104 | 107 | 100 | 88 | 83 |
| Plumbing | 91 | 99 | 115 | 116 | 102 | 103 | 101 | 98 | 100 | 94 | 90 | 91 |
| HVAC | 77 | 73 | 98 | 105 | 123 | 129 | 124 | 116 | 115 | 92 | 75 | 74 |
| Remodel & Repair | 92 | 88 | 119 | 111 | 105 | 95 | 102 | 92 | 102 | 104 | 95 | 96 |
| New Home | 86 | 100 | 141 | 125 | 108 | 103 | 108 | 82 | 90 | 89 | 83 | 86 |
| Home Addition | 95 | 98 | 98 | 106 | 114 | 106 | 118 | 101 | 97 | 106 | 76 | 84 |
| Driveway & Sidewalk | 123 | 84 | 81 | 127 | 121 | 102 | 118 | 116 | 74 | 122 | 67 | 67 |
| Swimming Pool | 100 | 91 | 133 | 89 | 106 | 92 | 126 | 92 | 92 | 113 | 95 | 70 |
| Demolition | 92 | 104 | 107 | 112 | 113 | 108 | 104 | 89 | 95 | 106 | 89 | 81 |
For each trade, the month with the most permit filings and the month with the fewest, October 2023 through September 2026. Trades do not all peak together, so the busy season depends on the job. Busiest is not the same as best: these are counts of filings, not prices or weather, though a quiet month at the permit counter can mean contractors have more room in the schedule.
June: Austin electrical permits peak in June (112 against an average month of 100, about 9% of a year's filings); December is the quietest (83). That is from 24,726 permits, October 2023 through September 2026. If you can choose when to schedule electrical work, December has the fewest filings; the usual permit then takes 76 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the electrical chart →
April: Austin plumbing permits peak in April (116 against an average month of 100, about 10% of a year's filings); November is the quietest (90). That is from 23,406 permits, October 2023 through September 2026. If you can choose when to schedule plumbing work, November has the fewest filings; the usual permit then takes 75 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the plumbing chart →
June: Austin HVAC permits peak in June (129 against an average month of 100, about 11% of a year's filings); February is the quietest (73). That is from 18,237 permits, October 2023 through September 2026. If you can choose when to schedule HVAC work, February has the fewest filings; the usual permit then takes 118 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the HVAC chart →
March: Austin remodel & repair permits peak in March (119 against an average month of 100, about 10% of a year's filings); February is the quietest (88). That is from 7,109 permits, October 2023 through September 2026. If you can choose when to schedule a home remodel, February has the fewest filings; the usual permit then takes 67 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the remodel & repair chart →
March: Austin new home permits peak in March (141 against an average month of 100, about 12% of a year's filings); August is the quietest (82). That is from 4,352 permits, October 2023 through September 2026. If you can choose when to schedule new home construction, August has the fewest filings; the usual permit then takes 356 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the new home chart →
July: Austin home addition permits peak in July (118 against an average month of 100, about 10% of a year's filings); November is the quietest (76). That is from 3,209 permits, October 2023 through September 2026. If you can choose when to schedule a home addition, November has the fewest filings; the usual permit then takes 238 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the home addition chart →
April: Austin driveway & sidewalk permits peak in April (127 against an average month of 100, about 11% of a year's filings); December is the quietest (67). That is from 2,137 permits, October 2023 through September 2026. If you can choose when to schedule driveway work, December has the fewest filings; the usual permit then takes 69 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the driveway & sidewalk chart →
March: Austin swimming pool permits peak in March (133 against an average month of 100, about 11% of a year's filings); December is the quietest (70). That is from 2,022 permits, October 2023 through September 2026. If you can choose when to schedule a pool build, December has the fewest filings; the usual permit then takes 300 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the swimming pool chart →
May: Austin demolition permits peak in May (113 against an average month of 100, about 9% of a year's filings); December is the quietest (81). That is from 1,925 permits, October 2023 through September 2026. If you can choose when to schedule demolition, December has the fewest filings; the usual permit then takes 133 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the demolition chart →
February: Austin backyard unit (ADU) permits peak in February (130 against an average month of 100, about 11% of a year's filings); August is the quietest (72). That is from 465 permits, October 2023 through September 2026. If you can choose when to schedule ADU construction, August has the fewest filings; the usual permit then takes 405 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month.
Top 10 by permits pulled in the last 12 months, all trades. This is volume, not quality: a busy firm is not a careful one. Pick what you value on the compare page to build a ranking.
| Contractor | Trades | Last 12 mo | All permits |
|---|---|---|---|
| Ies Residential, Inc. | Electrical, Plumbing, HVAC | 686 | 1,132 |
| Radiant Plumbing & AC | Plumbing | 606 | 1,000 |
| Radiant Plumbing and Air Conditioning | Electrical, HVAC | 579 | 1,359 |
| Stan's Heating, Air, Plumbing, & Electrical | HVAC | 516 | 1,678 |
| In Charge Electrical Services, LLC | Electrical | 497 | 1,346 |
| Aei Electric LLC | Electrical | 454 | 1,367 |
| McCullough Heating & Air | HVAC | 419 | 1,356 |
| New Abacus, LLC | Electrical, Plumbing, HVAC | 341 | 826 |
| Base Power | Electrical | 287 | 290 |
| Renewal by Andersen | Remodel & Repair, Home Addition | 271 | 856 |
Each permit counted at its property's ZIP code, October 2023 through September 2026, for the 10 kinds of home work we track. The 10 busiest of 37 ZIP codes with 100 or more permits; each opens permits by trade and the most active contractors there.
| ZIP code | Permits | Share | Top trade | Usual home value |
|---|---|---|---|---|
| 78745 | 6,738 | 8% | Electrical | $429,000 |
| 78704 | 6,514 | 7% | Electrical | $987,000 |
| 78757 | 5,580 | 6% | Plumbing | $654,000 |
| 78731 | 5,502 | 6% | Electrical | $1,073,000 |
| 78703 | 4,850 | 6% | Plumbing | $1,641,000 |
| 78723 | 4,639 | 5% | Electrical | $469,000 |
| 78702 | 4,201 | 5% | Electrical | $622,000 |
| 78747 | 3,674 | 4% | Electrical | $377,000 |
| 78759 | 3,537 | 4% | Electrical | $707,000 |
| 78748 | 3,040 | 3% | Plumbing | $418,000 |
Source: City of Austin issued construction permits. The window is October 2023 through September 2026; a permit filed after that isn't here yet.
A filed value is what the contractor wrote on the permit when they applied. It is not a quote and not the final bill.
Counts are permits, not jobs: one job can need several permits, and one permit can cover several visits. 37.6% of the 4,869 firms on the file match an active license at Texas TDLR air-conditioning and electrical contractor licenses and the Texas plumbing board's company list; the match goes by name and can miss one.
Nobody paid to be on this page and nobody can. How the records work in Austin →
Other cities: Nashville Orlando New York City Chicago Raleigh Cincinnati Cleveland Pittsburgh Miami Minneapolis St. Louis Denver San Diego Colorado Springs Honolulu Albuquerque Boulder Greensboro Saint Paul Arlington, VA Scottsdale Henderson Cambridge Somerville Cary Mesa Naperville Bellevue Cape Coral Provo Palo Alto Bellingham Bend Ames Denton Sugar Land Burlington, VT Seattle San Francisco Medford Anaheim Elk Grove Wilmington, NC Bismarck Tyler, TX Columbus, OH Wheaton, IL San Diego County (unincorporated) Marin County (unincorporated) Sacramento County (unincorporated) Citrus Heights, CA Waco, TX