15,278 permits from 4,266 contractors across 11 kinds of work in the City of Cambridge, October 2023 through September 2026: about 5,093 a year. Electrical is the biggest trade with 3,820 permits. The busiest month for filings is October.
Firms are distinct business names on the file. A linked usual filed value opens what that work costs. Finished is the share of permits a year or more old that the city closed out. Days to finish run from issue to the city's completion date, not from application.
| Trade | Permits | Firms | Active last 12 mo | Usual filed value | Finished | Days to finish | Busiest month |
|---|---|---|---|---|---|---|---|
| Electrical | 3,820 | 1,038 | 553 | $3,800 | 71.7% | 104 | September |
| Remodel, Addition & Alteration | 3,512 | 1,395 | 569 | $24,805 | 49.7% | 304 | October |
| Plumbing | 2,906 | 802 | 415 | — | 67.8% | 69 | July |
| Gas Fitting | 2,057 | 543 | 270 | — | 53.8% | 46 | October |
| HVAC & Sheet Metal | 1,470 | 470 | 192 | — | 54.7% | 325 | October |
| Roofing | 766 | 353 | 139 | $18,000 | 92.1% | 17 | April |
| Solar | 284 | 69 | 37 | $30,074 | 51.0% | 115 | October |
| Demolition | 133 | 104 | 65 | $20,000 | — | 697 | September |
| Fire Sprinkler | 113 | 45 | 25 | — | 93.3% | 308 | May |
| New Construction | 111 | 67 | 34 | $850,000 | 30.8% | 524 | June |
| Siding | 106 | 79 | 34 | $37,120 | — | — | September |
The file we publish splits exactly into the last 12 months on file and the 24 months before them, so these are 12-month periods ending September 2026, not calendar years. Per year scales each period to 12 months. Counts cover the 11 kinds of home work we track, not every permit Cambridge issues.
| Period | Months | Permits | Per year |
|---|---|---|---|
| Oct 2023–Sep 2025 | 24 | 10,309 | 5,154 |
| Oct 2025–Sep 2026 (last 12 months) | 12 | 4,969 | 4,969 |
Share of filings by month, 100 = an average month (the thin line). The 6 biggest trades, October 2023 through September 2026. A tall bar is a busy month at the permit counter, which usually means a longer wait for a contractor.
3,820 permits · busiest September, quietest August
3,512 permits · busiest October, quietest September
2,906 permits · busiest July, quietest May
2,057 permits · busiest October, quietest June
1,470 permits · busiest October, quietest December
766 permits · busiest April, quietest January
| Trade | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Electrical | 95 | 95 | 108 | 99 | 92 | 115 | 109 | 84 | 118 | 102 | 93 | 91 |
| Remodel, Addition & Alteration | 102 | 86 | 105 | 107 | 108 | 105 | 102 | 103 | 79 | 124 | 95 | 83 |
| Plumbing | 103 | 94 | 107 | 95 | 89 | 102 | 113 | 106 | 98 | 109 | 95 | 89 |
| Gas Fitting | 112 | 94 | 99 | 97 | 78 | 77 | 93 | 99 | 88 | 131 | 120 | 113 |
| HVAC & Sheet Metal | 108 | 108 | 100 | 95 | 86 | 93 | 102 | 84 | 117 | 119 | 110 | 79 |
| Roofing | 53 | 69 | 74 | 127 | 125 | 122 | 94 | 119 | 125 | 122 | 113 | 56 |
For each trade, the month with the most permit filings and the month with the fewest, October 2023 through September 2026. Trades do not all peak together, so the busy season depends on the job. Busiest is not the same as best: these are counts of filings, not prices or weather, though a quiet month at the permit counter can mean contractors have more room in the schedule.
September: Cambridge electrical permits peak in September (118 against an average month of 100, about 10% of a year's filings); August is the quietest (84). That is from 3,820 permits, October 2023 through September 2026. If you can choose when to schedule electrical work, August has the fewest filings; the usual permit then takes 104 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the electrical chart →
October: Cambridge remodel, addition & alteration permits peak in October (124 against an average month of 100, about 10% of a year's filings); September is the quietest (79). That is from 3,512 permits, October 2023 through September 2026. If you can choose when to schedule a home remodel, September has the fewest filings; the usual permit then takes 304 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the remodel, addition & alteration chart →
July: Cambridge plumbing permits peak in July (113 against an average month of 100, about 9% of a year's filings); May is the quietest (89). That is from 2,906 permits, October 2023 through September 2026. If you can choose when to schedule plumbing work, May has the fewest filings; the usual permit then takes 69 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the plumbing chart →
October: Cambridge gas fitting permits peak in October (131 against an average month of 100, about 11% of a year's filings); June is the quietest (77). That is from 2,057 permits, October 2023 through September 2026. If you can choose when to schedule gas fitting work, June has the fewest filings; the usual permit then takes 46 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the gas fitting chart →
October: Cambridge HVAC & sheet metal permits peak in October (119 against an average month of 100, about 10% of a year's filings); December is the quietest (79). That is from 1,470 permits, October 2023 through September 2026. If you can choose when to schedule HVAC work, December has the fewest filings; the usual permit then takes 325 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the HVAC & sheet metal chart →
April: Cambridge roofing permits peak in April (127 against an average month of 100, about 11% of a year's filings); January is the quietest (53). That is from 766 permits, October 2023 through September 2026. If you can choose when to schedule roofing work, January has the fewest filings; the usual permit then takes 17 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month. See the roofing chart →
October: Cambridge solar permits peak in October (169 against an average month of 100, about 14% of a year's filings); March is the quietest (72). That is from 284 permits, October 2023 through September 2026. If you can choose when to schedule solar installation, March has the fewest filings; the usual permit then takes 115 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month.
September: Cambridge demolition permits peak in September (162 against an average month of 100, about 14% of a year's filings); January is the quietest (45). That is from 133 permits, October 2023 through September 2026. If you can choose when to schedule demolition, January has the fewest filings; the usual permit then takes 697 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month.
May: Cambridge fire sprinkler permits peak in May (138 against an average month of 100, about 12% of a year's filings); January is the quietest (53). That is from 113 permits, October 2023 through September 2026. If you can choose when to schedule fire sprinkler work, January has the fewest filings; the usual permit then takes 308 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month.
June: Cambridge new construction permits peak in June (162 against an average month of 100, about 14% of a year's filings); February is the quietest (22). That is from 111 permits, October 2023 through September 2026. If you can choose when to schedule new home construction, February has the fewest filings; the usual permit then takes 524 days from issue to sign-off. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month.
September: Cambridge siding permits peak in September (181 against an average month of 100, about 15% of a year's filings); February is the quietest (34). That is from 106 permits, October 2023 through September 2026. If you can choose when to schedule siding work, February has the fewest filings. Busiest is not the same as best: this counts filings, not prices or weather, and we have no prices by month.
Top 10 by permits pulled in the last 12 months, all trades. This is volume, not quality: a busy firm is not a careful one. Pick what you value on the compare page to build a ranking.
| Contractor | Trades | Last 12 mo | All permits |
|---|---|---|---|
| Homeworks Energy | Remodel, Addition & Alteration | 77 | 217 |
| David M Patenaude | Plumbing, Gas Fitting | 62 | 171 |
| Joseph P Barrell | Plumbing, Gas Fitting, HVAC & Sheet Metal | 52 | 89 |
| Stephen S Akian | Plumbing, Gas Fitting, HVAC & Sheet Metal | 45 | 103 |
| Aaron Hanson | Plumbing, Gas Fitting, HVAC & Sheet Metal | 41 | 57 |
| RB Farina Roofing | Remodel, Addition & Alteration, Roofing | 39 | 143 |
| Joseph Marciano | Plumbing, Gas Fitting, HVAC & Sheet Metal | 33 | 89 |
| Timothy M O'Neil | Plumbing, Gas Fitting | 32 | 32 |
| Robert D Beaulieu | Electrical | 28 | 28 |
| FRS Roofing Inc | Remodel, Addition & Alteration, Roofing | 26 | 43 |
Each permit counted at its property's ZIP code, October 2023 through September 2026, for the 11 kinds of home work we track. All 5 ZIP codes with 100 or more permits; each opens permits by trade and the most active contractors there.
Source: City of Cambridge Inspectional Services permits (the city's per-type open-data permit files). The window is October 2023 through September 2026; a permit filed after that isn't here yet.
A filed value is what the contractor wrote on the permit when they applied. It is not a quote and not the final bill.
Counts are permits, not jobs: one job can need several permits, and one permit can cover several visits.
Nobody paid to be on this page and nobody can. How the records work in Cambridge →
Other cities: Nashville Orlando New York City Chicago Austin Raleigh Cincinnati Cleveland Pittsburgh Miami Minneapolis St. Louis Denver San Diego Colorado Springs Honolulu Albuquerque Boulder Greensboro Saint Paul Arlington, VA Scottsdale Henderson Somerville Cary Mesa Naperville Bellevue Cape Coral Provo Palo Alto Bellingham Bend Ames Denton Sugar Land Burlington, VT Seattle San Francisco Medford Anaheim Elk Grove Wilmington, NC Bismarck Tyler, TX Columbus, OH Wheaton, IL San Diego County (unincorporated) Marin County (unincorporated) Sacramento County (unincorporated) Citrus Heights, CA Waco, TX