HVAC permits in unincorporated Pierce County, WA

Data through September 2026 · updated 20 Oct 2026

5,332 HVAC permits were issued in unincorporated Pierce County, October 2024 through September 2026: about 2,666 a year and 35% of all permits. 2,649 HVAC permits in the last 12 months (Oct 2025–Sep 2026), about the same as the 2,683 in the 12 months before. The busiest month is June. The usual one took 24 days from issue to the county's final.

5,332permits issued
2,649last 12 months
Junbusiest month
24days, usual issue to final
62%finished
Sep 2026records through

HVAC permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 276Oct2024Nov 2024: 192Dec 2024: 224Jan 2025: 239Jan2025Feb 2025: 193Mar 2025: 153Apr 2025: 241May 2025: 231Jun 2025: 289Jul 2025: 272JulAug 2025: 217Sep 2025: 156Oct 2025: 223Nov 2025: 176Dec 2025: 174Jan 2026: 214Jan2026Feb 2026: 183Mar 2026: 228Apr 2026: 280May 2026: 238Jun 2026: 297Jul 2026: 255JulAug 2026: 185Sep 2026: 196
The same numbers as a table
MonthPermits
Oct 2024276
Nov 2024192
Dec 2024224
Jan 2025239
Feb 2025193
Mar 2025153
Apr 2025241
May 2025231
Jun 2025289
Jul 2025272
Aug 2025217
Sep 2025156
Oct 2025223
Nov 2025176
Dec 2025174
Jan 2026214
Feb 2026183
Mar 2026228
Apr 2026280
May 2026238
Jun 2026297
Jul 2026255
Aug 2026185
Sep 2026196

Download this table (CSV)

When HVAC permits are filed

By calendar month, 100 = an average month (the thin line). June is the busiest (132), September the quietest (79). A busy month at the permit counter usually means a longer wait for a contractor.

January: 102 (100 = an average month)February: 85 (100 = an average month)March: 86 (100 = an average month)April: 117 (100 = an average month)May: 106 (100 = an average month)June: 132 (100 = an average month)132July: 119 (100 = an average month)August: 90 (100 = an average month)September: 79 (100 = an average month)October: 112 (100 = an average month)November: 83 (100 = an average month)December: 90 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January102
February85
March86
April117
May106
June132
July119
August90
September79
October112
November83
December90

Download this table (CSV)

How long an HVAC permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 1,659 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 20252,683
Finished61.8%
Expired37.0%
Usual days, issue to final24
Middle half, days14–49

Download this table (CSV)

The county's own permit types

How the county filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
Mechanical5,04595%
Mechanical Commercial2875%

Download this table (CSV)

How Pierce County compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

Nearby permit data

HVAC permits for other places in Seattle and Puget Sound. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: Pierce County Open Data, Permits - Pierce County (Permits_Pierce_County, from PALS Plus), read 20 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Building, mechanical, plumbing, manufactured-home, demolition, pool and sign permits Pierce County Planning & Public Works issues for unincorporated land only: Spanaway, Graham, Frederickson, Parkland, South Hill, Lake Tapps, the Key Peninsula, Gig Harbor peninsula and similar places. Tacoma, Lakewood, Puyallup, University Place, Gig Harbor city, Bonney Lake and the other cities run their own permit offices and are not in this file. Engineering, sewer and fire-prevention permits are left out.

  • The county's open permit file names no contractor, so there are no contractor lists, rankings or firm pages for Pierce County.
  • The value is the building valuation the county works out to set the permit fee (largely from floor area and type of construction); mechanical and plumbing permits carry none. It is not a final cost.
  • The file has no property ZIP code, so there are no ZIP code pages for Pierce County.
  • Electrical permits in Washington are issued by the state Department of Labor & Industries, not the county, so electrical work does not appear here; rooftop solar appears only when it needed a county building permit.
  • Mechanical permits cover furnaces, heat pumps and air conditioning, and also gas piping, gas fireplaces and water heaters; those last are counted as plumbing when the description says so.
  • A final date is the county's final date; permits the county cancelled are not counted.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "HVAC permits in unincorporated Pierce County, WA", https://contractorrecords.com/pierce-county/hvac-permits, data through September 2026, from Pierce County Planning & Public Works building-permit records.

Link to a table: By month · Season · Days to final · Permit types.

Download the tables (CSV): HVAC permits by month · HVAC permits by calendar month (index) · HVAC permits: days to final · HVAC permits by permit type.

Common questions

  • How many HVAC permits does Pierce County issue a year?About 2,666 a year in unincorporated Pierce County: 5,332 permits issued October 2024 through September 2026, 2,649 of them in the last 12 months.
  • How long does an HVAC permit take in Pierce County?The usual one took 24 days from issue to the county's final inspection, and the middle half took 14 to 49 days (1,659 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Pierce County file the most HVAC permits?June (132 against an average month of 100); September is the quietest (79). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.