Fence and wall permits in unincorporated Riverside County, CA

Data through September 2026 · updated 23 Oct 2026

3,639 fence and wall permits were issued in unincorporated Riverside County, October 2024 through September 2026: about 1,820 a year and 13% of all permits. 1,636 fence and wall permits in the last 12 months (Oct 2025–Sep 2026), 18% fewer than the 2,003 in the 12 months before. The busiest month is April. The usual one took 150 days from issue to the county's final.

3,639permits issued
1,636last 12 months
Aprbusiest month
150days, usual issue to final
88%finished
Sep 2026records through

Fence and wall permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 165Oct2024Nov 2024: 253Dec 2024: 151Jan 2025: 198Jan2025Feb 2025: 105Mar 2025: 191Apr 2025: 385May 2025: 168Jun 2025: 104Jul 2025: 74JulAug 2025: 114Sep 2025: 95Oct 2025: 130Nov 2025: 65Dec 2025: 94Jan 2026: 114Jan2026Feb 2026: 134Mar 2026: 254Apr 2026: 118May 2026: 201Jun 2026: 167Jul 2026: 107JulAug 2026: 94Sep 2026: 158
The same numbers as a table
MonthPermits
Oct 2024165
Nov 2024253
Dec 2024151
Jan 2025198
Feb 2025105
Mar 2025191
Apr 2025385
May 2025168
Jun 2025104
Jul 202574
Aug 2025114
Sep 202595
Oct 2025130
Nov 202565
Dec 202594
Jan 2026114
Feb 2026134
Mar 2026254
Apr 2026118
May 2026201
Jun 2026167
Jul 2026107
Aug 202694
Sep 2026158

Download this table (CSV)

When fence and wall permits are filed

By calendar month, 100 = an average month (the thin line). April is the busiest (166), July the quietest (60). A busy month at the permit counter usually means a longer wait for a contractor.

January: 103 (100 = an average month)February: 79 (100 = an average month)March: 147 (100 = an average month)April: 166 (100 = an average month)166May: 122 (100 = an average month)June: 89 (100 = an average month)July: 60 (100 = an average month)August: 69 (100 = an average month)September: 83 (100 = an average month)October: 97 (100 = an average month)November: 105 (100 = an average month)December: 81 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January103
February79
March147
April166
May122
June89
July60
August69
September83
October97
November105
December81

Download this table (CSV)

How long a fence and wall permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 1,757 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 20252,003
Finished87.7%
Expired6.1%
Usual days, issue to final150
Middle half, days79–245

Download this table (CSV)

The county's own permit types

How the county filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
Repeat Production Wall2,16359%
Subdivision Retaining Wall Engineered42112%
Garden Wall-County Standard38911%
Garden Wall-Engineered2998%
Retaining Wall-County Standard2076%
Retaining Wall-Engineered1404%
Fences Over 7’20under 1%

Download this table (CSV)

Nearby permit data

Fence and wall permits for other places in Los Angeles and the Inland Empire. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: Riverside County GIS Open Data, PLUS_ACTIVITIES (Public Land Use System), Building department records, read 23 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Permits Riverside County Building and Safety issues for unincorporated land only: places such as Thermal, Mecca, Winchester, French Valley, Mead Valley, Anza, Aguanga, Temescal Valley and the Temecula wine country. Riverside, Moreno Valley, Corona, Temecula, Murrieta, Palm Springs and the county's other incorporated cities (28 in all) run their own permit offices and are not in this file. Blythe permits, which the county keeps under their own permit type, are left out too.

  • The county's file names no contractor, so there are no contractor lists, rankings or firm pages for Riverside County.
  • The file has no declared job value, so we show no costs.
  • The file gives a parcel number but no ZIP code, so there are no ZIP code pages.
  • Tract builders file one permit per house, so a new subdivision shows as many new-home permits, often with a matching repeat-production wall permit for each lot.
  • Battery storage permits are counted as electrical; rooftop and ground-mount solar as solar.
  • A final date is the county's completed date on a permit marked Final. Administratively closed permits count as expired.
  • Grading, hourly inspection, agricultural fee-only and legacy converted records are left out.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Fence and wall permits in unincorporated Riverside County, CA", https://contractorrecords.com/riverside-county/fence-permits, data through September 2026, from Riverside County Building and Safety building-permit records.

Link to a table: By month · Season · Days to final · Permit types.

Download the tables (CSV): Fences & walls permits by month · Fences & walls permits by calendar month (index) · Fences & walls permits: days to final · Fences & walls permits by permit type.

Common questions

  • How many fence and wall permits does Riverside County issue a year?About 1,820 a year in unincorporated Riverside County: 3,639 permits issued October 2024 through September 2026, 1,636 of them in the last 12 months.
  • How long does a fence and wall permit take in Riverside County?The usual one took 150 days from issue to the county's final inspection, and the middle half took 79 to 245 days (1,757 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Riverside County file the most fence and wall permits?April (166 against an average month of 100); July is the quietest (60). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.