New home permits in unincorporated Riverside County, CA

Data through September 2026 · updated 23 Oct 2026

3,769 new home permits were issued in unincorporated Riverside County, October 2024 through September 2026: about 1,884 a year and 14% of all permits. 1,765 new home permits in the last 12 months (Oct 2025–Sep 2026), 12% fewer than the 2,004 in the 12 months before. The busiest month is February. The usual one took 256 days from issue to the county's final.

3,769permits issued
1,765last 12 months
Febbusiest month
256days, usual issue to final
84%finished
Sep 2026records through

New home permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 139Oct2024Nov 2024: 143Dec 2024: 236Jan 2025: 177Jan2025Feb 2025: 430Mar 2025: 245Apr 2025: 114May 2025: 104Jun 2025: 80Jul 2025: 103JulAug 2025: 85Sep 2025: 148Oct 2025: 76Nov 2025: 70Dec 2025: 114Jan 2026: 125Jan2026Feb 2026: 122Mar 2026: 152Apr 2026: 288May 2026: 117Jun 2026: 224Jul 2026: 106JulAug 2026: 102Sep 2026: 269
The same numbers as a table
MonthPermits
Oct 2024139
Nov 2024143
Dec 2024236
Jan 2025177
Feb 2025430
Mar 2025245
Apr 2025114
May 2025104
Jun 202580
Jul 2025103
Aug 202585
Sep 2025148
Oct 202576
Nov 202570
Dec 2025114
Jan 2026125
Feb 2026122
Mar 2026152
Apr 2026288
May 2026117
Jun 2026224
Jul 2026106
Aug 2026102
Sep 2026269

Download this table (CSV)

When new home permits are filed

By calendar month, 100 = an average month (the thin line). February is the busiest (176), August the quietest (60). A busy month at the permit counter usually means a longer wait for a contractor.

January: 96 (100 = an average month)February: 176 (100 = an average month)176March: 126 (100 = an average month)April: 128 (100 = an average month)May: 70 (100 = an average month)June: 97 (100 = an average month)July: 67 (100 = an average month)August: 60 (100 = an average month)September: 133 (100 = an average month)October: 68 (100 = an average month)November: 68 (100 = an average month)December: 111 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January96
February176
March126
April128
May70
June97
July67
August60
September133
October68
November68
December111

Download this table (CSV)

How long a new home permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 1,680 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 20252,004
Finished83.8%
Expired0.9%
Usual days, issue to final256
Middle half, days186–344

Download this table (CSV)

The county's own permit types

How the county filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
Production Tract Dwelling2,61469%
Manufactured Home Residential58415%
Single Family Detached Dwelling3499%
Model Tract Dwelling1113%
Mobile Home Park Install531%
Replacement Manufactured Home Residential391%
Dwelling Final Inspection10under 1%
Low Profile Residential (Non Pf)7under 1%
Permit Ready Adu2under 1%

Download this table (CSV)

How Riverside County compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

Nearby permit data

New home permits for other places in Los Angeles and the Inland Empire. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: Riverside County GIS Open Data, PLUS_ACTIVITIES (Public Land Use System), Building department records, read 23 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Permits Riverside County Building and Safety issues for unincorporated land only: places such as Thermal, Mecca, Winchester, French Valley, Mead Valley, Anza, Aguanga, Temescal Valley and the Temecula wine country. Riverside, Moreno Valley, Corona, Temecula, Murrieta, Palm Springs and the county's other incorporated cities (28 in all) run their own permit offices and are not in this file. Blythe permits, which the county keeps under their own permit type, are left out too.

  • The county's file names no contractor, so there are no contractor lists, rankings or firm pages for Riverside County.
  • The file has no declared job value, so we show no costs.
  • The file gives a parcel number but no ZIP code, so there are no ZIP code pages.
  • Tract builders file one permit per house, so a new subdivision shows as many new-home permits, often with a matching repeat-production wall permit for each lot.
  • Battery storage permits are counted as electrical; rooftop and ground-mount solar as solar.
  • A final date is the county's completed date on a permit marked Final. Administratively closed permits count as expired.
  • Grading, hourly inspection, agricultural fee-only and legacy converted records are left out.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "New home permits in unincorporated Riverside County, CA", https://contractorrecords.com/riverside-county/new-home-permits, data through September 2026, from Riverside County Building and Safety building-permit records.

Link to a table: By month · Season · Days to final · Permit types.

Download the tables (CSV): New homes permits by month · New homes permits by calendar month (index) · New homes permits: days to final · New homes permits by permit type.

Common questions

  • How many new home permits does Riverside County issue a year?About 1,884 a year in unincorporated Riverside County: 3,769 permits issued October 2024 through September 2026, 1,765 of them in the last 12 months.
  • How long does a new home permit take in Riverside County?The usual one took 256 days from issue to the county's final inspection, and the middle half took 186 to 344 days (1,680 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Riverside County file the most new home permits?February (176 against an average month of 100); August is the quietest (60). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.