How long do permits take in Richmond, CA?

Data through April 2025 · updated 21 Oct 2026

The usual permit in Richmond takes 60 days from issue to the city's final inspection; the middle half take 27 to 147 days. That is from 2,631 permits issued May 2023–Apr 2024 that reached a final. Roofing permits are quickest at 31 days; new home permits take longest at 160 days. This is the time to finish the work and close the permit, not the wait for approval.

60days, usual issue to final
27–147days, middle half
76%finished
2,631permits with a final date
Apr 2025records through

Getting the permit vs finishing the work: two different clocks

“How long does a permit take?” can mean two waits. This page measures the second one.

Getting the permit (not measured): application → issue, the wait for the city to approve the plans. Ask the city for its current review times.

Finishing the work (measured here): issue → final. From the day the city issued the permit to the day it recorded the final inspection. We count only permits issued May 2023–Apr 2024, at least 12 months before the file ends, so slow jobs have had time to finish; a permit still open is not in the days.

By kind of work

Permits issued May 2023–Apr 2024. Usual days is the middle permit among those with a final date: half finished sooner, half later. Middle half is the range the middle 50% fell in. Kinds of work with fewer than 100 permits in that period are left out.

Kind of workPermitsFinishedExpiredUsual days to finalMiddle half (days)
Electrical59176.0%10.8%6928–148
Remodels & repairs62880.9%6.8%6837–146
Roofing52986.4%8.5%3116–77
Solar50479.8%15.9%6335–123
Plumbing40461.4%22.8%3515–115
HVAC27872.3%15.5%5429–108
Other35671.6%5.3%14242–302

Download this table (CSV)

How long each kind of permit takes

Each kind of work on its own, issue to the city's final.

How long does electrical work take in Richmond, from permit to final?

The usual electrical permit in Richmond takes 69 days from issue to final; the middle half take 28 to 148 days (448 permits with a final date, issued May 2023–Apr 2024). 76% of the 591 permits issued then have finished and 11% expired. Richmond electrical permits →

How long does a remodel take in Richmond, from permit to final?

The usual remodel and repair permit in Richmond takes 68 days from issue to final; the middle half take 37 to 146 days (507 permits with a final date, issued May 2023–Apr 2024). 81% of the 628 permits issued then have finished and 7% expired. Richmond remodel and repair permits →

How long does a roof replacement take in Richmond, from permit to final?

The usual roofing permit in Richmond takes 31 days from issue to final; the middle half take 16 to 77 days (455 permits with a final date, issued May 2023–Apr 2024). 86% of the 529 permits issued then have finished and 8% expired. Richmond roofing permits →

How long does a solar installation take in Richmond, from permit to final?

The usual solar permit in Richmond takes 63 days from issue to final; the middle half take 35 to 123 days (401 permits with a final date, issued May 2023–Apr 2024). 80% of the 504 permits issued then have finished and 16% expired. Richmond solar permits →

How long does plumbing work take in Richmond, from permit to final?

The usual plumbing permit in Richmond takes 35 days from issue to final; the middle half take 15 to 115 days (240 permits with a final date, issued May 2023–Apr 2024). 61% of the 404 permits issued then have finished and 23% expired. Richmond plumbing permits →

How long does an HVAC replacement take in Richmond, from permit to final?

The usual HVAC permit in Richmond takes 54 days from issue to final; the middle half take 29 to 108 days (198 permits with a final date, issued May 2023–Apr 2024). 72% of the 278 permits issued then have finished and 16% expired. Richmond HVAC permits →

How long does building a new home take in Richmond, from permit to final?

The usual new home permit in Richmond takes 160 days from issue to final; the middle half take 137 to 176 days (70 permits with a final date, issued May 2023–Apr 2024).

How Richmond compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

Nearby permit data

How long permits take for other places in the Bay Area. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: Transparent Richmond, PermitTrak (Socrata dataset qg2r-652v), read 21 Oct 2026. We count permits issued May 2023 through April 2025; denied and withdrawn permits are left out.

Building and trade permits the City of Richmond issued inside the city limits, including SolarAPP+ solar permits; a few city parcels carry an El Sobrante or San Pablo mailing address. Encroachment, fire, wastewater, rent-control and business permits, plan-check records and revisions of earlier permits are left out. Unincorporated North Richmond and El Sobrante are permitted by Contra Costa County and are not in this file.

  • The city's file names no contractor, so there are no contractor lists, rankings or firm pages for Richmond.
  • The city's published file holds no building permit issued after April 2025, although it is still updated for other permit kinds, so these pages end with April 2025.
  • Finished means the city's status is Finaled or Closed; a final date comes from the city's finaled date. Expired permits lapsed without a final inspection; cancelled permits are not counted.
  • The value is the job value declared on the permit.
  • Homes are the permits the city files as residential (building, electrical, plumbing and mechanical) plus SolarAPP+ rooftop solar permits.
  • Solar battery (Powerwall) permits without panels count as electrical; seismic retrofits and alteration or repair permits count as remodels.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "How long do permits take in Richmond, CA?", https://contractorrecords.com/richmond-ca/how-long-does-a-permit-take, data through April 2025, from City of Richmond Building Services building-permit records.

Link to a table: By kind of work · Each kind of permit.

Download the tables (CSV): Days to final by kind of work.

Common questions

  • What is the permit turnaround in Richmond?From issue to final inspection, the usual permit takes 60 days (middle half 27 to 147 days), from 2,631 permits issued May 2023–Apr 2024. The wait to get a permit issued is not in this file; ask the city for its current review times.
  • Which permits finish fastest in Richmond?Roofing permits, at 31 days. The slowest are new home permits, at 160 days. Bigger jobs take longer; so does work where the final inspection is easy to forget.
  • How many permits actually get finished in Richmond?76% of the 3,485 permits issued May 2023–Apr 2024 have finished; 11% expired without a final and the rest are still open.
  • Why does an open permit matter to me?An unfinished permit stays with the property, not the contractor. It can hold up a sale or a refinance. Ask whoever does the work to call for the final inspection and show you the result.