How long do permits take in San Francisco, CA?

The usual San Francisco permit takes 119 days from issue to the city's final inspection or closeout, across all 10 kinds of work on file (24,197 permits, October 2023 through September 2026). The usual roofing permit, the biggest trade here, takes 36 days. Roofing is also the quickest trade here; addition the slowest at 621 days. This is the turnaround to finish the work and close the permit, not the wait for approval.

119days, usual across trades
36days, usual roofing permit
87%roofing permits finished
24,197permits read
Sep 2026records through

Getting the permit vs finishing the work: two different clocks

“How long does a permit take?” can mean two waits. This page measures the second one.

Getting the permit (not measured): application → issue, the wait for the city to approve it. San Francisco's file we read does not carry a usable application date, so we don't guess at it. Ask the permit office for its current review times.

Finishing the work (measured here): issue → completion. The day the city issued the permit to the day it recorded a final inspection or closeout. That is the contractor's part: doing the work and getting it signed off.

What “finished” means in San Francisco: For contractors with at least 5 permits a year or more old, the share the city marked complete, adjusted for permit age. Permits that expire, are suspended or are revoked count against it.

Speed: How long their permits take from issue to the city's completed date, compared with other San Francisco contractors in the trade. Shown for firms with 10+ permits.

By trade

Usual is the middle permit: half finish sooner, half later. Finished is the share of permits a year or more old that the city closed out.

TradePermitsUsual days to finishFinishedFirms with 10+ permits
Roofing9,5373687.2%142
Kitchen, Bath & Remodel5,12618081.4%70
Windows & Skylights4,05015985.8%30
Decks, Stairs & Porches1,70123782.7%6
Siding, Dry Rot & Exterior Repair1,07610379.4%10
Foundation & Seismic78119182.2%8
Addition67462151.7%0
Fire Sprinklers & Alarms47833377.4%13
Solar & Battery44134974.2%8
ADU33356752.5%0

How long each kind of permit takes in San Francisco

Each trade on its own, from issue to the city's sign-off. The spread between the quickest and slowest quarter of firms is the part you can choose.

How long does roofing work take in San Francisco, from permit to sign-off?

The usual roofing permit in San Francisco takes 36 days from issue to the city's final inspection or closeout (9,537 permits, October 2023 through September 2026). 87.2% of roofing permits a year or more old have been closed out. The quickest quarter of firms usually finish in 0.5 months, the slowest quarter in 1.6 months. The wait for approval before issue is not in San Francisco's file.

0.5 moquickest quarter of firms
0.9 mousual firm
1.6 moslowest quarter of firms

131 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare San Francisco roofing contractors →

How long does a home remodel take in San Francisco, from permit to sign-off?

The usual kitchen, bath & remodel permit in San Francisco takes 180 days from issue to the city's final inspection or closeout (5,126 permits, October 2023 through September 2026). 81.4% of kitchen, bath & remodel permits a year or more old have been closed out. The quickest quarter of firms usually finish in 4 months, the slowest quarter in 6 months. The wait for approval before issue is not in San Francisco's file.

4 moquickest quarter of firms
4.7 mousual firm
6 moslowest quarter of firms

63 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare San Francisco kitchen, bath & remodel contractors →

How long does window replacement take in San Francisco, from permit to sign-off?

The usual windows & skylights permit in San Francisco takes 159 days from issue to the city's final inspection or closeout (4,050 permits, October 2023 through September 2026). 85.8% of windows & skylights permits a year or more old have been closed out. The quickest quarter of firms usually finish in 2.9 months, the slowest quarter in 4.4 months. The wait for approval before issue is not in San Francisco's file.

2.9 moquickest quarter of firms
2.9 mousual firm
4.4 moslowest quarter of firms

29 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare San Francisco windows & skylights contractors →

How long does a deck build take in San Francisco, from permit to sign-off?

The usual decks, stairs & porches permit in San Francisco takes 237 days from issue to the city's final inspection or closeout (1,701 permits, October 2023 through September 2026). 82.7% of decks, stairs & porches permits a year or more old have been closed out. The wait for approval before issue is not in San Francisco's file.

How long does exterior work take in San Francisco, from permit to sign-off?

The usual siding, dry rot & exterior repair permit in San Francisco takes 103 days from issue to the city's final inspection or closeout (1,076 permits, October 2023 through September 2026). 79.4% of siding, dry rot & exterior repair permits a year or more old have been closed out. The quickest quarter of firms usually finish in 2 months, the slowest quarter in 2.7 months. The wait for approval before issue is not in San Francisco's file.

2 moquickest quarter of firms
2.3 mousual firm
2.7 moslowest quarter of firms

9 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare San Francisco siding, dry rot & exterior repair contractors →

How long does foundation work take in San Francisco, from permit to sign-off?

The usual foundation & seismic permit in San Francisco takes 191 days from issue to the city's final inspection or closeout (781 permits, October 2023 through September 2026). 82.2% of foundation & seismic permits a year or more old have been closed out. The wait for approval before issue is not in San Francisco's file.

How long does a home addition take in San Francisco, from permit to sign-off?

The usual addition permit in San Francisco takes 621 days from issue to the city's final inspection or closeout (674 permits, October 2023 through September 2026). 51.7% of addition permits a year or more old have been closed out. The wait for approval before issue is not in San Francisco's file.

How long does fire sprinkler and alarm work take in San Francisco, from permit to sign-off?

The usual fire sprinklers & alarms permit in San Francisco takes 333 days from issue to the city's final inspection or closeout (478 permits, October 2023 through September 2026). 77.4% of fire sprinklers & alarms permits a year or more old have been closed out. The wait for approval before issue is not in San Francisco's file.

How long does solar installation take in San Francisco, from permit to sign-off?

The usual solar & battery permit in San Francisco takes 349 days from issue to the city's final inspection or closeout (441 permits, October 2023 through September 2026). 74.2% of solar & battery permits a year or more old have been closed out. The quickest quarter of firms usually finish in 5.8 months, the slowest quarter in 8.1 months. The wait for approval before issue is not in San Francisco's file.

5.8 moquickest quarter of firms
8.1 mousual firm
8.1 moslowest quarter of firms

5 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare San Francisco solar & battery contractors →

How long does ADU construction take in San Francisco, from permit to sign-off?

The usual ADU permit in San Francisco takes 567 days from issue to the city's final inspection or closeout (333 permits, October 2023 through September 2026). 52.5% of ADU permits a year or more old have been closed out. The wait for approval before issue is not in San Francisco's file.

How these numbers are made

Source: San Francisco DBI building permits on one- and two-family homes, with the contractor from the city's permit contacts file. The window is October 2023 through September 2026; a permit filed after that isn't here yet.

A filed value is what the contractor wrote on the permit when they applied. It is not a quote and not the final bill.

Counts are permits, not jobs: one job can need several permits, and one permit can cover several visits.

Nobody paid to be on this page and nobody can. How the records work in San Francisco →

Common questions

  • What is the permit turnaround in San Francisco?From issue to final inspection or closeout, the usual roofing permit in San Francisco takes 36 days (9,537 permits, October 2023 through September 2026). The wait to get a permit issued is not in San Francisco's file; ask the permit office for its current review times.
  • How long does it take to get a permit approved in San Francisco?We can't say from the record: San Francisco's file we read has no usable application date, so the approval wait is not in these numbers and we don't estimate it. Every figure on this page runs from the day the permit was issued to the day the city closed it. Ask the permit office for its current review times.
  • Which permits finish fastest in San Francisco?Roofing at 36 days. The slowest is addition at 621 days. Bigger jobs take longer; so do trades where the final inspection is easy to forget.
  • How many permits actually get finished?It depends on the trade: 87.2% of roofing permits a year or more old were closed out, against 51.7% for addition. An open permit can mean unfinished work or a missed final inspection; either one can surface when you sell.
  • Why does an open permit matter to me?An unfinished permit stays on the property, not the contractor. It can hold up a sale or a refinance, and the fix is on you. Ask any contractor you hire to close their permit and show you the final.
  • Can I see this for one contractor?Yes. Every San Francisco roofing contractor is listed with their finished share and time to finish; pick what you value and the list moves. San Francisco permit statistics →

Other cities: Nashville Orlando New York City Chicago Austin Raleigh Cincinnati Cleveland Pittsburgh Miami Minneapolis St. Louis Denver San Diego Colorado Springs Honolulu Albuquerque Boulder Greensboro Saint Paul Arlington, VA Scottsdale Henderson Cambridge Somerville Cary Mesa Naperville Bellevue Cape Coral Provo Palo Alto Bellingham Bend Ames Denton Sugar Land Burlington, VT Seattle Medford Anaheim Elk Grove Wilmington, NC Bismarck Tyler, TX Columbus, OH Wheaton, IL San Diego County (unincorporated) Marin County (unincorporated) Sacramento County (unincorporated) Citrus Heights, CA Waco, TX