330 new home permits were issued in the City of Spokane, April 2024 through March 2026: about 165 a year and under 1% of all permits. 108 new home permits in the last 12 months on file (Apr 2025–Mar 2026), 51% fewer than the 222 in the 12 months before. The busiest month is October.
Permits issued each month, April 2024 through March 2026.
| Month | Permits |
|---|---|
| Apr 2024 | 3 |
| May 2024 | 12 |
| Jun 2024 | 29 |
| Jul 2024 | 22 |
| Aug 2024 | 21 |
| Sep 2024 | 33 |
| Oct 2024 | 28 |
| Nov 2024 | 5 |
| Dec 2024 | 14 |
| Jan 2025 | 20 |
| Feb 2025 | 11 |
| Mar 2025 | 24 |
| Apr 2025 | 22 |
| May 2025 | 14 |
| Jun 2025 | 10 |
| Jul 2025 | 11 |
| Aug 2025 | 5 |
| Sep 2025 | 13 |
| Oct 2025 | 19 |
| Nov 2025 | 4 |
| Dec 2025 | 3 |
| Jan 2026 | 2 |
| Feb 2026 | 1 |
| Mar 2026 | 4 |
By calendar month, 100 = an average month (the thin line). October is the busiest (171), November the quietest (33). A busy month at the permit counter usually means a longer wait for a contractor.
| Month | Index |
|---|---|
| January | 80 |
| February | 44 |
| March | 102 |
| April | 91 |
| May | 95 |
| June | 142 |
| July | 120 |
| August | 95 |
| September | 167 |
| October | 171 |
| November | 33 |
| December | 62 |
Permits issued Apr 2024–Mar 2025, at least 12 months before the file ends.
| Measure | Value |
|---|---|
| Permits issued Apr 2024–Mar 2025 | 222 |
| Finished | 85.1% |
How the city filed these permits. We group its types into kinds of work; this is the split.
| Permit type | Permits | Share |
|---|---|---|
| Residential Building Permit | 316 | 96% |
| Manufactured Structure Permit | 14 | 4% |
Electrical (15,771)HVAC (9,746)Roofing (4,539)Plumbing (3,628)Remodels & repairs (1,942)Fences & walls (858)Solar (473)Garages, sheds & shade structures (438)Demolition (215)
From our cross-city data studies: the same measure, read the same way, for every city we cover.
Source: City of Spokane GIS, Permit (Building and Engineering Permits) layer behind the Permit Activity Map, read 19 Oct 2026. We count permits issued April 2024 through March 2026; denied and withdrawn permits are left out.
Building and trade permits the City of Spokane issues inside city limits: residential and commercial building, electrical, mechanical, plumbing, roofing/siding/window, solar, fence, demolition, pool, manufactured-home and sign permits. Side sewer, water and right-of-way permits from the city's Engineering side, planning cases and short-term rental licences are not counted. Spokane Valley, Liberty Lake and unincorporated Spokane County run their own permit offices and are not in this file.
Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →
Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:
Contractor Records, "New home permits in the City of Spokane, WA", https://contractorrecords.com/spokane/new-home-permits, data through March 2026, from City of Spokane Development Services Center building-permit records.Link to a table: By month · Season · How many get finished · Permit types.
Download the tables (CSV): New homes permits by month · New homes permits by calendar month (index) · New homes permits: finished share · New homes permits by permit type.