Data through March 2026 · updated 19 Oct 2026
4,539 roofing permits were issued in the City of Spokane, April 2024 through March 2026: about 2,270 a year and 12% of all permits. 2,379 roofing permits in the last 12 months on file (Apr 2025–Mar 2026), 10% more than the 2,160 in the 12 months before. The busiest month is April.
Permits issued each month, April 2024 through March 2026.
| Month | Permits |
|---|---|
| Apr 2024 | 246 |
| May 2024 | 234 |
| Jun 2024 | 215 |
| Jul 2024 | 244 |
| Aug 2024 | 234 |
| Sep 2024 | 190 |
| Oct 2024 | 194 |
| Nov 2024 | 100 |
| Dec 2024 | 98 |
| Jan 2025 | 102 |
| Feb 2025 | 87 |
| Mar 2025 | 216 |
| Apr 2025 | 263 |
| May 2025 | 225 |
| Jun 2025 | 246 |
| Jul 2025 | 213 |
| Aug 2025 | 205 |
| Sep 2025 | 224 |
| Oct 2025 | 243 |
| Nov 2025 | 167 |
| Dec 2025 | 90 |
| Jan 2026 | 140 |
| Feb 2026 | 125 |
| Mar 2026 | 238 |
By calendar month, 100 = an average month (the thin line). April is the busiest (135), December the quietest (50). A busy month at the permit counter usually means a longer wait for a contractor.
| Month | Index |
|---|---|
| January | 64 |
| February | 56 |
| March | 120 |
| April | 135 |
| May | 121 |
| June | 122 |
| July | 121 |
| August | 116 |
| September | 109 |
| October | 116 |
| November | 71 |
| December | 50 |
Permits issued Apr 2024–Mar 2025, at least 12 months before the file ends.
| Measure | Value |
|---|---|
| Permits issued Apr 2024–Mar 2025 | 2,160 |
| Finished | 89.9% |
Electrical (15,771)HVAC (9,746)Plumbing (3,628)Remodels & repairs (1,942)Fences & walls (858)Solar (473)Garages, sheds & shade structures (438)New homes (330)Demolition (215)
From our cross-city data studies: the same measure, read the same way, for every city we cover.
Source: City of Spokane GIS, Permit (Building and Engineering Permits) layer behind the Permit Activity Map, read 19 Oct 2026. We count permits issued April 2024 through March 2026; denied and withdrawn permits are left out.
Building and trade permits the City of Spokane issues inside city limits: residential and commercial building, electrical, mechanical, plumbing, roofing/siding/window, solar, fence, demolition, pool, manufactured-home and sign permits. Side sewer, water and right-of-way permits from the city's Engineering side, planning cases and short-term rental licences are not counted. Spokane Valley, Liberty Lake and unincorporated Spokane County run their own permit offices and are not in this file.
Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →
Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:
Contractor Records, "Roofing permits in the City of Spokane, WA", https://contractorrecords.com/spokane/roofing-permits, data through March 2026, from City of Spokane Development Services Center building-permit records.Link to a table: By month · Season · How many get finished.
Download the tables (CSV): Roofing permits by month · Roofing permits by calendar month (index) · Roofing permits: finished share.