Electrical Work Cost in Cary, NC: what the permits say

How much does electrical work cost in Cary? The usual electrical job filed with Cary is $2,117, from 1,452 priced permits (October 2023 through September 2026); the middle half of firms file between $1,350 and $3,900. A filed value is what the contractor wrote on the permit, not a quote or the final bill.

$2,117usual filed value
$1,350–$3,900middle half of firms' usual jobs
1,452priced permits (100% of 1,455)
279firms on file
41days, permit issue to final
Sep 2026records through

How much does electrical work cost in Cary?

The usual electrical job filed with Cary is $2,117, from 1,452 priced permits, October 2023 through September 2026. The middle half of firms usually file between $1,350 and $3,900. Half of jobs were filed for less, half for more. A filed value is what the contractor wrote on the permit, not a quote or the final bill. An electrical permit here usually takes 41 days from issue to final inspection. How long permits take →

What the spread looks like

Approximately, from each firm's own spread: every firm's range of filed values, weighted by its 1,452 priced permits across 278 firms, pooled into one. Half of Cary electrical permits were filed between $1,100 and $4,300.

PercentileFiled valueReads as
10th$7001 in 10 permits filed below
25th$1,1001 in 4 filed below
50th$2,200the middle permit
75th$4,3001 in 4 filed above
90th$7,6001 in 10 filed above

By home value

Firms split into thirds by the usual value of the homes they work on, with each third's usual filed value weighted by permits. Home values: Wake County parcel values.

Firms working onUsual home valueUsual filed valueFirmsPermits
Lower thirdunder $535,342$2,27587271
Middle third$535,342–$709,879$2,05888922
Upper third$719,924 and up$2,00088246

Busiest firms and what they usually charge

Top 10 by permits in the last 12 months. Usual is each firm's middle filed value; middle half is the range its middle half of jobs were filed in. Busy is not the same as careful: pick what you value to build a list.

FirmPermitsLast 12 moUsualMiddle halfFinished
Alternate Current Solutions16757$2,058$1,124–$4,21679.2%
Dawson's Electric Inc.8536$4,745$1,943–$8,00074.8%
Touchstone Electric Rdu, LLC4132$700$700–$3,3004 of 9
Michael & Sons10428$3,500$1,500–$6,00078.5%
Roy Electric LLC9926$1,170$850–$2,00083.1%
Triad Electrical Serv3019$3,503$1,532–$4,82057.2%
Raleigh Electric Co4916$975$500–$2,22087.5%
NC Solar Now Inc.1514$15,095$4,030–$19,605—
The Iglesias Group LLC1212$650$375–$900—
Pro Elite Electrical Service2010$1,250$807–$2,62554.5%

Why filed values run low or high

  • The 10 busiest firms usually file $2,058; the 253 firms with fewer than 10 permits usually file $2,250.
  • Firms working on the most expensive third of homes (usual home value $719,924 and up) usually file $2,000, against $2,275 for the least expensive third.
  • One permit type covers small and large jobs: 1 in 10 electrical permits is filed under $700 and 1 in 10 over $7,600, 11 times as much.
  • 99.8% of the 1,455 permits carry a value; the 3 without one are left out of every figure here.

Is your quote normal? Compare it with 1,452 filed values

Line your quote up against the file. In Cary, 1 in 10 electrical filed values sit under $700, the middle half between $1,100 and $4,300, and 1 in 10 over $7,600.

  • $9,900Above $7,600: higher than 9 in 10 filed values for this work in Cary.
  • $2,117Right at the usual $2,117: in the middle of the file.
  • $490Below $700: lower than 9 in 10. Ask what the quote leaves out.

When to schedule electrical work in Cary

Cary files the fewest electrical permits in December (79 against an average month of 100) and the most in July (116). If you can choose, ask for quotes in a quiet month. We have no prices by month, so this is about crews' schedules, not a discount. When each trade is busiest in Cary →

How these numbers are made

Source: Town of Cary building permit applications (issued permits only). The window is October 2023 through September 2026; a permit filed after that isn't here yet.

Usual is the middle permit: half were filed for less, half for more. Only permits with a filed value count; a value of $0 or none is left out.

The spread is approximate: we keep seven points of each firm's own range of filed values, not every permit, and pool them.

Nobody paid to be on this page and nobody can. How the records work in Cary →

Common questions

  • How many quotes should I get for an electrical job in Cary?At least three. In the permit record the middle half of Cary electrical firms usually file between $1,350 and $3,900 a job, so two ordinary firms can sit 2.9 times apart and both be normal for Cary. A third quote shows which one is the outlier. Filed values are what contractors wrote on permits, not quotes, so use them to judge the spread, not to price your own job.
  • What range is normal for electrical jobs in Cary?Half of permits were filed between $1,100 and $4,300; 8 in 10 between $700 and $7,600. These are approximate, pooled from each firm's own spread.
  • How much do electricians charge in Cary?The usual electrical job is filed at $2,117; the middle half of firms usually file between $1,350 and $3,900. The 10 firms with the most permits in the last 12 months usually file $2,058, about the same as the usual. See every firm's usual job →
  • Do bigger houses get bigger bills?Not in the file: firms working on the upper third of homes by value usually file $2,000, the lower third $2,275.
  • Where does this data come from?Town of Cary building permit applications (issued permits only), read October 2026. How the records work in Cary →

Electrical cost in other cities: Nashville Orlando Cleveland Pittsburgh Miami Colorado Springs Honolulu Boulder Saint Paul Arlington, VA Cambridge Somerville Mesa Naperville Cape Coral Palo Alto Denton Burlington, VT Seattle Medford Elk Grove Wheaton, IL Marin County (unincorporated) Sacramento County (unincorporated) Citrus Heights, CA