907 electrical permits were issued in Corona, October 2024 through September 2026: about 454 a year and 12% of all permits. 492 electrical permits in the last 12 months (Oct 2025–Sep 2026), 19% more than the 415 in the 12 months before. The busiest month is September. The usual one took 29 days from issue to the city's final. 92882 has the most, 396.

907permits issued
492last 12 months
Sepbusiest month
29days, usual issue to final
71%finished
$3,500usual declared value
Sep 2026records through

Electrical permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 34Oct2024Nov 2024: 36Dec 2024: 22Jan 2025: 33Jan2025Feb 2025: 32Mar 2025: 33Apr 2025: 41May 2025: 31Jun 2025: 39Jul 2025: 39JulAug 2025: 25Sep 2025: 50Oct 2025: 48Nov 2025: 47Dec 2025: 19Jan 2026: 34Jan2026Feb 2026: 32Mar 2026: 46Apr 2026: 41May 2026: 35Jun 2026: 53Jul 2026: 42JulAug 2026: 52Sep 2026: 43
The same numbers as a table
MonthPermits
Oct 202434
Nov 202436
Dec 202422
Jan 202533
Feb 202532
Mar 202533
Apr 202541
May 202531
Jun 202539
Jul 202539
Aug 202525
Sep 202550
Oct 202548
Nov 202547
Dec 202519
Jan 202634
Feb 202632
Mar 202646
Apr 202641
May 202635
Jun 202653
Jul 202642
Aug 202652
Sep 202643

Download this table (CSV)

When electrical permits are filed

By calendar month, 100 = an average month (the thin line). September is the busiest (123), December the quietest (54). A busy month at the permit counter usually means a longer wait for a contractor.

January: 89 (100 = an average month)February: 85 (100 = an average month)March: 105 (100 = an average month)April: 108 (100 = an average month)May: 87 (100 = an average month)June: 122 (100 = an average month)July: 107 (100 = an average month)August: 102 (100 = an average month)September: 123 (100 = an average month)123October: 108 (100 = an average month)November: 110 (100 = an average month)December: 54 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January89
February85
March105
April108
May87
June122
July107
August102
September123
October108
November110
December54

Download this table (CSV)

How long an electrical permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 296 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 2025415
Finished71.3%
Usual days, issue to final29
Middle half, days14–83

Download this table (CSV)

What an electrical permit is declared at

The value written on the permit at application, from 310 permits with one. Not a quote and not the final bill.

MeasureValue
Usual declared value$3,500
Middle half$1,800–$6,000

Download this table (CSV)

ZIP codes with the most electrical permits

Counted at the property's ZIP code. Share is the part of the city's 907 electrical permits.

ZIP codePermitsShare
9288239644%
9287922425%
9288113715%
92880799%
92883516%

Download this table (CSV)

The city's own permit types

How the city filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
Electrical Residential81990%
Electrical Commercial8810%

Download this table (CSV)

How Corona compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

Nearby permit data

Electrical permits for other places in Los Angeles and the Inland Empire. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: CorStat (City of Corona open data), Building Permits dataset 2agx-camz, read 23 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Building, electrical, plumbing, mechanical, solar, re-roof, fence, pool and fire-sprinkler permits the City of Corona Building Division issues inside city limits. Unincorporated neighbors such as Temescal Valley, El Cerrito, Home Gardens and Coronita get their permits from Riverside County and are not in this file (they are on the Riverside County pages). Public-works encroachment and utility permits and planning or fire-prevention reviews are not counted.

  • The city's permit file names no contractor, so there are no contractor lists, rankings or firm pages for Corona.
  • The job value is filled on about half of permits: almost always on re-roofs, fences, home additions, ADUs, new homes and commercial work, but most electrical, solar, HVAC and plumbing permits carry $0, which we treat as no value.
  • Solar counts both the city's standard solar permits and those issued through its automated online solar review (listed in the file as Symbium Solar); many include battery storage.
  • A final date is the city's finaled date. A permit marked with a certificate of occupancy counts as finished. Water-heater replacements count as plumbing; fire sprinklers, alarms and signs count as other.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Electrical permits in Corona, CA", https://contractorrecords.com/corona/electrical-permits, data through September 2026, from City of Corona Building Division building-permit records.

Link to a table: By month · Season · Days to final · Declared value · By ZIP code · Permit types.

Download the tables (CSV): Electrical permits by month · Electrical permits by calendar month (index) · Electrical permits: days to final · Electrical permits: declared value · Electrical permits by ZIP code · Electrical permits by permit type.

Common questions

  • How many electrical permits does Corona issue a year?About 454 a year in Corona: 907 permits issued October 2024 through September 2026, 492 of them in the last 12 months.
  • How long does an electrical permit take in Corona?The usual one took 29 days from issue to the city's final inspection, and the middle half took 14 to 83 days (296 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Corona file the most electrical permits?September (123 against an average month of 100); December is the quietest (54). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.
  • Which ZIP code has the most electrical permits in Corona?92882, with 396 of the 907 (44%); then 92879 (224).