HVAC permits in Corona, CA

Data through September 2026 · updated 23 Oct 2026

700 HVAC permits were issued in Corona, October 2024 through September 2026: about 350 a year and 9% of all permits. 338 HVAC permits in the last 12 months (Oct 2025–Sep 2026), 7% fewer than the 362 in the 12 months before. The busiest month is August. The usual one took 45 days from issue to the city's final. 92882 has the most, 286.

700permits issued
338last 12 months
Augbusiest month
45days, usual issue to final
71%finished
$13,000usual declared value
Sep 2026records through

HVAC permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 28Oct2024Nov 2024: 27Dec 2024: 21Jan 2025: 24Jan2025Feb 2025: 17Mar 2025: 25Apr 2025: 31May 2025: 38Jun 2025: 36Jul 2025: 43JulAug 2025: 34Sep 2025: 38Oct 2025: 24Nov 2025: 23Dec 2025: 17Jan 2026: 24Jan2026Feb 2026: 21Mar 2026: 35Apr 2026: 24May 2026: 23Jun 2026: 35Jul 2026: 31JulAug 2026: 48Sep 2026: 33
The same numbers as a table
MonthPermits
Oct 202428
Nov 202427
Dec 202421
Jan 202524
Feb 202517
Mar 202525
Apr 202531
May 202538
Jun 202536
Jul 202543
Aug 202534
Sep 202538
Oct 202524
Nov 202523
Dec 202517
Jan 202624
Feb 202621
Mar 202635
Apr 202624
May 202623
Jun 202635
Jul 202631
Aug 202648
Sep 202633

Download this table (CSV)

When HVAC permits are filed

By calendar month, 100 = an average month (the thin line). August is the busiest (141), February the quietest (65). A busy month at the permit counter usually means a longer wait for a contractor.

January: 82 (100 = an average month)February: 65 (100 = an average month)March: 103 (100 = an average month)April: 94 (100 = an average month)May: 105 (100 = an average month)June: 122 (100 = an average month)July: 127 (100 = an average month)August: 141 (100 = an average month)141September: 122 (100 = an average month)October: 89 (100 = an average month)November: 86 (100 = an average month)December: 65 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January82
February65
March103
April94
May105
June122
July127
August141
September122
October89
November86
December65

Download this table (CSV)

How long an HVAC permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 253 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 2025362
Finished71.0%
Usual days, issue to final45
Middle half, days27–78

Download this table (CSV)

What an HVAC permit is declared at

The value written on the permit at application, from 122 permits with one. Not a quote and not the final bill.

MeasureValue
Usual declared value$13,000
Middle half$7,000–$25,000

Download this table (CSV)

ZIP codes with the most HVAC permits

Counted at the property's ZIP code. Share is the part of the city's 700 HVAC permits.

ZIP codePermitsShare
9288228641%
9287916223%
9288115222%
92880548%
92883396%
928782under 1%
928601under 1%

Download this table (CSV)

The city's own permit types

How the city filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
Mechanical Residential66895%
Mechanical - Commercial325%

Download this table (CSV)

How Corona compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

Nearby permit data

HVAC permits for other places in Los Angeles and the Inland Empire. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: CorStat (City of Corona open data), Building Permits dataset 2agx-camz, read 23 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Building, electrical, plumbing, mechanical, solar, re-roof, fence, pool and fire-sprinkler permits the City of Corona Building Division issues inside city limits. Unincorporated neighbors such as Temescal Valley, El Cerrito, Home Gardens and Coronita get their permits from Riverside County and are not in this file (they are on the Riverside County pages). Public-works encroachment and utility permits and planning or fire-prevention reviews are not counted.

  • The city's permit file names no contractor, so there are no contractor lists, rankings or firm pages for Corona.
  • The job value is filled on about half of permits: almost always on re-roofs, fences, home additions, ADUs, new homes and commercial work, but most electrical, solar, HVAC and plumbing permits carry $0, which we treat as no value.
  • Solar counts both the city's standard solar permits and those issued through its automated online solar review (listed in the file as Symbium Solar); many include battery storage.
  • A final date is the city's finaled date. A permit marked with a certificate of occupancy counts as finished. Water-heater replacements count as plumbing; fire sprinklers, alarms and signs count as other.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "HVAC permits in Corona, CA", https://contractorrecords.com/corona/hvac-permits, data through September 2026, from City of Corona Building Division building-permit records.

Link to a table: By month · Season · Days to final · Declared value · By ZIP code · Permit types.

Download the tables (CSV): HVAC permits by month · HVAC permits by calendar month (index) · HVAC permits: days to final · HVAC permits: declared value · HVAC permits by ZIP code · HVAC permits by permit type.

Common questions

  • How many HVAC permits does Corona issue a year?About 350 a year in Corona: 700 permits issued October 2024 through September 2026, 338 of them in the last 12 months.
  • How long does an HVAC permit take in Corona?The usual one took 45 days from issue to the city's final inspection, and the middle half took 27 to 78 days (253 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Corona file the most HVAC permits?August (141 against an average month of 100); February is the quietest (65). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.
  • Which ZIP code has the most HVAC permits in Corona?92882, with 286 of the 700 (41%); then 92879 (162).