Electrical permits in unincorporated Riverside County, CA

Data through September 2026 · updated 23 Oct 2026

4,935 electrical permits were issued in unincorporated Riverside County, October 2024 through September 2026: about 2,468 a year and 18% of all permits. 2,419 electrical permits in the last 12 months (Oct 2025–Sep 2026), 4% fewer than the 2,516 in the 12 months before. The busiest month is April. The usual one took 56 days from issue to the county's final.

4,935permits issued
2,419last 12 months
Aprbusiest month
56days, usual issue to final
84%finished
Sep 2026records through

Electrical permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 196Oct2024Nov 2024: 142Dec 2024: 164Jan 2025: 164Jan2025Feb 2025: 152Mar 2025: 238Apr 2025: 277May 2025: 247Jun 2025: 226Jul 2025: 217JulAug 2025: 235Sep 2025: 258Oct 2025: 216Nov 2025: 186Dec 2025: 222Jan 2026: 150Jan2026Feb 2026: 202Mar 2026: 244Apr 2026: 227May 2026: 177Jun 2026: 209Jul 2026: 180JulAug 2026: 226Sep 2026: 180
The same numbers as a table
MonthPermits
Oct 2024196
Nov 2024142
Dec 2024164
Jan 2025164
Feb 2025152
Mar 2025238
Apr 2025277
May 2025247
Jun 2025226
Jul 2025217
Aug 2025235
Sep 2025258
Oct 2025216
Nov 2025186
Dec 2025222
Jan 2026150
Feb 2026202
Mar 2026244
Apr 2026227
May 2026177
Jun 2026209
Jul 2026180
Aug 2026226
Sep 2026180

Download this table (CSV)

When electrical permits are filed

By calendar month, 100 = an average month (the thin line). April is the busiest (123), January the quietest (76). A busy month at the permit counter usually means a longer wait for a contractor.

January: 76 (100 = an average month)February: 86 (100 = an average month)March: 117 (100 = an average month)April: 123 (100 = an average month)123May: 103 (100 = an average month)June: 106 (100 = an average month)July: 97 (100 = an average month)August: 112 (100 = an average month)September: 107 (100 = an average month)October: 100 (100 = an average month)November: 80 (100 = an average month)December: 94 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January76
February86
March117
April123
May103
June106
July97
August112
September107
October100
November80
December94

Download this table (CSV)

How long an electrical permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 2,108 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 20252,516
Finished83.8%
Expired13.4%
Usual days, issue to final56
Middle half, days17–121

Download this table (CSV)

The county's own permit types

How the county filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
Other Construction1,78336%
Service Upgrade-Residential1,14123%
Residential Electric79316%
Commercial Electric4198%
Energy Storage System3978%
Meter Reset To Residential2846%
Temporary Power731%
Electric To Well43under 1%
Bbq Portable1under 1%
Light Standard1under 1%

Download this table (CSV)

How Riverside County compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

Nearby permit data

Electrical permits for other places in Los Angeles and the Inland Empire. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: Riverside County GIS Open Data, PLUS_ACTIVITIES (Public Land Use System), Building department records, read 23 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Permits Riverside County Building and Safety issues for unincorporated land only: places such as Thermal, Mecca, Winchester, French Valley, Mead Valley, Anza, Aguanga, Temescal Valley and the Temecula wine country. Riverside, Moreno Valley, Corona, Temecula, Murrieta, Palm Springs and the county's other incorporated cities (28 in all) run their own permit offices and are not in this file. Blythe permits, which the county keeps under their own permit type, are left out too.

  • The county's file names no contractor, so there are no contractor lists, rankings or firm pages for Riverside County.
  • The file has no declared job value, so we show no costs.
  • The file gives a parcel number but no ZIP code, so there are no ZIP code pages.
  • Tract builders file one permit per house, so a new subdivision shows as many new-home permits, often with a matching repeat-production wall permit for each lot.
  • Battery storage permits are counted as electrical; rooftop and ground-mount solar as solar.
  • A final date is the county's completed date on a permit marked Final. Administratively closed permits count as expired.
  • Grading, hourly inspection, agricultural fee-only and legacy converted records are left out.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Electrical permits in unincorporated Riverside County, CA", https://contractorrecords.com/riverside-county/electrical-permits, data through September 2026, from Riverside County Building and Safety building-permit records.

Link to a table: By month · Season · Days to final · Permit types.

Download the tables (CSV): Electrical permits by month · Electrical permits by calendar month (index) · Electrical permits: days to final · Electrical permits by permit type.

Common questions

  • How many electrical permits does Riverside County issue a year?About 2,468 a year in unincorporated Riverside County: 4,935 permits issued October 2024 through September 2026, 2,419 of them in the last 12 months.
  • How long does an electrical permit take in Riverside County?The usual one took 56 days from issue to the county's final inspection, and the middle half took 17 to 121 days (2,108 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Riverside County file the most electrical permits?April (123 against an average month of 100); January is the quietest (76). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.