Roofing permits in Corona, CA

Data through September 2026 · updated 23 Oct 2026

686 roofing permits were issued in Corona, October 2024 through September 2026: about 343 a year and 9% of all permits. 386 roofing permits in the last 12 months (Oct 2025–Sep 2026), 29% more than the 300 in the 12 months before. The busiest month is October. The usual one took 15 days from issue to the city's final. 92882 has the most, 301.

686permits issued
386last 12 months
Octbusiest month
15days, usual issue to final
88%finished
$14,000usual declared value
Sep 2026records through

Roofing permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 48Oct2024Nov 2024: 36Dec 2024: 19Jan 2025: 23Jan2025Feb 2025: 17Mar 2025: 20Apr 2025: 23May 2025: 25Jun 2025: 35Jul 2025: 20JulAug 2025: 18Sep 2025: 16Oct 2025: 57Nov 2025: 48Dec 2025: 20Jan 2026: 53Jan2026Feb 2026: 17Mar 2026: 39Apr 2026: 23May 2026: 21Jun 2026: 26Jul 2026: 31JulAug 2026: 30Sep 2026: 21
The same numbers as a table
MonthPermits
Oct 202448
Nov 202436
Dec 202419
Jan 202523
Feb 202517
Mar 202520
Apr 202523
May 202525
Jun 202535
Jul 202520
Aug 202518
Sep 202516
Oct 202557
Nov 202548
Dec 202520
Jan 202653
Feb 202617
Mar 202639
Apr 202623
May 202621
Jun 202626
Jul 202631
Aug 202630
Sep 202621

Download this table (CSV)

When roofing permits are filed

By calendar month, 100 = an average month (the thin line). October is the busiest (184), February the quietest (59). A busy month at the permit counter usually means a longer wait for a contractor.

January: 133 (100 = an average month)February: 59 (100 = an average month)March: 103 (100 = an average month)April: 80 (100 = an average month)May: 80 (100 = an average month)June: 107 (100 = an average month)July: 89 (100 = an average month)August: 84 (100 = an average month)September: 65 (100 = an average month)October: 184 (100 = an average month)184November: 147 (100 = an average month)December: 68 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January133
February59
March103
April80
May80
June107
July89
August84
September65
October184
November147
December68

Download this table (CSV)

How long a roofing permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 264 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 2025300
Finished88.3%
Usual days, issue to final15
Middle half, days9–29

Download this table (CSV)

What a roofing permit is declared at

The value written on the permit at application, from 659 permits with one. Not a quote and not the final bill.

MeasureValue
Usual declared value$14,000
Middle half$9,200–$20,000

Download this table (CSV)

ZIP codes with the most roofing permits

Counted at the property's ZIP code. Share is the part of the city's 686 roofing permits.

ZIP codePermitsShare
9288230144%
9287926238%
92880649%
92881568%
928831under 1%

Download this table (CSV)

How Corona compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

Nearby permit data

Roofing permits for other places in Los Angeles and the Inland Empire. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: CorStat (City of Corona open data), Building Permits dataset 2agx-camz, read 23 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Building, electrical, plumbing, mechanical, solar, re-roof, fence, pool and fire-sprinkler permits the City of Corona Building Division issues inside city limits. Unincorporated neighbors such as Temescal Valley, El Cerrito, Home Gardens and Coronita get their permits from Riverside County and are not in this file (they are on the Riverside County pages). Public-works encroachment and utility permits and planning or fire-prevention reviews are not counted.

  • The city's permit file names no contractor, so there are no contractor lists, rankings or firm pages for Corona.
  • The job value is filled on about half of permits: almost always on re-roofs, fences, home additions, ADUs, new homes and commercial work, but most electrical, solar, HVAC and plumbing permits carry $0, which we treat as no value.
  • Solar counts both the city's standard solar permits and those issued through its automated online solar review (listed in the file as Symbium Solar); many include battery storage.
  • A final date is the city's finaled date. A permit marked with a certificate of occupancy counts as finished. Water-heater replacements count as plumbing; fire sprinklers, alarms and signs count as other.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Roofing permits in Corona, CA", https://contractorrecords.com/corona/roofing-permits, data through September 2026, from City of Corona Building Division building-permit records.

Link to a table: By month · Season · Days to final · Declared value · By ZIP code.

Download the tables (CSV): Roofing permits by month · Roofing permits by calendar month (index) · Roofing permits: days to final · Roofing permits: declared value · Roofing permits by ZIP code.

Common questions

  • How many roofing permits does Corona issue a year?About 343 a year in Corona: 686 permits issued October 2024 through September 2026, 386 of them in the last 12 months.
  • How long does a roofing permit take in Corona?The usual one took 15 days from issue to the city's final inspection, and the middle half took 9 to 29 days (264 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Corona file the most roofing permits?October (184 against an average month of 100); February is the quietest (59). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.
  • Which ZIP code has the most roofing permits in Corona?92882, with 301 of the 686 (44%); then 92879 (262).