Solar permits in unincorporated Riverside County, CA

Data through September 2026 · updated 23 Oct 2026

4,242 solar permits were issued in unincorporated Riverside County, October 2024 through September 2026: about 2,121 a year and 16% of all permits. 1,942 solar permits in the last 12 months (Oct 2025–Sep 2026), 16% fewer than the 2,300 in the 12 months before. The busiest month is October. The usual one took 100 days from issue to the county's final.

4,242permits issued
1,942last 12 months
Octbusiest month
100days, usual issue to final
76%finished
Sep 2026records through

Solar permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 188Oct2024Nov 2024: 158Dec 2024: 175Jan 2025: 176Jan2025Feb 2025: 137Mar 2025: 209Apr 2025: 241May 2025: 224Jun 2025: 150Jul 2025: 218JulAug 2025: 202Sep 2025: 222Oct 2025: 245Nov 2025: 211Dec 2025: 240Jan 2026: 139Jan2026Feb 2026: 141Mar 2026: 153Apr 2026: 129May 2026: 134Jun 2026: 149Jul 2026: 112JulAug 2026: 148Sep 2026: 141
The same numbers as a table
MonthPermits
Oct 2024188
Nov 2024158
Dec 2024175
Jan 2025176
Feb 2025137
Mar 2025209
Apr 2025241
May 2025224
Jun 2025150
Jul 2025218
Aug 2025202
Sep 2025222
Oct 2025245
Nov 2025211
Dec 2025240
Jan 2026139
Feb 2026141
Mar 2026153
Apr 2026129
May 2026134
Jun 2026149
Jul 2026112
Aug 2026148
Sep 2026141

Download this table (CSV)

When solar permits are filed

By calendar month, 100 = an average month (the thin line). October is the busiest (122), February the quietest (79). A busy month at the permit counter usually means a longer wait for a contractor.

January: 89 (100 = an average month)February: 79 (100 = an average month)March: 102 (100 = an average month)April: 105 (100 = an average month)May: 101 (100 = an average month)June: 85 (100 = an average month)July: 93 (100 = an average month)August: 99 (100 = an average month)September: 103 (100 = an average month)October: 122 (100 = an average month)122November: 104 (100 = an average month)December: 117 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January89
February79
March102
April105
May101
June85
July93
August99
September103
October122
November104
December117

Download this table (CSV)

How long a solar permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 1,755 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 20252,300
Finished76.3%
Expired22.8%
Usual days, issue to final100
Middle half, days55–168

Download this table (CSV)

The county's own permit types

How the county filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
Roof Mount Solar Residential1,89745%
Express Residential Solar And Storage1,85944%
Express Residential Solar Only2075%
Other Construction1383%
Ground Mount Solar Residential1193%
Energy Storage System15under 1%
Light Standard4under 1%
Solar Commercial3under 1%

Download this table (CSV)

How Riverside County compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

Nearby permit data

Solar permits for other places in Los Angeles and the Inland Empire. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: Riverside County GIS Open Data, PLUS_ACTIVITIES (Public Land Use System), Building department records, read 23 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Permits Riverside County Building and Safety issues for unincorporated land only: places such as Thermal, Mecca, Winchester, French Valley, Mead Valley, Anza, Aguanga, Temescal Valley and the Temecula wine country. Riverside, Moreno Valley, Corona, Temecula, Murrieta, Palm Springs and the county's other incorporated cities (28 in all) run their own permit offices and are not in this file. Blythe permits, which the county keeps under their own permit type, are left out too.

  • The county's file names no contractor, so there are no contractor lists, rankings or firm pages for Riverside County.
  • The file has no declared job value, so we show no costs.
  • The file gives a parcel number but no ZIP code, so there are no ZIP code pages.
  • Tract builders file one permit per house, so a new subdivision shows as many new-home permits, often with a matching repeat-production wall permit for each lot.
  • Battery storage permits are counted as electrical; rooftop and ground-mount solar as solar.
  • A final date is the county's completed date on a permit marked Final. Administratively closed permits count as expired.
  • Grading, hourly inspection, agricultural fee-only and legacy converted records are left out.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Solar permits in unincorporated Riverside County, CA", https://contractorrecords.com/riverside-county/solar-permits, data through September 2026, from Riverside County Building and Safety building-permit records.

Link to a table: By month · Season · Days to final · Permit types.

Download the tables (CSV): Solar permits by month · Solar permits by calendar month (index) · Solar permits: days to final · Solar permits by permit type.

Common questions

  • How many solar permits does Riverside County issue a year?About 2,121 a year in unincorporated Riverside County: 4,242 permits issued October 2024 through September 2026, 1,942 of them in the last 12 months.
  • How long does a solar permit take in Riverside County?The usual one took 100 days from issue to the county's final inspection, and the middle half took 55 to 168 days (1,755 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Riverside County file the most solar permits?October (122 against an average month of 100); February is the quietest (79). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.