Remodel and repair permits in the City of Centennial, CO

Data through September 2026 · updated 20 Oct 2026

3,071 remodel and repair permits were issued in the City of Centennial, October 2024 through September 2026: about 1,536 a year and 23% of all permits. 1,529 remodel and repair permits in the last 12 months (Oct 2025–Sep 2026), about the same as the 1,542 in the 12 months before. The busiest month is June. The usual one took 59 days from issue to the city's final. 80122 has the most, 990.

3,071permits issued
1,529last 12 months
Junbusiest month
59days, usual issue to final
85%finished
$10,000usual declared value
Sep 2026records through

Remodel and repair permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 135Oct2024Nov 2024: 115Dec 2024: 103Jan 2025: 116Jan2025Feb 2025: 104Mar 2025: 118Apr 2025: 135May 2025: 137Jun 2025: 131Jul 2025: 144JulAug 2025: 151Sep 2025: 153Oct 2025: 139Nov 2025: 112Dec 2025: 104Jan 2026: 113Jan2026Feb 2026: 116Mar 2026: 108Apr 2026: 130May 2026: 107Jun 2026: 176Jul 2026: 131JulAug 2026: 141Sep 2026: 152
The same numbers as a table
MonthPermits
Oct 2024135
Nov 2024115
Dec 2024103
Jan 2025116
Feb 2025104
Mar 2025118
Apr 2025135
May 2025137
Jun 2025131
Jul 2025144
Aug 2025151
Sep 2025153
Oct 2025139
Nov 2025112
Dec 2025104
Jan 2026113
Feb 2026116
Mar 2026108
Apr 2026130
May 2026107
Jun 2026176
Jul 2026131
Aug 2026141
Sep 2026152

Download this table (CSV)

When remodel and repair permits are filed

By calendar month, 100 = an average month (the thin line). June is the busiest (120), December the quietest (81). A busy month at the permit counter usually means a longer wait for a contractor.

January: 89 (100 = an average month)February: 86 (100 = an average month)March: 88 (100 = an average month)April: 104 (100 = an average month)May: 95 (100 = an average month)June: 120 (100 = an average month)120July: 107 (100 = an average month)August: 114 (100 = an average month)September: 119 (100 = an average month)October: 107 (100 = an average month)November: 89 (100 = an average month)December: 81 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January89
February86
March88
April104
May95
June120
July107
August114
September119
October107
November89
December81

Download this table (CSV)

How long a remodel and repair permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 1,304 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 20251,542
Finished84.8%
Expired13.8%
Usual days, issue to final59
Middle half, days29–118

Download this table (CSV)

What a remodel and repair permit is declared at

The value written on the permit at application, from 3,071 permits with one. Not a quote and not the final bill.

MeasureValue
Usual declared value$10,000
Middle half$4,500–$21,361

Download this table (CSV)

ZIP codes with the most remodel and repair permits

Counted at the property's ZIP code. Share is the part of the city's 3,071 remodel and repair permits.

ZIP codePermitsShare
8012299032%
8001563821%
8011259619%
8012140413%
800162528%
801111916%

Download this table (CSV)

The city's own permit types

How the city filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
Windows/Doors1,46848%
Misc83927%
Alterations50917%
Windows/Doors (No Structural Changes)1234%
Basement Finish1063%
Windows/Doors (Includes Structural Changes)25under 1%
Irrigation Line1under 1%

Download this table (CSV)

How Centennial compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

Nearby permit data

Remodel and repair permits for other places in Denver and Boulder. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: City of Centennial ArcGIS Server, EPL_Permit (EnerGov permit table), read 20 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Building, trade, fence and sign permits the City of Centennial issues inside the city limits only. Homes with a Centennial mailing address in unincorporated Arapahoe County, and the neighbouring cities of Greenwood Village, Littleton, Englewood, Lone Tree and Aurora, get their permits elsewhere and are not in this file.

  • The city's file names no contractor, so there are no contractor lists, rankings or firm pages for Centennial.
  • The value is the valuation declared on the permit, which sets the fee. Many over-the-counter home permits list none or a nominal figure, so values are a guide, not a cost.
  • Hailstorms drive roofing: a storm season can double a month's permits, so roofing counts swing from year to year.
  • The city's broad 'Misc' class (EV circuits, sewer repairs, furnace swaps, siding) is sorted into trades from the short work description; anything left is a remodel or repair.
  • Homes are permits the city files as residential. Multi-family buildings and commercial work count as other.
  • A final date is the date the permit was finaled. Right-of-way, temporary use and development permits are left out.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Remodel and repair permits in the City of Centennial, CO", https://contractorrecords.com/centennial/remodel-permits, data through September 2026, from the City of Centennial Building Services building-permit records.

Link to a table: By month · Season · Days to final · Declared value · By ZIP code · Permit types.

Download the tables (CSV): Remodels & repairs permits by month · Remodels & repairs permits by calendar month (index) · Remodels & repairs permits: days to final · Remodels & repairs permits: declared value · Remodels & repairs permits by ZIP code · Remodels & repairs permits by permit type.

Common questions

  • How many remodel and repair permits does Centennial issue a year?About 1,536 a year in the City of Centennial: 3,071 permits issued October 2024 through September 2026, 1,529 of them in the last 12 months.
  • How long does a remodel and repair permit take in Centennial?The usual one took 59 days from issue to the city's final inspection, and the middle half took 29 to 118 days (1,304 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Centennial file the most remodel and repair permits?June (120 against an average month of 100); December is the quietest (81). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.
  • Which ZIP code has the most remodel and repair permits in Centennial?80122, with 990 of the 3,071 (32%); then 80015 (638).