How long do permits take in the City of Centennial, CO?

Data through September 2026 · updated 20 Oct 2026

The usual permit in the City of Centennial takes 36 days from issue to the city's final inspection; the middle half take 13 to 97 days. That is from 5,853 permits issued Oct 2024–Sep 2025 that reached a final. Fence and wall permits are quickest at 0 days; new home permits take longest at 224 days. This is the time to finish the work and close the permit, not the wait for approval.

36days, usual issue to final
13–97days, middle half
83%finished
5,853permits with a final date
Sep 2026records through

Getting the permit vs finishing the work: two different clocks

“How long does a permit take?” can mean two waits. This page measures the second one.

Getting the permit (not measured): application → issue, the wait for the city to approve the plans. Ask the city for its current review times.

Finishing the work (measured here): issue → final. From the day the city issued the permit to the day it recorded the final inspection. We count only permits issued Oct 2024–Sep 2025, at least 12 months before the file ends, so slow jobs have had time to finish; a permit still open is not in the days.

By kind of work

Permits issued Oct 2024–Sep 2025. Usual days is the middle permit among those with a final date: half finished sooner, half later. Middle half is the range the middle 50% fell in. Kinds of work with fewer than 100 permits in that period are left out.

Kind of workPermitsFinishedExpiredUsual days to finalMiddle half (days)
Remodels & repairs1,54284.8%13.8%5929–118
Roofing1,67288.0%11.7%3719–91
Plumbing1,07077.8%22.0%83–29
HVAC91272.5%27.2%2110–48
Electrical65878.4%20.7%187–47
Solar27491.6%7.7%6236–106
New homes18189.5%5.5%224202–256
Fences & walls13093.8%5.4%00–0
Garages, sheds & shade structures10291.2%3.9%6440–130
Other51380.9%13.8%10532–224

Download this table (CSV)

How long each kind of permit takes

Each kind of work on its own, issue to the city's final.

How long does a remodel take in Centennial, from permit to final?

The usual remodel and repair permit in the City of Centennial takes 59 days from issue to final; the middle half take 29 to 118 days (1,304 permits with a final date, issued Oct 2024–Sep 2025). 85% of the 1,542 permits issued then have finished and 14% expired. Centennial remodel and repair permits →

How long does a roof replacement take in Centennial, from permit to final?

The usual roofing permit in the City of Centennial takes 37 days from issue to final; the middle half take 19 to 91 days (1,470 permits with a final date, issued Oct 2024–Sep 2025). 88% of the 1,672 permits issued then have finished and 12% expired. Centennial roofing permits →

How long does plumbing work take in Centennial, from permit to final?

The usual plumbing permit in the City of Centennial takes 8 days from issue to final; the middle half take 3 to 29 days (832 permits with a final date, issued Oct 2024–Sep 2025). 78% of the 1,070 permits issued then have finished and 22% expired. Centennial plumbing permits →

How long does an HVAC replacement take in Centennial, from permit to final?

The usual HVAC permit in the City of Centennial takes 21 days from issue to final; the middle half take 10 to 48 days (660 permits with a final date, issued Oct 2024–Sep 2025). 72% of the 912 permits issued then have finished and 27% expired. Centennial HVAC permits →

How long does electrical work take in Centennial, from permit to final?

The usual electrical permit in the City of Centennial takes 18 days from issue to final; the middle half take 7 to 47 days (514 permits with a final date, issued Oct 2024–Sep 2025). 78% of the 658 permits issued then have finished and 21% expired. Centennial electrical permits →

How long does a solar installation take in Centennial, from permit to final?

The usual solar permit in the City of Centennial takes 62 days from issue to final; the middle half take 36 to 106 days (251 permits with a final date, issued Oct 2024–Sep 2025). 92% of the 274 permits issued then have finished and 8% expired. Centennial solar permits →

How long does building a new home take in Centennial, from permit to final?

The usual new home permit in the City of Centennial takes 224 days from issue to final; the middle half take 202 to 256 days (162 permits with a final date, issued Oct 2024–Sep 2025). 90% of the 181 permits issued then have finished and 6% expired. Centennial new home permits →

How long does a fence or wall take in Centennial, from permit to final?

The usual fence and wall permit in the City of Centennial takes 0 days from issue to final; the middle half take 0 to 0 days (122 permits with a final date, issued Oct 2024–Sep 2025). 94% of the 130 permits issued then have finished and 5% expired. Centennial fence and wall permits →

How long does a garage, shed or patio cover take in Centennial, from permit to final?

The usual garage, shed and shade structure permit in the City of Centennial takes 64 days from issue to final; the middle half take 40 to 130 days (93 permits with a final date, issued Oct 2024–Sep 2025). 91% of the 102 permits issued then have finished and 4% expired. Centennial garage, shed and shade structure permits →

How Centennial compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

Nearby permit data

How long permits take for other places in Denver and Boulder. Each permit office keeps its own file, so the numbers are not added together.

How these numbers are made

Source: City of Centennial ArcGIS Server, EPL_Permit (EnerGov permit table), read 20 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Building, trade, fence and sign permits the City of Centennial issues inside the city limits only. Homes with a Centennial mailing address in unincorporated Arapahoe County, and the neighbouring cities of Greenwood Village, Littleton, Englewood, Lone Tree and Aurora, get their permits elsewhere and are not in this file.

  • The city's file names no contractor, so there are no contractor lists, rankings or firm pages for Centennial.
  • The value is the valuation declared on the permit, which sets the fee. Many over-the-counter home permits list none or a nominal figure, so values are a guide, not a cost.
  • Hailstorms drive roofing: a storm season can double a month's permits, so roofing counts swing from year to year.
  • The city's broad 'Misc' class (EV circuits, sewer repairs, furnace swaps, siding) is sorted into trades from the short work description; anything left is a remodel or repair.
  • Homes are permits the city files as residential. Multi-family buildings and commercial work count as other.
  • A final date is the date the permit was finaled. Right-of-way, temporary use and development permits are left out.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "How long do permits take in the City of Centennial, CO?", https://contractorrecords.com/centennial/how-long-does-a-permit-take, data through September 2026, from the City of Centennial Building Services building-permit records.

Link to a table: By kind of work · Each kind of permit.

Download the tables (CSV): Days to final by kind of work.

Common questions

  • What is the permit turnaround in Centennial?From issue to final inspection, the usual permit takes 36 days (middle half 13 to 97 days), from 5,853 permits issued Oct 2024–Sep 2025. The wait to get a permit issued is not in this file; ask the city for its current review times.
  • Which permits finish fastest in Centennial?Fence and wall permits, at 0 days. The slowest are new home permits, at 224 days. Bigger jobs take longer; so does work where the final inspection is easy to forget.
  • How many permits actually get finished in Centennial?83% of the 7,105 permits issued Oct 2024–Sep 2025 have finished; 16% expired without a final and the rest are still open.
  • Why does an open permit matter to me?An unfinished permit stays with the property, not the contractor. It can hold up a sale or a refinance. Ask whoever does the work to call for the final inspection and show you the result.