Home addition permits in New Orleans, LA

Data through September 2026 · updated 18 Oct 2026

304 home addition permits were issued in New Orleans, October 2024 through September 2026: about 152 a year and 1% of all permits. 157 home addition permits in the last 12 months (Oct 2025–Sep 2026), 7% more than the 147 in the 12 months before. The busiest month is May. The usual one took 286 days from issue to the city's final. 70115 has the most, 75.

304permits issued
157last 12 months
Maybusiest month
286days, usual issue to final
48%finished
$150,000usual declared value
Sep 2026records through

Home addition permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 7Oct2024Nov 2024: 10Dec 2024: 11Jan 2025: 14Jan2025Feb 2025: 12Mar 2025: 10Apr 2025: 10May 2025: 21Jun 2025: 13Jul 2025: 16JulAug 2025: 12Sep 2025: 11Oct 2025: 18Nov 2025: 13Dec 2025: 12Jan 2026: 10Jan2026Feb 2026: 12Mar 2026: 16Apr 2026: 17May 2026: 16Jun 2026: 10Jul 2026: 11JulAug 2026: 8Sep 2026: 14
The same numbers as a table
MonthPermits
Oct 20247
Nov 202410
Dec 202411
Jan 202514
Feb 202512
Mar 202510
Apr 202510
May 202521
Jun 202513
Jul 202516
Aug 202512
Sep 202511
Oct 202518
Nov 202513
Dec 202512
Jan 202610
Feb 202612
Mar 202616
Apr 202617
May 202616
Jun 202610
Jul 202611
Aug 20268
Sep 202614

Download this table (CSV)

When home addition permits are filed

By calendar month, 100 = an average month (the thin line). May is the busiest (146), August the quietest (79). A busy month at the permit counter usually means a longer wait for a contractor.

January: 95 (100 = an average month)February: 95 (100 = an average month)March: 103 (100 = an average month)April: 107 (100 = an average month)May: 146 (100 = an average month)146June: 91 (100 = an average month)July: 107 (100 = an average month)August: 79 (100 = an average month)September: 99 (100 = an average month)October: 99 (100 = an average month)November: 91 (100 = an average month)December: 91 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January95
February95
March103
April107
May146
June91
July107
August79
September99
October99
November91
December91

Download this table (CSV)

How long a home addition permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 68 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 2025147
Finished48.3%
Expired0.0%
Usual days, issue to final286
Middle half, days230–363

Download this table (CSV)

What a home addition permit is declared at

The value written on the permit at application, from 302 permits with one. Not a quote and not the final bill.

MeasureValue
Usual declared value$150,000
Middle half$75,000–$311,350

Download this table (CSV)

ZIP codes with the most home addition permits

Counted at the property's ZIP code. Share is the part of the city's 304 home addition permits.

ZIP codePermitsShare
701157525%
701185518%
70119227%
70124196%
70130155%
70122155%
70117145%
70116114%
7011483%
7012562%

Download this table (CSV)

The city's own permit types

How the city filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
Renovation (Structural)28694%
Renovation (Non-Structural)134%
Renovation (Structural or Non-structural)52%

Download this table (CSV)

How these numbers are made

Source: City of New Orleans, Permits - BLDS (data.nola.gov, dataset 72f9-bi28), read 18 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Residential permits the City of New Orleans Department of Safety and Permits issues inside the city, which is also Orleans Parish: building, renovation, re-roofing, electrical, plumbing, gas, HVAC, solar, pool, generator and demolition permits for single-family homes, two-family homes and doubles. Permits for buildings with three or more units and commercial property are not counted, nor are historic-district reviews, right-of-way permits (street cuts, driveways, sidewalks) and address changes in the same file. Jefferson, St. Bernard and St. Tammany parishes run their own permit offices and are not in this file.

  • The city's file lists a contractor on most permits, usually the licensed person rather than the company, but these pages show permit counts only: there are no contractor lists, rankings or firm pages for New Orleans.
  • The value is the project cost declared on the application. About a third of permits carry none, mostly small trade permits.
  • Gas permits (gas lines, water heaters and the six-month gas test after a home sits empty) are counted with plumbing; an electrical vacancy permit, needed to turn power back on in a home that sat empty, counts as electrical.
  • The city's file has a residential re-roofing permit type only from May 2025; before that few re-roofs appear in it, so the rise in roofing permits mostly reflects the new permit type, not more roofs.
  • A final date is the day the city recorded the permit as finaled or completed. Permits the city marks Closed count as finished but add no days, because the file does not say whether the work passed a final inspection.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Home addition permits in New Orleans, LA", https://contractorrecords.com/new-orleans/addition-permits, data through September 2026, from the City of New Orleans Department of Safety and Permits building-permit records.

Link to a table: By month · Season · Days to final · Declared value · By ZIP code · Permit types.

Download the tables (CSV): Additions permits by month · Additions permits by calendar month (index) · Additions permits: days to final · Additions permits: declared value · Additions permits by ZIP code · Additions permits by permit type.

Common questions

  • How many home addition permits does New Orleans issue a year?About 152 a year in New Orleans: 304 permits issued October 2024 through September 2026, 157 of them in the last 12 months.
  • How long does a home addition permit take in New Orleans?The usual one took 286 days from issue to the city's final inspection, and the middle half took 230 to 363 days (68 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in New Orleans file the most home addition permits?May (146 against an average month of 100); August is the quietest (79). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.
  • Which ZIP code has the most home addition permits in New Orleans?70115, with 75 of the 304 (25%); then 70118 (55).