How long do permits take in New Orleans, LA?

Data through September 2026 · updated 18 Oct 2026

The usual permit in New Orleans takes 72 days from issue to the city's final inspection; the middle half take 22 to 176 days. That is from 8,946 permits issued Oct 2024–Sep 2025 that reached a final. Plumbing permits are quickest at 41 days; home addition permits take longest at 286 days. This is the time to finish the work and close the permit, not the wait for approval.

72days, usual issue to final
22–176days, middle half
70%finished
8,946permits with a final date
Sep 2026records through

Getting the permit vs finishing the work: two different clocks

“How long does a permit take?” can mean two waits. This page measures the second one.

Getting the permit (not measured): application → issue, the wait for the city to approve the plans. Ask the city for its current review times.

Finishing the work (measured here): issue → final. From the day the city issued the permit to the day it recorded the final inspection. We count only permits issued Oct 2024–Sep 2025, at least 12 months before the file ends, so slow jobs have had time to finish; a permit still open is not in the days.

By kind of work

Permits issued Oct 2024–Sep 2025. Usual days is the middle permit among those with a final date: half finished sooner, half later. Middle half is the range the middle 50% fell in. Kinds of work with fewer than 100 permits in that period are left out.

Kind of workPermitsFinishedExpiredUsual days to finalMiddle half (days)
Electrical4,91674.2%1.6%4720–130
Plumbing3,64977.8%0.5%418–158
HVAC1,41575.9%0.5%11260–192
Remodels & repairs1,21954.4%0.6%15575–286
Roofing50151.9%0.4%11134–203
Solar88073.3%0.2%6341–115
New homes33278.0%0.0%272199–348
Demolition40820.3%0.7%20386–320
Pools & spas18417.9%0.5%––
Additions14748.3%0.0%286230–363

Download this table (CSV)

How long each kind of permit takes

Each kind of work on its own, issue to the city's final.

How long does electrical work take in New Orleans, from permit to final?

The usual electrical permit in New Orleans takes 47 days from issue to final; the middle half take 20 to 130 days (3,232 permits with a final date, issued Oct 2024–Sep 2025). 74% of the 4,916 permits issued then have finished and 2% expired. New Orleans electrical permits →

How long does plumbing work take in New Orleans, from permit to final?

The usual plumbing permit in New Orleans takes 41 days from issue to final; the middle half take 8 to 158 days (2,713 permits with a final date, issued Oct 2024–Sep 2025). 78% of the 3,649 permits issued then have finished and under 1% expired. New Orleans plumbing permits →

How long does an HVAC replacement take in New Orleans, from permit to final?

The usual HVAC permit in New Orleans takes 112 days from issue to final; the middle half take 60 to 192 days (1,070 permits with a final date, issued Oct 2024–Sep 2025). 76% of the 1,415 permits issued then have finished and under 1% expired. New Orleans HVAC permits →

How long does a remodel take in New Orleans, from permit to final?

The usual remodel and repair permit in New Orleans takes 155 days from issue to final; the middle half take 75 to 286 days (643 permits with a final date, issued Oct 2024–Sep 2025). 54% of the 1,219 permits issued then have finished and under 1% expired. New Orleans remodel and repair permits →

How long does a roof replacement take in New Orleans, from permit to final?

The usual roofing permit in New Orleans takes 111 days from issue to final; the middle half take 34 to 203 days (251 permits with a final date, issued Oct 2024–Sep 2025). 52% of the 501 permits issued then have finished and under 1% expired. New Orleans roofing permits →

How long does a solar installation take in New Orleans, from permit to final?

The usual solar permit in New Orleans takes 63 days from issue to final; the middle half take 41 to 115 days (587 permits with a final date, issued Oct 2024–Sep 2025). 73% of the 880 permits issued then have finished and under 1% expired. New Orleans solar permits →

How long does building a new home take in New Orleans, from permit to final?

The usual new home permit in New Orleans takes 272 days from issue to final; the middle half take 199 to 348 days (257 permits with a final date, issued Oct 2024–Sep 2025). 78% of the 332 permits issued then have finished and 0% expired. New Orleans new home permits →

How long does a demolition take in New Orleans, from permit to final?

The usual demolition permit in New Orleans takes 203 days from issue to final; the middle half take 86 to 320 days (78 permits with a final date, issued Oct 2024–Sep 2025). 20% of the 408 permits issued then have finished and under 1% expired. New Orleans demolition permits →

How long does a home addition take in New Orleans, from permit to final?

The usual home addition permit in New Orleans takes 286 days from issue to final; the middle half take 230 to 363 days (68 permits with a final date, issued Oct 2024–Sep 2025). 48% of the 147 permits issued then have finished and 0% expired. New Orleans home addition permits →

How New Orleans compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

How these numbers are made

Source: City of New Orleans, Permits - BLDS (data.nola.gov, dataset 72f9-bi28), read 18 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Residential permits the City of New Orleans Department of Safety and Permits issues inside the city, which is also Orleans Parish: building, renovation, re-roofing, electrical, plumbing, gas, HVAC, solar, pool, generator and demolition permits for single-family homes, two-family homes and doubles. Permits for buildings with three or more units and commercial property are not counted, nor are historic-district reviews, right-of-way permits (street cuts, driveways, sidewalks) and address changes in the same file. Jefferson, St. Bernard and St. Tammany parishes run their own permit offices and are not in this file.

  • The city's file lists a contractor on most permits, usually the licensed person rather than the company, but these pages show permit counts only: there are no contractor lists, rankings or firm pages for New Orleans.
  • The value is the project cost declared on the application. About a third of permits carry none, mostly small trade permits.
  • Gas permits (gas lines, water heaters and the six-month gas test after a home sits empty) are counted with plumbing; an electrical vacancy permit, needed to turn power back on in a home that sat empty, counts as electrical.
  • The city's file has a residential re-roofing permit type only from May 2025; before that few re-roofs appear in it, so the rise in roofing permits mostly reflects the new permit type, not more roofs.
  • A final date is the day the city recorded the permit as finaled or completed. Permits the city marks Closed count as finished but add no days, because the file does not say whether the work passed a final inspection.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "How long do permits take in New Orleans, LA?", https://contractorrecords.com/new-orleans/how-long-does-a-permit-take, data through September 2026, from the City of New Orleans Department of Safety and Permits building-permit records.

Link to a table: By kind of work · Each kind of permit.

Download the tables (CSV): Days to final by kind of work.

Common questions

  • What is the permit turnaround in New Orleans?From issue to final inspection, the usual permit takes 72 days (middle half 22 to 176 days), from 8,946 permits issued Oct 2024–Sep 2025. The wait to get a permit issued is not in this file; ask the city for its current review times.
  • Which permits finish fastest in New Orleans?Plumbing permits, at 41 days. The slowest are home addition permits, at 286 days. Bigger jobs take longer; so does work where the final inspection is easy to forget.
  • How many permits actually get finished in New Orleans?70% of the 13,725 permits issued Oct 2024–Sep 2025 have finished; under 1% expired without a final and the rest are still open.
  • Why does an open permit matter to me?An unfinished permit stays with the property, not the contractor. It can hold up a sale or a refinance. Ask whoever does the work to call for the final inspection and show you the result.