Roofing permits in New Orleans, LA

Data through September 2026 · updated 18 Oct 2026

1,777 roofing permits were issued in New Orleans, October 2024 through September 2026: about 888 a year and 6% of all permits. 1,276 roofing permits in the last 12 months (Oct 2025–Sep 2026), 155% more than the 501 in the 12 months before. The busiest month is September. The usual one took 111 days from issue to the city's final. 70122 has the most, 191.

1,777permits issued
1,276last 12 months
Sepbusiest month
111days, usual issue to final
52%finished
$35,542usual declared value
Sep 2026records through

Roofing permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 18Oct2024Nov 2024: 18Dec 2024: 13Jan 2025: 17Jan2025Feb 2025: 22Mar 2025: 22Apr 2025: 24May 2025: 59Jun 2025: 93Jul 2025: 72JulAug 2025: 62Sep 2025: 81Oct 2025: 139Nov 2025: 86Dec 2025: 53Jan 2026: 98Jan2026Feb 2026: 71Mar 2026: 110Apr 2026: 142May 2026: 139Jun 2026: 96Jul 2026: 109JulAug 2026: 103Sep 2026: 130
The same numbers as a table
MonthPermits
Oct 202418
Nov 202418
Dec 202413
Jan 202517
Feb 202522
Mar 202522
Apr 202524
May 202559
Jun 202593
Jul 202572
Aug 202562
Sep 202581
Oct 2025139
Nov 202586
Dec 202553
Jan 202698
Feb 202671
Mar 2026110
Apr 2026142
May 2026139
Jun 202696
Jul 2026109
Aug 2026103
Sep 2026130

Download this table (CSV)

When roofing permits are filed

By calendar month, 100 = an average month (the thin line). September is the busiest (142), December the quietest (45). A busy month at the permit counter usually means a longer wait for a contractor.

January: 78 (100 = an average month)February: 63 (100 = an average month)March: 89 (100 = an average month)April: 112 (100 = an average month)May: 134 (100 = an average month)June: 128 (100 = an average month)July: 122 (100 = an average month)August: 111 (100 = an average month)September: 142 (100 = an average month)142October: 106 (100 = an average month)November: 70 (100 = an average month)December: 45 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January78
February63
March89
April112
May134
June128
July122
August111
September142
October106
November70
December45

Download this table (CSV)

How long a roofing permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 251 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 2025501
Finished51.9%
Expired0.4%
Usual days, issue to final111
Middle half, days34–203

Download this table (CSV)

What a roofing permit is declared at

The value written on the permit at application, from 315 permits with one. Not a quote and not the final bill.

MeasureValue
Usual declared value$35,542
Middle half$17,990–$69,611

Download this table (CSV)

ZIP codes with the most roofing permits

Counted at the property's ZIP code. Share is the part of the city's 1,777 roofing permits.

ZIP codePermitsShare
7012219111%
7011517510%
701191589%
701171478%
701181428%
701241368%
701311297%
701261026%
70114925%
70128674%

Download this table (CSV)

The city's own permit types

How the city filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
Residential Re-Roofing1,40979%
Renovation (Non-Structural)23613%
Renovation (Structural)764%
Re-Roofing543%
Renovation (Structural or Non-structural)2under 1%

Download this table (CSV)

How New Orleans compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

How these numbers are made

Source: City of New Orleans, Permits - BLDS (data.nola.gov, dataset 72f9-bi28), read 18 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Residential permits the City of New Orleans Department of Safety and Permits issues inside the city, which is also Orleans Parish: building, renovation, re-roofing, electrical, plumbing, gas, HVAC, solar, pool, generator and demolition permits for single-family homes, two-family homes and doubles. Permits for buildings with three or more units and commercial property are not counted, nor are historic-district reviews, right-of-way permits (street cuts, driveways, sidewalks) and address changes in the same file. Jefferson, St. Bernard and St. Tammany parishes run their own permit offices and are not in this file.

  • The city's file lists a contractor on most permits, usually the licensed person rather than the company, but these pages show permit counts only: there are no contractor lists, rankings or firm pages for New Orleans.
  • The value is the project cost declared on the application. About a third of permits carry none, mostly small trade permits.
  • Gas permits (gas lines, water heaters and the six-month gas test after a home sits empty) are counted with plumbing; an electrical vacancy permit, needed to turn power back on in a home that sat empty, counts as electrical.
  • The city's file has a residential re-roofing permit type only from May 2025; before that few re-roofs appear in it, so the rise in roofing permits mostly reflects the new permit type, not more roofs.
  • A final date is the day the city recorded the permit as finaled or completed. Permits the city marks Closed count as finished but add no days, because the file does not say whether the work passed a final inspection.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Roofing permits in New Orleans, LA", https://contractorrecords.com/new-orleans/roofing-permits, data through September 2026, from the City of New Orleans Department of Safety and Permits building-permit records.

Link to a table: By month · Season · Days to final · Declared value · By ZIP code · Permit types.

Download the tables (CSV): Roofing permits by month · Roofing permits by calendar month (index) · Roofing permits: days to final · Roofing permits: declared value · Roofing permits by ZIP code · Roofing permits by permit type.

Common questions

  • How many roofing permits does New Orleans issue a year?About 888 a year in New Orleans: 1,777 permits issued October 2024 through September 2026, 1,276 of them in the last 12 months.
  • How long does a roofing permit take in New Orleans?The usual one took 111 days from issue to the city's final inspection, and the middle half took 34 to 203 days (251 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in New Orleans file the most roofing permits?September (142 against an average month of 100); December is the quietest (45). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.
  • Which ZIP code has the most roofing permits in New Orleans?70122, with 191 of the 1,777 (11%); then 70115 (175).